Whether quantities confirmed at the progress-payment stage can be re-measured and reduced at the final account: the line between provisional payment and lock-in (lock-in by signed measurement results, stage settlements absorbed into the final account, rough measurement as no basis for settlement)
No single answer; the determinant is the nature and level of the confirming document, not whether payment has been made: the three confirmations that are provisional in nature - issue of an interim payment certificate, provisional payment, and rough measurement (by physical progress or proportion) - may be re-measured and reduced at the final account (GB/T 50500-2024 Articles 9.1.14 and 9.4.14); once both parties sign the measurement results without limiting them 'for progress payment use only' (Article 7.1.8), or the interim settlement by construction stage documents have been signed (Article 10.2.3, 'the final account must not re-measure or re-price them'), the quantities are locked and may not be reduced, the sole exception being preliminaries and main contractor's attendance and coordination provisions, which must be recalculated under Articles 10.2.7 and 10.3.3; once the final account documents are signed and sealed by both parties, no repeated checking is allowed in any case (Article 10.3.12; Article 19 of MOHURD Decree No. 16).
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第7.1.3、7.1.5~7.1.8条、第9.1.14、9.4.11、9.4.13、9.4.14条、第10.2.3、10.2.7、10.3.3、10.3.12条
- 住房和城乡建设部令第16号《建筑工程施工发包与承包计价管理办法》第十八条、第十九条
- 财建〔2004〕369号《建设工程价款结算暂行办法》第十三条、第十六条
- 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第二十九条
- 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第十三条、第二十三条(自2026年6月30日起施行)
- 国务院令第802号《保障中小企业款项支付条例(2025修订)》第九条、第十条、第十二条、第十五条、第十七条
- 《中华人民共和国民事诉讼法》(2023修正)第六十七条、第七十九条
- 《中华人民共和国仲裁法》(2025修订)第三条、第五条、第十条
- 《天津市建设工程计价办法(2025)》第7.2.3、7.2.6、7.3.4、7.3.5条(地方同构口径参照)
Topic Positioning
This answers one of the most common adversarial questions in practice: can the employer, at the final account stage, overturn and re-measure and reduce quantities it confirmed - or even paid for - at the progress payment (interim payment) stage? The card resets the test from 'was it confirmed, was it paid' to 'on which level of document did the confirmation land, and was that document limited in use', and gives the tiered basis for what can and cannot be reduced.
Core Conclusions
The lock-in line is drawn on the nature of the document, not on the fact of payment. GB/T 50500-2024 Article 7.1.8: 'Measurement results of the works confirmed by signature of the employer and the contractor serve as the basis for adjustment of the contract price and for settlement, except where the contract provides otherwise, the parties expressly limit them to a basis for progress payment use only, or the measurement results are rough estimates.' The article itself opens two exceptions - contrary contractual agreement or express limitation to 'progress payment use only', and results that are rough estimates.
Confirmations at the progress-payment level are provisional and may be reduced at the final account (affirmative situations):
Article 9.1.14: where the contractor fails to submit an interim payment application under Article 9.1.2, or the application omits the adjusted contract amounts for completed works calculated under Chapter 8, the employer may provisionally pay interim amounts based on the cumulative price of completed works and the adjusted contract amounts, 'but the provisional payment serves only as payment of the interim amount and must not serve as the basis for settlement of the works or of completed works, and the contractor must not raise related claims against the employer for the difference between the provisional payment and the settlement'.
Article 9.4.14: where the contract provides, or the parties agree, that completed quantities or progress payments use rough measurement, 'it shall be clearly stated in the progress payment documents or the corresponding documents that they serve only for progress payment use and not as the basis for settlement of the works'; 'the results are used only for progress payment and not as a basis for completed works'.
Article 9.4.11: the employer checks the progress payment application, issues a payment certificate and pays; 'where the parties dispute the measurement and pricing results of some BOQ items, the employer shall issue the progress payment certificate and pay the progress payment on the undisputed BOQ items' - conversely, the disputed items are not locked by the issue of a certificate.
Re-measurement is confined to acceptable work: under Article 7.1.3, re-measurement of the contract works and measurement of variations and additional works 'shall be based on the acceptable works completed by the contractor as required by the contract and to be measured, on the construction drawings and the variation instructions issued by the employer, and on the national and industry quantity take-off standards and supplementary measurement rules agreed in the contract'. Quantities not accepted, failing acceptance or reworked are not measurable.
The classic rule of non-measurement (Cai Jian [2004] No. 369, Article 13(2)(3)): 'the employer does not measure quantities beyond the design drawings (including design changes) or reworked due to the contractor's fault'.
Staged measurement: Article 7.1.3 also provides that BOQ items of divisional works subject to price adjustment for changes in costs shall be measured in stages against the completed works in the agreed adjustment cycle - progress measurement is itself staged and provisional.
Three levels of progressive lock-in: signed measurement results, signed stage settlements, and the doubly signed final account (negative situations):
Measurement-results level: Article 7.1.7 requires that 'the employer and the contractor shall sign and confirm the agreed measurement results'; where checking, re-checking or review still yields no agreement, the dispute-resolution methods of Chapter 11 apply; Article 7.1.8 makes the signed results the basis for adjustment of the contract price and for settlement.
Deemed-approval level (lock-in without signature): Article 7.1.5 provides that where the employer fails to provide checking results within the agreed time, 'the measurement results submitted by the contractor may be deemed approved by the employer'; 'unless the contract provides otherwise, the measurement results submitted by the contractor may serve as the basis for calculating the project price, but not as evidence of acceptable delivery of the relevant works'; Article 7.1.6 provides that where the contractor fails to confirm in writing or seek re-checking of the employer's checking results within the agreed time, 'the measurement results checked by the employer may be deemed approved by the contractor', and the checked results submitted by the employer may serve as the basis for calculating the project price; conversely, where the employer fails to provide review results within the agreed time, the contractor's re-checking opinions may be deemed approved.
Stage-settlement level: Article 10.2.3: 'Except as provided in Article 10.2.7 of this Standard, stage settlement documents confirmed by signature of the employer and the contractor form part of the final account documents, and the final account must not re-measure or re-price them.' Article 9.4.13 further requires the parties to summarise the measurement statements of all measurement cycles and sign the summary sheet.
The only compulsory recalculation within stage settlement - preliminaries and main contractor's attendance and coordination provisions: Article 10.2.7 - the preliminaries and the attendance and coordination provisions calculated under Articles 10.2.5 and 10.2.6 'are used only to calculate and pay the stage settlement price and are not the basis for determining the final account price'; at the final account they are recalculated per the contract and increased or decreased accordingly; Article 10.3.3 further requires that at the final account all preliminaries contained in the completed works (including adjustments to statutory safety provisions) be calculated under Section 7.3 and Chapter 8, and all attendance and coordination provisions for specialist subcontracted works, directly commissioned specialist works and employer-supplied (free-issue) materials under Section 8.5; 'the preliminaries listed in the stage settlement must not serve as the basis for the final account of the works' and 'the attendance and coordination provisions listed in the stage settlement must not serve as the basis for the final account of the works'.
Final-account level: Article 10.3.12 - once the final account checking is completed and the employer and the contractor have signed and sealed it, 'the employer must not require the contractor to have the final account repeatedly checked with another construction cost consultant'; 'except as otherwise provided by laws and regulations, the final account documents signed and sealed by the employer and the contractor take effect per the contract, and the employer must not re-check the final account'. Article 19 of MOHURD Decree No. 16 is to the same effect: 'final account documents confirmed by signature of the employer and the contractor serve as the basis for the project financial accounts; without the consent of the other party, neither party may engage a construction cost consultancy to re-audit the effective final account documents. The employer shall pay the final account amount promptly per the final account documents.' The same Measures require the employer to file the final account documents with the housing and urban-rural development department of the people's government at or above county level at the place of the project.
Rules once the dispute enters expert assessment and adjudication:
Where the parties have reached agreement on the settlement of the project price before suit and one applies in litigation for a construction cost expert assessment, 'the people's court will not permit it' (Article 29 of Fa Shi [2020] No. 25) - signed settlement results block expert assessment.
Where audit conclusions or government fiscal review conclusions were agreed to determine the price: where the conclusion is not issued within a reasonable period for reasons not attributable to the contractor, or the contractor has evidence that it plainly contradicts the construction contract, the court permits judicial expert assessment of the construction cost on the contractor's application; the reasonable period follows the agreement, failing agreement the court determines it comprehensively by project scale, cost and complexity, not exceeding one year from the contractor's submission of the final account documents; where determining the price by audit or review conclusion was not agreed but the employer requests it, the court will not support the request (Article 13 of Fa Shi [2026] No. 12).
Evidence and expert procedure: each party bears the burden of proving its claims; evidence that cannot be collected by a party for objective reasons, or that the court considers necessary for the trial, is collected by the court (Civil Procedure Law Article 67); expert appraisal of specialised questions may be applied for, the expert being agreed by the parties or, failing agreement, appointed by the court (Civil Procedure Law Article 79); in arbitration one award is final, and after it is made no further arbitration or suit may be brought for the same dispute, but arbitration is accepted only with an arbitration agreement (Arbitration Law Articles 3, 5 and 10).
The SME-protection side: in dealings between state organs, public institutions and large enterprises and SMEs, where part is disputed but does not affect the performance of the rest, 'the undisputed portion must be paid promptly' (State Council Decree No. 802, Article 15); state organs, public institutions and state-owned large enterprises must not compel the use of the audit authority's audit conclusion as the settlement basis (Article 12); late payment carries overdue interest - an agreed rate not below the 1-year loan prime rate at the time of conclusion, or absent agreement 0.05% per day (Article 17) - so the risk of withholding a whole payment on the ground of 'disputes unresolved, need to re-reduce' sits with the employer.
Scope and Limits
This card applies to works priced on a bill of quantities basis and measured under GB/T 50500-2024, such as building and municipal works; where the contract provides otherwise on measurement procedure and the effect of confirmation, the contract governs (Article 7.1.8 'the contract provides otherwise' and Article 7.1.6 'unless the contract provides otherwise' both preserve party autonomy), so the first step in any reduction dispute is always to check the particular conditions on the signing of measurement results and the time limits. It does not apply to: (1) contracts expressly providing that progress measurement is final measurement; (2) cost-plus and similar contract types measured by agreed methods; (3) cases where a separate settlement agreement has been signed and falls within the reach of Article 29 of Fa Shi [2020] No. 25. The progress payment ratio and review-period clauses of Cai Jian [2004] No. 369 are no longer an appropriate current operating standard (its substantive rule that quantities beyond the design drawings and rework due to the contractor's fault are not measured remains referable); local measures may be stricter in procedure (e.g. the Tianjin pricing measures contain parallel provisions on stage settlement confirmation, recalculation of preliminaries and attendance provisions, and deemed approval on failure to check in time). Fa Shi [2026] No. 12 takes effect on 30 June 2026 and applies to first-instance construction contract dispute cases newly accepted after that date. This card is an analysis of the application of rules and contains no monetary calculations.
Further Reading
GB/T 50500-2024, China national pricing standard for BOQ: Articles 7.1.3, 7.1.5, 7.1.6, 7.1.7 and 7.1.8 (measurement of the contract works and lock-in by confirmation), Articles 9.1.14, 9.4.11, 9.4.13 and 9.4.14 (interim payment, rough measurement and the provisional nature of payments), Articles 10.2.3, 10.2.7, 10.3.3 and 10.3.12 (stage settlement absorbed into the final account; no repeated final-account checking); MOHURD Decree No. 16, Measures for the Administration of Pricing in the Awarding and Contracting of Building Works, Articles 18 and 19; Cai Jian [2004] No. 369, Interim Measures for Settlement of Construction Project Prices, Articles 13, 16 and 17; Fa Shi [2020] No. 25, Interpretation (I), Article 29; Fa Shi [2026] No. 12, Interpretation (II), Articles 13 and 23; State Council Decree No. 802, Regulation on Ensuring Payment to SMEs (2025 revision), Articles 9, 10, 12, 15 and 17; Civil Procedure Law (2023 amendment), Articles 67 and 79; Arbitration Law (2025 revision), Articles 3, 5 and 10; for the local interface, see Tianjin Measures for Construction Pricing (2025), Articles 7.2.3, 7.2.6, 7.3.4 and 7.3.5. Suggested order of enquiry in practice: first read the contract measurement clauses -> obtain any signed measurement confirmation sheets or summary sheets -> then determine whether measurement was rough or marked 'progress payment use only' -> finally confirm whether signed stage settlement documents exist. Evidence points: originals of confirmations, measurement summary sheets, use annotations on payment certificates, records of receipt of correspondence.