Impairment risk assessment for projects completed but long unsettled: a two-step method of recoverable amount measurement and aging matrix

Two-step impairment assessment for completed-but-unsettled projects: individually, recoverable amount = expected settlement amount × (1 − expected reduction rate) ÷ (1 + discount rate)^(expected recovery years), providing for the shortfall below carrying amount; in bulk, provide by aging matrix (>3 years at 50% is a common reference). Link with the legal levers of "deemed acceptance upon overdue silence + limitation-period interruption + overdue interest" to compress the impairment exposure.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • 企业财务通则(财政部令第4号)
  • 企业会计准则(财政部令第5号)
  • 中华人民共和国民法典
  • 保障中小企业款项支付条例(国务院令第728号)
  • DB42/T 823-2021 建设工程造价咨询质量控制规范

Topic Positioning

Impairment risk assessment for a construction enterprise's projects completed but long unsettled: first classify the asset, then provide for impairment by the two-step method of "individual recoverable amount measurement + aging matrix portfolio provision", linked with legal levers — deemed acceptance of settlement, limitation periods — to compress the exposure.

Core Conclusions

  1. Asset classification sets the risk tier: settlement submitted but unverified → contract assets (double exposure to reduction and recovery); verified but uncollected → accounts receivable; settlement not even submitted → contract assets + inventory, highest risk.
  2. Impairment indicators (any one triggers testing): the employer neither replies nor verifies beyond the agreed period (28 days absent agreement); employer financial deterioration/litigation/bankruptcy; a high reduction ratio (e.g., >10%); quality or schedule disputes; government funds not in place; aging over 1 year without written commitment.
  3. Two-step method: individual assessment — recoverable amount = expected settlement amount × (1 − expected reduction rate) ÷ (1 + discount rate)^(expected recovery years); provide for the shortfall below the carrying amount; portfolio provision — aging matrix (≤1 year 5%, 1–2 years 10%, 2–3 years 20%, >3 years 50% as common references, rates set by the enterprise's accounting policy; overdue beyond 3 years unrecoverable may be a bad debt loss, General Rules on Enterprise Finance, Article 13).
  4. Legal linkage: overdue silence deemed acceptance (GB/T 50500-2024 Clause 10.3.8 etc.); the 3-year limitation period needs demand letters to interrupt it (Civil Code, Article 188); overdue interest at the 1-year LPR or 0.05‰ per day (Regulation on Ensuring Payment to SMEs, Article 15).

Applicable Boundaries

Applies to impairment assessment of contract assets and receivables of completed-but-unsettled/uncollected projects; individual assessment for large amounts, the aging matrix for bulk small/medium amounts. Reduction and discount rates are estimated from the employer's history and dispute intensity; aging percentages are references, not mandates. Not applicable to: in-construction projects (normally reported as contract assets), claims already in bankruptcy liquidation, and projects under audit (see the related card for the settlement evidence priority).

Further Reading

GB/T 50500-2024 Clauses 10.3.6–10.3.11 (final account submission-verification-recheck-confirmation closed loop) and Clause 10.5.1 (retention ≤3%); General Rules on Enterprise Finance (Ministry of Finance Order No. 4), Article 13 (bad debt loss determination); Accounting Standards for Business Enterprises (Ministry of Finance Order No. 5), Article 27 (bad debt provisions); Civil Code, Article 188; Regulation on Ensuring Payment to SMEs (State Council Order No. 728), Article 15; DB42/T 823-2021 Clauses 8.3.6, 8.3.8 (final account review and tri-party sign-off).

Keywords

  • 减值评估
  • 坏账准备
  • 合同资产
  • 可收回金额
  • 账龄分析
  • 未结算
  • 应收账款
  • 工程款回收