Engineering Knowledge Cards.
Confidence HighUpdated 2026-11-11

The price-taking order for deducting employer-supplied materials where the contract is silent: fix the 2013 / 2024 pricing basis first, then descend supply-contract unit price -> the signed Schedule of Employer-Supplied Materials -> the parties' pre-purchase confirmed price -> the Civil Code statutory fallback, with the price and quantity rules of cost expert assessment

Silence never means a blanket published price or market price. Under GB/T 50500-2024 (free-issue prices never enter the all-in rate, clause 3.6.1) the deduction price takes first the unit price of the corresponding supply contract (clause 3.6.3), deducting only the contractor-fault over-draw; under GB 50500-2013 (free-issue prices already in the rate, clause 3.2.1) recovery runs in full at the unit price of the signed Schedule of Employer-Supplied Materials and Equipment x quantity (clause 10.3.5). Next the parties' pre-purchase confirmed price (2024 Appendix A clause A.2.5, silence in time deeming approval; GB/T 51262-2017 clause 5.6.4(1)); unreported purchases take the contractual price (item 2 of the same clause); only a wholly missing evidence chain falls to Civil Code Article 510 (supplementary agreement, related terms or trade usage) and Article 511(2) - 'the market price at the place of performance when the contract was concluded', with the assessment fallback per T/ZBD 100.4-2023 clause 3.1.6's three routes. Quantity runs its own basis: actual consumption = issues - stock (T/ZBD 100.4-2023 clause 4.5.7); the 2013 basis takes the consumption of like items in the pricing quotas (2013 clause 3.2.4).

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 第3.6.1条
  • GB/T 50500-2024 第3.6.2条
  • GB/T 50500-2024 第3.6.3条
  • GB/T 50500-2024 第3.2.4条
  • GB/T 50500-2024 第6.2.4条
  • GB/T 50500-2024 App. A 第A.2.5条
  • GB/T 50500-2024 App. G.1 Table G.1.1
  • GB 50500-2013 建设工程工程量清单计价规范 第3.2.1条
  • GB 50500-2013 第3.2.4条
  • GB 50500-2013 第10.3.5条
  • GB 50500-2013 App. L.1
  • GB/T 51262-2017 建设工程造价鉴定规范 第5.6.4条
  • T/ZBD 100.4-2023 建设工程造价鉴定作业指引 第3.1.6条
  • T/ZBD 100.4-2023 第4.5.7条
  • 中华人民共和国民法典 第五百一十条
  • 中华人民共和国民法典 第五百一十一条第(二)项
  • 法释〔2020〕25号 建设工程施工合同纠纷案件适用法律问题的解释(一)第十九条

Positioning

When the construction contract fixes no deduction price for employer-supplied (free-issue) materials, in what order the price basis is chosen, on what basis quantity verifies, and how the cost expert assessment handles it. The full path: fix the pricing edition, walk the evidence chain, fall back to statute.

Core conclusions

1. The precondition: fix the nature of the deduction - the two editions never mix

  • GB 50500-2013 clause 3.2.1: 'at bidding, free-issue unit prices enter the all-in rates of the items; after award the employer deducts the free-issue amounts per contract, unpaid.' - recovery in full along the same path, at the very price bid into the rates: the unit price of the signed Schedule of Employer-Supplied Materials and Equipment (Appendix L.1, naming material, specification, quantity, unit price, delivery terms and place). Clause 10.3.5: 'the free-issue amounts deduct from progress payments at the employer's signed unit prices and quantities, listed in the period's deductions.' Bid at that price, deduct at the same price - never bid low and deduct high.
  • GB/T 50500-2024 clause 3.6.1: 'at bidding, the prices of employer-supplied materials do not enter the all-in rates.' Clause 3.2.4: free-issue material costs stay out of the work-item list, installation items carrying installation only, 'excluding the prices of employer-supplied materials, the wastage borne by the employer per Appendix G.1 Table G.1.1, and the matching attendance provisions'. - no full recovery exists; only the clause 3.6.3 deduction of contractor-fault over-draws.
  • Carrying 'full recovery at the signed price' into the 2024 basis deducts material cost twice off a price already stripped of it - the classic error. The test is the pricing standard cited at contracting; 2013 serves only contracts signed under it.

2. The price-taking order (the core)

1. First: the unit price of the corresponding supply contract (2024). The employer's own purchase contract price - not the BOQ rate, not the published price information, not the market price. Clause 3.6.3 verbatim: 'where through contractor fault the drawn quantities exceed the drawing-derived actual (unit-rate) or reasonable (lump-sum) quantities plus the contractual effective wastage, the excess material cost is the contractor's, and the employer may compute the over-drawn cost at the corresponding supply contract's unit price and deduct it from interim or final payments.'

2. Second: the unit price in the tendered / signed Schedule of Employer-Supplied Materials (the lawful recovery basis under 2013; under 2024, the reconciliation base). Basis: 2013 clauses 3.2.1 and 10.3.5; 2024 clause 3.6.2 - the employer states the effective wastage rates in the tender documents and completes Appendix G.1 Table G.1.1, quantities per the tender drawings and the national / industry measurement standards.

3. Third: the price confirmed / agreed by both parties before purchase.

  • 2024 Appendix A clause A.2.5 verbatim: 'where the employer-recognised purchase price serves as the period market price, the contractor submits quantities and unit prices before purchase; the employer checks and confirms within the agreed time and computation follows the confirmed price, batches weighted; employer silence past the period may be deemed approval and grounds for adjustment.' - silence deems approval, closing the 'employer refuses after the fact'.
  • GB/T 51262-2017 clause 5.6.4 (expert assessment): price disputes go to the commissioning party's decision; absent a timely decision - (1) 'prices approved or signed by the employer or its representative before purchase are assessed at those prices'; (2) 'purchases never submitted for quality and price approval are assessed at the contractual price'; (3) quality-based refusals assess at the agreed price, quality disputes going to separate quality appraisal. In short: purchase prices and invoices prove only what was spent - without the confirmation procedure they never rise to a deduction basis.

4. Only a wholly missing chain falls to statute.

  • Civil Code Article 5510: gaps are filled by supplementary agreement, then related contract terms or trade usage - never a jump straight to market price.
  • Article 511(2): price unclear - 'the market price at the place of performance when the contract was concluded'; government-priced items follow those rules. The fallback moment is contracting and the place is performance - not the dispute date, not the project-location published prices.
  • Fa Shi [2020] No. 25 Article 19: agreed standards govern; design changes leaving price unagreed may settle on the local standards current at contracting.
  • Assessment fallback (T/ZBD 100.4-2023 clause 3.1.6): with no agreed price or determination principle, the appraiser agrees the method with the commissioning party by - (1) fair market prices from its own survey on professional judgement; (2) the applicable sector or local pricing quotas; (3) audited direct-cost data combined with market indirect levels.

3. Quantity (price fixed - how the amount verifies)

  • 2024: unit-rate over-draw = issues - drawing-derived actual x (1 + effective wastage); lump-sum = issues - drawing-derived reasonable x (1 + wastage); 'the drawn quantities exclude variations' - variation parts price as variations. Fault exceptions: employer-supplied specifications differing from the tender, pushing wastage beyond the effective rate - the excess is the employer's; employer-caused over-draws likewise.
  • 2013 (clause 3.2.4): 'quantity disputes unresolved compute on the material consumption of like items in the pricing quotas.'
  • Assessment (T/ZBD 100.4-2023 clause 4.5.7): fix actual consumption from the drawings and the consumption quota (rate build-up detail), then verify purchases, issues, returns and stock; 'verified actual consumption = issues - stock'; excess issues return with formalities or deduct per contract; late supply confirmed by the employer's representative prices on the confirmation sheets, consumption as above.
  • Price and quantity disputes run apart on different bases - never one rule for both.

Applicable boundaries

  • For BOQ-priced free-issue deduction disputes; express contractual prices or methods govern, this order serving only where silent or unclear (Civil Code Articles 510, 511; Fa Shi [2020] No. 25 Article 19).
  • The editions never cross: 2013 (into the rates, full recovery) and 2024 (stripped, over-draw only) - mixing them double-deducts or under-deducts.
  • 'Supply-contract unit price' is the employer's purchase contract price - neither the BOQ rate, nor the published price information, nor the contractor's bid enquiry.
  • Not for: free-issue turning contractor-purchased (prices by joint tender or enquiry, the corrected rate adding material, overheads and profit to the installation rate); provisional-price adjustment after confirmation (clause set 8.4); ordinary price-adjustment bands (clause 8.7.2 with Appendix A).
  • The fallback 'market price at contracting at the place of performance' remains an assessment basis - fix it through the confirmation procedure or an appraisal opinion, never straight off invoices.

Further reading

GB/T 50500-2024 clauses 3.6.1-3.6.3, 3.2.4, 6.2.4 (bid installation scope and the delivery-point cost divide), Appendix A clause A.2.5, Appendix G.1 Table G.1.1; GB 50500-2013 clauses 3.2.1, 3.2.4, 10.3.5, Appendix L.1 (superseded, legacy contracts only); GB/T 51262-2017 clause 5.6.4; T/ZBD 100.4-2023 clauses 3.1.6 and 4.5.7; Civil Code Articles 510 and 511(2); Fa Shi [2020] No. 25 Article 19.