Two-stage comparison of requirement elements between interim settlement by construction stage and the final account (GB/T 50500-2024): timing, definition of completed works, payment percentage, price calculation, dispute handling and node division

Interim settlement by construction stage is the calculation, adjustment, confirmation and payment of the contract price for completed works at settlement nodes (term 2.0.34, also termed interim settlement, with nodes divided by month / quarter / year / physical progress); the final account is the consolidated settlement of the total price of the works after completion acceptance has passed and is the summary of the interim settlements by construction stage (2.0.35). Signed stage settlement documents form part of the final account documents and the final account does not re-measure or re-price them (10.2.3); only preliminaries and the main contractor's attendance and coordination provisions are interim payments that must be recalculated at final account stage (10.2.7, 10.3.3). The stage settlement payment percentage is no less than 80% of the total settlement amount for the current period (10.2.4); the final account has no percentage concept - it is closed out on the total price less retained retention money (cumulatively no more than 3% of the total settlement price of the works, 10.5.1), per formula 7 of clause 10.3.15.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.34、2.0.35、10.1.3、10.1.9、10.2.3、10.2.4、10.2.7、10.2.8、10.2.9、10.2.10、10.2.11、10.3.1、10.3.2、10.3.3、10.3.6、10.3.7、10.3.14、10.3.15、10.3.16、10.5.1、9.4.11条
  • GB 50500-2013 建设工程工程量清单计价规范 第11.3.2、11.3.3、11.4.2条
  • 财建〔2004〕369号 建设工程价款结算暂行办法 第十六条
  • 天津市建设工程计价办法(2025)第7.2、7.3节

Topic positioning

This card compares, under GB/T 50500-2024, the China national pricing standard for BOQ, the differences in requirement elements between the two settlement tiers - interim settlement by construction stage and the final account: timing, definition of completed works, pricing and payment treatment, dispute handling and the force of the resulting documents, and explains how stage settlement nodes are divided. It serves planning of contract settlement clauses, in-process measurement approval, and preparation and checking of the final account.

Core conclusions

1. Positioning of the two stages under chapter 2 terms

  • Interim settlement by construction stage (2.0.34): 'the activity in which the employer and the contractor, under relevant laws and regulations and the contract, calculate, adjust, confirm and pay the contract price for completed works at construction stage settlement nodes.' Also termed interim settlement.
  • Works settlement (2.0.35): covers 'interim settlement by construction stage, settlement on termination of the contract, the final account and settlement on expiry of the works warranty.' 'Interim settlement by construction stage is also termed interim settlement, and includes settlements by monthly, quarterly, annual and physical-progress nodes. Termination settlement is the settlement made where the contract is no longer performed. The final account is the settlement of the total price of the works made by the employer and the contractor per the contract once the works have passed completion acceptance, and is the summary of the interim settlements by construction stage.' The final account is composed level by level of the final accounts of unit works, individual works and the construction project.

2. How nodes are divided

Nodes are chosen from month, quarter, year and physical-progress nodes (2.0.35), and the contract fixes the nodes, procedure and method: 'where the contract provides for interim settlement by construction stage, the employer and the contractor shall carry out the measurement and payment of the relevant stage settlement per the nodes, procedure and method agreed in the contract' (10.1.3). The 2024 edition sets no fixed day counts - submission, checking and payment time limits are all expressed as 'the prescribed time' or 'the agreed time'; the 2013 edition prescribed day counts directly (see the time-limit row of the table below).

3. Requirement comparison table (GB/T 50500-2024; clause numbers in brackets)

Item Interim settlement by construction stage Final account
Timing During construction: when a contractually agreed settlement node is reached and the works of the node are complete, the contractor submits the stage settlement documents (10.1.3, 10.2.8); where the contract does not provide for stage settlement (no nodes agreed), this stage does not arise 'After completion of the works, the employer and the contractor shall, per the contract and clause 10.2.1 of this standard, and on the basis of all stage settlement documents signed and confirmed by both parties, prepare and check [the final account] within the agreed time' (10.3.1); marked by the works passing completion acceptance and the settlement of the total price of the works (2.0.35)
Definition of completed works Limited to completed works within the scope of the current settlement node; the submission must include 'the relevant quality-certification and other acceptance documents for the stage settlement items', including self-inspection quality certificates and process acceptance documents meeting the contract (10.2.8, 10.2.9); 'in-process acceptance does not replace completion acceptance and does not excuse or mitigate the contractor's rectification obligations for defects found at completion acceptance, and interim settlement by stage shall not affect the defects liability period or the quality warranty period' (10.2.9) Covers the entire content of the completed works, listed per the 13-item order of clause 10.3.2: (1) total price of the contract BOQ; (2) adjustment for errors and omissions in the BOQ; (3) adjustment of provisional sums; (4) adjustment of provisional prices (materials, specialist works); (5) adjustment of the main contractor's attendance and coordination provisions (main contract); (6) adjustment of dayworks; (7) adjustment for changes in costs; (8) adjustment for changes in laws, regulations and policies; (9) price increase or decrease from variations; (10) price of additional works; (11) claim amounts; (12) liquidated damages for non-performance per the contract; (13) other amounts. Signed stage settlement parts are not re-measured or re-priced (10.2.3), except preliminaries and the main contractor's attendance and coordination provisions, which must be recalculated per section 7.3, chapter 8 and section 8.5 for all costs contained in the completed works, including the adjustment of statutory safety provisions (10.2.7, 10.3.3)
Price calculation Calculated as 'the difference between the cumulative price of works completed up to the settlement node and the cumulative price already paid'; the payment application contains: (1) cumulative completed stage settlement amounts (costs of divisional and sub-divisional work items, preliminaries, other items including provisional sums, contract price adjustments, and calculable VAT, listed separately); (2) cumulative stage settlement amounts already paid; (3) total deductions for the current period (recovery of advance payments, recovery of progress payments already made, amounts deducted by the employer); (4) the stage settlement amount payable for the current period; provisional sums are listed separately for works, services and contract price adjustments that could not be fully foreseen or specified (10.2.10) The payment application contains: (1) the total final account price of the works; (2) cumulative amounts actually paid; (3) retention money to be retained (except where another form of quality assurance has been provided); (4) the final account amount actually payable. Formula: 'final account payable = final account total price - retention money to be retained - cumulative amounts actually paid earlier'; where another form of quality assurance is used, the retention money term in the formula is not calculated (10.3.15, formula 7)
Payment percentage Agreed in the contract; 'shall not be lower than 80% of the total stage settlement amount for the current period' (10.2.4) No 'percentage' concept; closed out as the settlement total price less retained retention money (10.3.15); retention money: 'the cumulative retention money retained, or the bond amount where a bond replaces the retention money, shall not exceed 3% of the total settlement price of the works'; where the contractor has provided performance security, no retention money shall be retained before completion, and where quality assurance guarantees or quality insurance are used, no further retention is allowed (10.5.1)
Dispute handling Where a party objects to a stage settlement and agreement cannot be reached through checking and consultation, the parties 'may resolve it by the dispute resolution methods of chapter 11 of this standard'; dispute review or mediation is preferred (10.1.9); after confirmation the contractor submits the payment application, and verification, issue and payment follow clause 10.3.16 (10.2.11); at the progress payment stage, where measurement and pricing of some BOQ items are disputed, the employer shall certify and pay the undisputed part (9.4.11) Where the review result raises no objection, both parties sign, seal and confirm the final account documents within the agreed time; where there are objections, 'the undisputed part shall be handled as a partial final account limited to the undisputed items per item 1 of this clause; the disputed part shall be resolved by consultation between the parties, and where consultation fails, the dispute resolution methods of chapter 11 of this standard may be applied' (10.3.7); where the employer requests supplementary documents or submits checking comments requiring amendment of the final account documents, the contractor supplements, amends and resubmits for review (10.3.6); where the employer fails to verify or issue the settlement payment certificate in time, the contractor's payment application is deemed approved and shall be paid at the amount stated in the application (10.3.16); quality objections are handled by situation: works already accepted at completion, or completed but not yet accepted yet put to premature use by the employer, follow the warranty provisions with settlement proceeding as usual; works completed but not accepted and not in use, and suspended or halted works, may have the disputed part tested and expert-assessed or handled per the decision of the quality supervision authority, with the undisputed part settled as usual (10.3.14)
Time-limit treatment The 2024 edition sets no fixed day counts; nodes, procedure and time limits are agreed in the contract (10.1.3, 10.2.8); the old 2013 treatment: the employer checks within 28 days of receiving the final account documents; where supplementation is needed, the contractor amends and resubmits within 28 days of receiving the checking comments (GB 50500-2013 clause 11.3.2); re-checking within 28 days of resubmission, and signature confirmation within 7 days if no objection (clause 11.3.3); within 7 days of receiving the settlement payment application the employer verifies and issues the payment certificate (clause 11.4.2) Same as the left column: checking, re-checking, confirmation and payment are all completed 'within the agreed time' (10.3.6, 10.3.7, 10.3.16); 'Interim Measures for the Settlement of Construction Project Payments' (Cai Jian [2004] No. 369), article 16, still provides: where the employer raises no opinion within the prescribed or agreed period after receiving the final account report and complete documents, it is deemed to have accepted them; where the contractor, overdue in providing complete documents, still fails to provide them or gives no clear reply within 14 days after being urged, the employer may review on the basis of the documents held, at the contractor's risk; the employer shall pay the settlement amount within 15 days of receiving the payment application and bears liability for breach if overdue
Force of the resulting documents Stage settlement documents signed and confirmed by both parties 'shall form part of the final account documents of the works, and the final account shall not re-measure or re-price them' (10.2.3); of these, preliminaries and the main contractor's attendance and coordination provisions are interim payments of the works price (which may be calculated proportionally), 'used only for calculating and paying stage settlement amounts and not as the basis for determining the final account price of the works'; at completion they are recalculated and increased or decreased accordingly (10.2.7, 10.2.3 commentary) The final account documents are the definitive documents fixing the total price of the works; once signed, sealed and confirmed by both parties, the final account is confirmed (10.3.7); stage settlement documents are not recalculated - only preliminaries and the main contractor's attendance and coordination provisions are recalculated (10.3.3)

4. Local implementation (same-approach example)

Tianjin 2025 construction works pricing measures, sections 7.2 and 7.3, implement the same approach: nodes and bases per the nine bases of 7.2.1; confirmed contract price adjustments enter the current stage settlement and are paid in the same period (7.2.2); signed stage settlement documents are folded into the final account without re-measurement or re-pricing (7.2.3); payment percentage no less than 80% (7.2.4); preliminaries and the main contractor's attendance and coordination provisions recalculated at the final account, with stage-settlement listings not used as the basis (7.2.6, 7.3.3); where the employer fails to check or raise checking comments in time it is deemed to have approved, and where the contractor neither confirms nor objects in time it is likewise deemed to have approved (7.3.4, 7.3.5).

Applicability boundaries

  • Applies to works contracts priced on a BOQ basis, such as building and municipal works; GB/T 50500-2024 is a recommended standard, 'the agreed contract prevails', and where interim settlement by construction stage is not agreed the stage does not arise.
  • Interim settlement by construction stage is not the same as progress payment: once a stage settlement is signed its measurement and pricing are locked in and it becomes part of the final account; progress payments are advances in nature.
  • Preliminaries and the main contractor's attendance and coordination provisions in stage settlements can never be carried straight into the final account; they must be recalculated over the full content of the completed works - the only 'must-recalculate' exception between the two stages.
  • The 2024 edition no longer prescribes fixed day counts such as 28 days; citing time limits must return to the contract; the 28-day / 7-day counts of the 2013 edition apply only to that edition or contracts incorporating it.
  • This card is only a synthesis of standard clauses and involves no amounts or settlement data of any specific project.

Further reading

  • GB/T 50500-2024, China national pricing standard for BOQ: chapter 2 terms 2.0.34 (interim settlement by construction stage), 2.0.35 (works settlement); chapter 10 'Works settlement and payment', clauses 10.1.3, 10.1.9, 10.2.3, 10.2.4, 10.2.7, 10.2.8, 10.2.9, 10.2.10, 10.2.11, 10.3.1, 10.3.2, 10.3.3, 10.3.6, 10.3.7, 10.3.14, 10.3.15, 10.3.16; clause 10.5.1 (retention money); clause 9.4.11 (progress payment disputes paid on the undisputed part).
  • GB 50500-2013, China national BOQ pricing code, chapter 11 'Final account and payment', clauses 11.3.2, 11.3.3, 11.4.2 (old fixed time limits).
  • 'Interim Measures for the Settlement of Construction Project Payments' (Cai Jian [2004] No. 369), article 16 (deemed acceptance, 14-day urging, 15-day payment).
  • Tianjin 2025 construction works pricing measures, sections 7.1.4, 7.2, 7.3 (local same-approach example).