Dividing price and quantity gaps of employer-supplied (free-issue) materials: price gaps to the employer and outside the contractor's adjustment scope, quantity gaps bounded by the effective wastage rate, custody and freight splitting at the delivery point with unloading (GB/T 50500-2024 clauses 3.6.1, 3.2.4, 3.6.3, 6.2.4, 8.7.5; against GB 50500-2013 clause 3.2.1)
Price gaps are the employer's and never enter the contractor's adjustment: 3.6.1 - 'at bidding, the prices of employer-supplied materials do not enter the all-in unit rates'; 3.2.4 - 'the material cost of employer-supplied materials does not enter the work-item list'; 8.7.5 - 'the material adjustments of 8.7.2~8.7.4 are not suited to employer-supplied items... adjustable by the employer on actual changes but not listed in the contract total' - the gap between actual purchase and contracted prices is the employer's own, forming no contractor adjustment income and no downward contract revision. Quantity gaps split at the effective wastage rate: contractor-caused over-draws are borne by the contractor per 3.6.3, clawed back at supply-contract prices from interim or final payments; within the rate, and employer-caused excesses (specification mismatch pushing wastage beyond the rate; employer-caused over-draws), fall on the employer. Custody and freight split at 'delivered to the delivery point and unloaded': before, the employer's (6.2.4 - bid rates exclude those costs); after, site custody, double handling and own installation wastage are the contractor's, coordination and custody services charged to the employer in attendance provisions (3.6.4).
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第3.6.1条
- GB/T 50500-2024 第3.6.2条
- GB/T 50500-2024 第3.6.3条
- GB/T 50500-2024 第3.6.4条
- GB/T 50500-2024 第3.6.5条
- GB/T 50500-2024 第3.6.6条
- GB/T 50500-2024 第3.2.4条
- GB/T 50500-2024 第3.3.5条
- GB/T 50500-2024 第3.7.4条
- GB/T 50500-2024 第6.2.4条
- GB/T 50500-2024 第8.5.2条
- GB/T 50500-2024 第8.7.5条
- GB/T 50500-2024 App. G.1 Table G.1.1 发包人提供材料一览表
- GB/T 50500-2024 App. G.2 Table G.2.1-1/Table G.2.1-2 承包人提供可调价主要材料表
- GB 50500-2013 第3.2.1条(已被GB/T 50500-2024替代)
- GB 50500-2013 第3.2.3条(已被替代)
- GB 50500-2013 第3.2.4条(已被替代)
- GB 50500-2013 第10.3.5条(已被替代)
- T/ZBD 100.4-2023 建设工程造价鉴定作业指引 第4.5.7条
Positioning
Attributing price and quantity gaps of free-issue materials (employer supplies, contractor installs): why price gaps stay out of the contractor's adjustment, how the effective wastage rate cuts quantity gaps, and where custody and freight divide. For BOQ-priced free-issue disputes (recovery procedure in the companion card).
Core conclusions
1. Price gaps: the employer's own, outside contractor adjustment
- Prices stay out of the bid - 3.6.1: 'The employer states the quality and delivery terms of its materials in the tender documents; at bidding their prices do not enter the all-in unit rates. Materials not meeting the contract or delivery terms changed for employer reasons - the employer bears the added cost and / or delay and pays reasonable profit.' The clause also requires the tender documents to name, grade, specify and locate the materials and to describe them in the item descriptions.
- The material cost stripped wholesale - 3.2.4: 'items of employer-supplied material installed by the contractor include in their rates the contractor's own installation wastage but not the material price, the wastage borne by the employer per Appendix G.1 Table G.1.1, or the attendance provisions'; 'the material cost does not enter the work-item list, but installation costs are computed... excluding delivery and unloading to site and the wastage share of Table G.1.1'.
- Exclusion - 8.7.5: 'The material adjustments of 8.7.2~8.7.4 are not suited to employer-supplied and provisionally priced items. Employer-supplied items may be adjusted by the employer on actual changes but not listed in the contract total; provisionally priced items follow 8.4.' With 3.3.5 item 2 (the adjustable-material tables of Appendix G.2 cover contractor-supplied materials only - free-issue never appears there) and item 4 (adjustments carry VAT only, never overheads or profit).
- Landing: purchase above the contracted free-issue price touches only the employer's own cost - no contractor income; below, the employer neither revises the contract down nor seeks refund; free-issue materials take no part in Appendix A adjustment.
- 2013 contrast (superseded; legacy reference) - 3.2.1: 'at bidding, free-issue unit prices enter the all-in unit rates; after award the employer deducts the free-issue amounts per contract, unpaid'; 10.3.5: 'deducted from progress payments at the signed unit prices and quantities'. The recovery base is locked to the signed price - the employer digests its own over-purchase and never passes it on; under-purchase yields no refund to the contractor.
2. Quantity gaps: the effective wastage rate
- Main line (3.6.3): 'Where through contractor fault the drawn quantities exceed the drawing-derived actual quantities (unit-rate contracts) or reasonable quantities (lump-sum contracts) plus the contractual effective wastage, the excess material cost is the contractor's, computed by the employer at supply-contract prices and deducted from interim or final payments.' Over-draw = drawn (variations excluded) - drawing-derived x (1 + effective wastage); priced at supply-contract prices (the employer's purchase), never list or published prices.
- The rate is the employer's to set (3.6.2): 'The employer states the effective wastage rates in the tender documents, reasonably from similar works, and completes Appendix G.1 Table G.1.1, quantities per the tender drawings and the national / industry measurement standards.' That quantity caps the contractor's usable amount.
- Employer-borne gaps: (1) specifications differing from the tender, pushing actual wastage beyond the effective rate - the excess is the employer's; (2) employer-caused over-draws - the extra wastage is the employer's (3.6.3).
- Over-supply, one of two routes in the settlement agreement: return (unused excess returned with formalities, never entering settlement) or transfer (retained at supply-contract prices, the cost a deduction only, never contractor income).
- Under-supply: 3.6.5 - non-conforming or off-schedule delivery, delays, changed place or manner: the contractor helps withdraw and replace; 'any extension runs under chapter 8, with losses including profit compensated'. 2013 clause 3.2.3 the same.
- Mode switches (the right road for price treatment): free-issue to contractor purchase (3.6.6) needs the contractor's written consent (reasonable objection allowed); prices 'by joint tendering or market enquiry'; the corrected rate = the priced-list installation rate + material (with reasonable wastage) + overheads and profit, attendance reduced per 8.5. Contractor to free-issue (3.7.4): deduct material and custody costs, other costs unchanged, the remainder the installation rate, VAT of deductions reversed, attendance paid per 8.5.2.
- Quantity disputes: 2013 clause 3.2.4 - 'settled per the consumption of like items in the pricing quotas'; assessment (T/ZBD 100.4-2023 clause 4.5.7): fix actual consumption from drawings and quotas, verify purchases, issues, returns and stock; consumption = issues - stock; excess issues return or deduct per contract; late supply priced on the employer-representative's confirmation sheets.
3. Custody and freight: the delivery point (with unloading)
- 6.2.4: 'bid rates and totals exclude the supplier's costs of delivering and unloading at the delivery point'; installation bids cover 'receiving at the delivery point through to fixing in position, including on-site double handling and the bidder's own over-consumption'.
- The divide: freight and purchasing-custody before delivery and unloading are the employer's (procurement follows the purchaser; 2024 strips them from the rates); after, site custody, double handling and own installation wastage are the contractor's, inside the installation rate.
- 3.6.4: the contractor plans deliveries per the progress programme, helps coordinate delivery and unloading to the contracted point, and conducts acceptance with the supplier; 'coordination and custody services for employer-supplied materials are borne by the employer, chargeable in attendance provisions'. The acceptance record starts the quantity reconciliation.
Applicable boundaries
- For BOQ-priced free-issue price and quantity attribution; presupposes names, grades, specifications, delivery terms and effective wastage stated in the tender documents and described in the item descriptions (3.6.1, 3.6.2).
- Never mix editions: 2013 (prices inside rates, full recovery at signed prices) is superseded by 2024 (stripped, only contractor-fault over-draws recovered); the test is the standard cited at contract plus particular terms.
- 8.7.5 excludes only the 8.7.2~8.7.4 adjustments; free-issue may still adjust on the employer's actual changes, outside the total. Express contract or local rules (pre-tax cost bases) prevail.
- Absent a stated effective rate, never judge over-supply by raw issues - fix a reasonable rate per 3.6.2 or resolve by assessment.
- This card fixes attribution; recovery procedure, deduction bases, payment columns and VAT bases sit in the companion cards.
Further reading
GB/T 50500-2024 clauses 3.6.1~3.6.6, 3.2.4, 3.3.5, 3.7.4, 6.2.4, 8.5.2, 8.7.5; Appendix G.1 Table G.1.1 and Appendix G.2 Tables G.2.1-1/-2; GB 50500-2013 clauses 3.2.1, 3.2.3, 3.2.4, 10.3.5 (superseded, legacy reference); T/ZBD 100.4-2023 clause 4.5.7.