Composition differences between interim settlement by construction stage and the final account: stage settlement on three elements plus a five-item payment application, the final account on 13 listed items (GB/T 50500-2024 clauses 10.2 / 10.3)

Interim settlement by stage prices at settlement nodes: its composition = the relevant contract sums within the total price for the period or node + the contract adjustments agreed by the parties, less contractor-cause liquidated damages (clause 10.2.1); the payment application follows the five items of clause 10.2.10 on 'cumulative completed price - cumulative paid - current deductions'. The final account is compiled per clause 10.3.2 as 13 items in order (contract BOQ total - BOQ errors, provisional sums, provisional prices, main contractor's attendance, dayworks, price fluctuation, law and policy changes, variations, additional works, claims, damages, others). Stage settlement files signed by both parties form part of the final account and are not re-measured or re-priced (clause 10.2.3) - only preliminaries and the main contractor's attendance provisions are recomputed per clause 10.3.3.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.13、2.0.34、2.0.35条
  • GB/T 50500-2024 第10.2.1、10.2.3、10.2.5、10.2.6、10.2.7、10.2.10条
  • GB/T 50500-2024 第10.3.1、10.3.2、10.3.3、10.3.4、10.3.15条
  • GB/T 50500-2024 第7.3节、Ch. 8、第8.5节、第8.3.5条

Positioning

Comparing the two settlement compositions of GB/T 50500-2024: clause set 10.2 (interim settlement by construction stage) and 10.3 (the final account) - which cost items each holds, how adjustments and provisional sums are treated, the deductions, and the lock-in versus recomputation relationship between them.

Core conclusions

1. How they relate (terms 2.0.34, 2.0.35)

  • Interim settlement by construction stage: the activity of computing, adjusting, confirming and paying the contract price at stage-settlement nodes per law and contract - monthly, quarterly, annually or by physical-progress nodes.
  • Works settlement: computing, adjusting, confirming and paying during implementation, on termination and after completion - comprising interim settlements, termination settlement, the final account and post-warranty closure.
  • Final account: after passing completion acceptance, the total-price settlement under the contract - the roll-up of the interim settlements, built unit works -> single projects -> project.

2. Stage settlement composition Clause 10.2.1 closing: the stage settlement includes the relevant contract sums in the total price for the period or node, the contract adjustments determined by the parties, and the deduction of contractor-cause liquidated damages per the contract. Nine bases in the same clause: 1) the contract and supplements (with the priced BOQ and bid clarifications); 2) this standard and the national / industry measurement standards; 3) contract and as-built drawings and survey / design data; 4) the specification and the employer's supplementary technical specifications; 5) bid and tender documents; 6) approved or confirmed variations, dayworks, claims; 7) quantities and prices confirmed for the current stage; 8) contract adjustments confirmed for the current stage; 9) other bases.

3. The five-item payment application (clause 10.2.10) 1 Cumulative completed interim settlement amounts: 1) cumulative completed work-item costs; 2) cumulative completed preliminaries; 3) cumulative completed other-item costs (including provisional sums for works and services not fully foreseeable or detailed under term 2.0.13); 4) cumulative completed contract-price adjustments; 5) cumulative VAT. 2 Cumulative paid interim settlement amounts. 3 Current deductions: 1) advance recovery; 2) recovery of progress payments made; 3) employer deductions. 4 Current payable interim settlement amount. Rule: the difference of cumulative completed and cumulative paid price to the node; provisional sums are listed separately for unforeseeable works / services and for price adjustments.

4. Interim treatment of preliminaries and attendance

  • Preliminaries (10.2.5): by the agreed payment breakdown; absent one, by the share of the stage's work-item list total in the contract's work-item total x the contract preliminaries total.
  • Main contractor's attendance and coordination provisions (10.2.6): by the confirmed cumulative price of the specialist subcontract works / its contract price x the adjusted attendance total per clause 8.5; employer-supplied materials and directly-let specialist works follow the specialist pricing method.
  • Limits (10.2.7): the two serve only to compute and pay interim amounts, not as the basis of the final account; after completion they are recomputed per the contract and adjusted up or down.

5. The final account's 13 items (clause 10.3.2, in order) 1 contract BOQ total; 2 BOQ errors adjustment; 3 provisional sums adjustment; 4 provisional price adjustments: 1) materials, 2) specialist works (general-contract projects); 5 attendance adjustments (general-contract projects); 6 dayworks adjustment; 7 price-fluctuation adjustment; 8 law / policy change adjustment; 9 variations; 10 additional works; 11 claims; 12 liquidated damages for non-performance; 13 others. This is the composition of the final account total, for compiling comparable cost indicators and estimates.

6. Lock-in rules

  • 10.2.3: save as 10.2.7 provides, interim settlement files signed by both parties form part of the final account and are not re-measured or re-priced; preliminaries and attendance may adjust per 10.3.3.
  • 10.3.1: after completion, the parties compile, reconcile and conclude the final account per the contract, 10.2.1, and all signed interim files; absent other agreement, interim amounts are the basis of the final account.
  • 10.3.3: preliminaries and attendance are recomputed at the final account - preliminaries per clauses 7.3 and chapter 8 for all completed preliminaries, including adjustments of the statutory safety provisions; attendance per clause 8.5 over all specialist subcontracts, directly-let specialist works and employer-supplied materials; the interim amounts of these two are not the basis.
  • 10.3.4: the contractor completes the quality-acceptance evidence and submits the full final account file on the basis of the confirmed interim settlements.

7. Provisional sums at settlement (clause 8.3.5) With no adjustment event occurring, the provisional sums in the total price are deducted in full at settlement; with events, declared, verified, determined and paid per chapter 8. Sums for not-yet-defined works or services are computed from the works actually demanded by the employer; undemanded parts are deducted at the final account.

8. Final payment (clause 10.3.15) The application: 1 total final account; 2 cumulative actually paid; 3 retention to be held (other quality security excepted); 4 amount payable. Payable = total - retention - cumulative paid; with other security, retention is not computed.

9. Summary table

Dimension Stage settlement (10.2) Final account (10.3)
Object Completed works to the node (cumulative) The whole contract works
Composition 10.2.1 three elements + 10.2.10 five items 10.3.2 thirteen items
Preliminaries / attendance 10.2.5/10.2.6 pro-rata, interim 10.3.3 recomputed in full
Adjustments Confirmed per period, cumulative Listed by cause
Provisional sums In other items, split Deducted in full if unused
Deductions Advance and progress recovery, employer deductions Retention, cumulative paid
Effect Signed -> part of final account, not re-measured (partial lock-in) Total price finalised (roll-up + two recomputations)

Applicable boundaries

  • For BOQ-priced works under GB/T 50500-2024; other contractual arrangements govern (10.3.1 "save as the contract provides").
  • The lock-in binds only files signed by both parties; one-sided drafts lock nothing.
  • Lock-in is partial: preliminaries and attendance are interim amounts recomputed at the final account, including statutory safety provision adjustments.
  • Full deduction of provisional sums presupposes "no adjustment event" or "not demanded by the employer"; events processed under chapter 8 adjust rather than deduct.
  • A recommended national standard - rules bind through contract reference; conflicts resolve per the contract and industry rules.
  • This card maps compositions; payment ratios, time limits and amounts follow chapter 9 and clauses 10.3.8/10.3.10.

Further reading

GB/T 50500-2024 terms 2.0.13, 2.0.34, 2.0.35; clauses 10.2.1, 10.2.3, 10.2.5~10.2.7, 10.2.10, 10.3.1~10.3.4, 10.3.15; clause sets 7.3, 8, 8.5, 8.3.5.