Four-basis accounting for construction enterprises: computing and reporting construction in progress, completed-but-unsettled, settled-but-unfinished, and contract liabilities

Construction in progress belongs to the cost basis (counted month-end, valued by the equivalent-production or process-proportion method and carried forward to the next period); completed-but-unsettled = cumulative recognized revenue minus cumulative settled price (positive difference, presented as a contract asset); settled-but-unfinished = cumulative settled price minus cumulative recognized revenue (positive difference, presented as a contract liability); contract liability = advance project payments plus settled-but-unfinished, as defined in Accounting Standard No. 14 - Revenue.

Applicable Codes

  • 《企业会计准则》(财政部令第5号)
  • 《企业会计准则第14号——收入》(财会〔2017〕22号)
  • GB/T 50326-2017 建设工程项目管理规范
  • TB 10402-2019 铁路建设工程监理规范
  • 国发〔1984〕34号 国营企业成本管理条例

Topic Positioning

Clarifies the four most confused concepts in construction-enterprise financial accounting - construction in progress, completed-but-unsettled, settled-but-unfinished and contract liability - with definitions, calculation formulas, statement presentation and a unified reconciliation, for cost accounting, work verification and valuation, and revenue recognition.

Core Conclusions

The four concepts span three bases:

  • Construction in progress (cost basis): elemental works into which labor, materials and plant have been input but which have not completed all the processes prescribed by the budget quota and cannot be settled. It is counted month-end, valued and carried forward to the next period, and excluded from the current period's completed-works cost. Value of construction in progress = sum of (equivalent quantity of uncompleted processes x budget unit price of the elemental work); cost allocation formula = cumulative actual cost of the elemental work x equivalent WIP output / (completed output + equivalent WIP output).
  • Completed-but-unsettled (settlement basis): the portion whose physical progress is complete and meets the measurement conditions but has not yet been verified and valued = cumulative recognized revenue minus cumulative settled price (positive difference), presented as a contract asset.
  • Settled-but-unfinished (settlement basis): the portion already valued where performance progress lags settlement progress = cumulative settled price minus cumulative recognized revenue (positive difference), presented as a contract liability.
  • Contract liability (statement basis): the obligation to transfer goods to the customer for consideration already received or receivable = advance project payments plus settled-but-unfinished.

Unified reconciliation: through the 'contract settlement' account - debit: revenue recognized per performance progress; credit: price already settled. Revenue greater than settlement gives a contract asset (completed-but-unsettled); revenue less than settlement gives a contract liability (settled-but-unfinished); construction in progress is presented as inventory, independent of the settlement basis.

Applicable Boundaries

Applies to construction enterprises applying the new revenue standard (Cai Kuai [2017] No. 22); performance progress is determined as cumulative actual cost divided by estimated total cost, or completed quantity divided by contract total; pure advances are accounted for as advance receipts, coexisting with contract liabilities; construction in progress is a cost-basis item and must not be confused with completed-but-unsettled (settlement basis); in railway works, un-verified-and-valued work is the typical cause of completed-but-unsettled.

Further Reading

Accounting Standards for Business Enterprises (MOF Decree No. 5), Article 45 (revenue for long-term works recognized by the percentage-of-completion method), Article 52 (costs accounted at actual amounts); Accounting Standard No. 14 - Revenue (Cai Kuai [2017] No. 22), Article 41 (definition of contract liability); Guo Fa [1984] No. 34, Regulations on Cost Management of State-Owned Enterprises, Articles 17 and 21 (accrual basis; costs accounted quarterly); GB/T 50326-2017, Code for Construction Project Management, 11.4.3 (synchronization of physical progress, output statistics and cost accumulation); for railway work-verification-and-valuation limits see TB 10402-2019, Specification for Construction Supervision of Railway Engineering, 6.0.6.