Interim payment and final settlement of preliminaries: statutory safety provisions prepayment and recovery points (9.3.2 - at least 50% within 28 days of commencement), progress-payment methods (9.4.4 - agreed breakdown or element-works ratios), the three-stage preliminaries breakdown table (6.2.13, Appendix E Table E.3.3), interim versus final settlement (10.2.7, 10.3.3) and the three-class treatment in settlement review

Statutory safety provisions prepay at not less than 50% of the total within 28 days of commencement, the rest decomposed per the early-arrangement principle and paid with progress payments; computing progress payments never recovers the prepayment - it is recovered once at the final account (9.3.2). Preliminaries progress payments follow the parties' agreed breakdown; absent agreement, by the ratio of cumulative completed work-item list value to the work-item list total, the breakdown resting on Appendix E Table E.3.3 (initial set-up / mid-term running / late dismantling, 6.2.13, 9.4.4). Preliminaries listed in interim settlements serve only interim payment (10.2.7); the final account recomputes all preliminaries of the completed works per clause set 7.3 and chapter 8, including safety-provision adjustments - interim figures are no basis (10.3.3).

Applicable Codes

  • GB/T 50500-2024 第6.2.13条(措施项目费用分拆表)
  • GB/T 50500-2024 第9.3.2条(安全生产措施费预付与扣回)
  • GB/T 50500-2024 第9.4.4条(措施项目进度款)
  • GB/T 50500-2024 第10.2.7条(过程结算措施费不作为竣工结算依据)
  • GB/T 50500-2024 第10.3.3条(竣工结算措施费重新计算)
  • GB/T 50500-2024 第3.2.5条(安全生产措施费不可竞争)
  • GB/T 50500-2024 App. E Table E.3.3(措施项目费用分拆表)
  • T/ZBD 100.5-2023 第3.1.6条(固定单价结算审核中措施项目费的调整口径)

Positioning

The two money points of preliminaries: interim payment (prepayment, progress payments, breakdown) and the final account (the standing of interim preliminaries, recomputation). Basis: GB/T 50500-2024 clauses 6.2.13, 9.3.2, 9.4.4, 10.2.7, 10.3.3 and the settlement review guide - 'how much, how computed, recoverable, recomputed?'.

Core conclusions

1. The technical base of breakdowns: the preliminaries breakdown table (6.2.13)

Tenderers submit with their bids a breakdown per Appendix E Table E.3.3 stating each item's initial set-up, mid-term running and late dismantling costs; the table serves chapter 8 claim pricing and chapter 9 progress payments. Without it, duration-change pricing (8.9.4, multiplying by 'mid-term running costs') and payment breakdowns lose their quantitative base.

2. Prepayment and recovery of statutory safety provisions (9.3.2)

'The employer shall prepay not less than 50% of the statutory safety provisions within 28 days of commencement; the rest is decomposed per the early-arrangement principle and paid with progress payments. For major works spanning years, the prepaid total may be decomposed by the annual programme. Progress payments shall not recover the prepayment.' Recovery comes once at the final account. Statutory safety provisions are non-competitive (3.2.5), priced per state and provincial / sectoral rules.

3. Preliminaries progress payments (9.4.4)

By the agreed breakdown; absent agreement, 'by the ratio of cumulative completed work-item list value to the work-item list total'. The breakdown may follow 6.2.13 / Table E.3.3. Safety-provision progress payments follow the contractual decomposition; absent one, the same ratio x 'the total net of the prepayment'. Practice: preliminaries are mostly lump-sum 'per item' without physical quantities - only agreed breakdowns or element-works ratios; both bases belong locked in the particular conditions, else monthly disputes.

4. Interim versus final settlement (10.2.7, 10.3.3)

10.2.7: preliminaries (10.2.5) and attendance (10.2.6) 'serve only to compute and pay interim settlement amounts, not as the basis of the final account'; at completion they are recomputed per contract and adjusted up or down. 10.3.3: at the final account the parties recompute both - 'preliminaries per clause sets 7.3 and chapter 8 for all preliminaries of the completed works, including statutory safety-provision adjustments; interim-listed preliminaries are no basis'. Recomputation means re-running clause 7.3 measurement and chapter 8 adjustments (variations, BOQ errors, policy changes) - interim settlements remain process payment vouchers. Note: recomputation never reopens the bid - items bid at zero stay zero; 10.3.3 is no recovery ground.

5. Three-class treatment in settlement review (T/ZBD 100.5-2023 clause 3.1.6)

Where the contract is silent:

  1. preliminaries tied to physical work items (formwork, scaffolds): quantities adjust with the work items, priced at contract rates;
  2. competitive independent preliminaries (slope protection, dewatering, retention, temporary roads, hoarding): per contract or the original bid, not linked to quantities;
  3. project-wide rate- or scheme-based preliminaries (mandatory HSE provisions, vertical transport, super-height additions): on the regulated base and the bid rate or detail. Contractual agreements on items and pricing prevail over the guide.

Applicable boundaries

  • For BOQ-priced works under GB/T 50500-2024; a recommended standard - particular conditions on ratios and breakdowns prevail.
  • 50% is a floor - contracts may prepay more; multi-year works may decompose by annual programme.
  • Recomputation presupposes reviewable evidence (approved variation schemes, Table E.3.3, records, policy files) - evidence-free 'recomputation' merely copies the interim figures.
  • Railway, highway and water works have their own safety-fund rules (possibly on-actuals, no lump sum).
  • The three-class guide is a team standard yielding to contract.

Further reading

  • GB/T 50500-2024: 6.2.13 and Appendix E Table E.3.3; clause set 9.3; 9.4.4; 10.2.5~10.2.7; 10.3.3; 3.2.5.
  • T/ZBD 100.5-2023 clause 3.1.6; companion cards on progress payments, prepayments and safety funds.