Procedures for handling contract price adjustment matters under GB/T 50500-2024 section 8.1: the five steps submission - checking - re-checking - further review - confirmation, the two-way forfeiture rules under which each party's silence is deemed approval, the link between signing the output documents and concurrent payment with progress payments / stage settlement payments, and the boundaries against the prior scheme submission for preliminaries and the price review for additional works
Under GB/T 50500-2024 section 8.1, contract price adjustments are handled through 'submission - checking - re-checking - further review - confirmation': the contractor measures the quantities under chapter 7, prices the adjustment under sections 8.2 to 8.11 and submits both with the supporting documents to the employer for checking within the agreed time (8.1.2); the employer verifies within the agreed time and either notifies confirmation in writing or replies in writing with checking comments, and if it neither confirms nor comments, the contractor's report is deemed accepted (8.1.3); after receiving the checking comments the contractor re-checks within the agreed time, and if it neither confirms nor comments, the employer's comments are deemed accepted (8.1.4); the parties sign the measurement and pricing output documents, which become the payment basis under chapters 9 and 10, and the adjusted additional (reduced) price is paid concurrently with the progress payments and the interim settlement payments by construction stage (8.1.6). All periods run 'within the agreed time'; the standard sets no uniform number of days.
Applicable Codes
- GB/T 50500-2024 第8.1.2条
- GB/T 50500-2024 第8.1.3条
- GB/T 50500-2024 第8.1.4条
- GB/T 50500-2024 第8.1.6条
- GB/T 50500-2024 Ch. 7(合同工程计量)
- GB/T 50500-2024 Ch. 9(合同价款支付)
- GB/T 50500-2024 Ch. 10(竣工结算与支付)
- 法释〔2020〕25号 第21条
Scope of the Topic
This card explains the 'procedures for handling contract price adjustment matters' laid down in GB/T 50500-2024 section 8.1: how the contractor reports, how the employer checks, how the contractor re-checks, what silence produces, and how the confirmed output documents flow into payment. It applies to the whole process of in-course price adjustment (variations, BOQ errors, provisional prices, cost fluctuation, changes in law, additional works, claims and the like) and is the common procedural shell around every kind of adjustment calculation.
Core Conclusions
I. The four trunk clauses, verbatim. Clause 8.1.2: 'Where a contract price adjustment matter arises during performance, the contractor shall calculate the quantities of the adjustment matter under chapter 7 of this standard, calculate the adjustment price under sections 8.2 to 8.11, and submit both with the supporting documents to the employer for checking within the agreed time.' 'The employer and the contractor may handle contract price adjustment matters through the procedure of submission, checking, re-checking, further review and confirmation.' Clause 8.1.3: 'On receiving the contractor's contract price adjustment report and supporting documents, the employer shall verify them within the agreed time; if it confirms them, it shall notify the contractor in writing; if it does not confirm them, it shall reply to the contractor in writing with its price adjustment checking comments; if it neither confirms nor raises checking comments, the contract price adjustment report submitted by the contractor shall be deemed accepted by the employer.' Clause 8.1.4: 'Where the employer raises price adjustment checking comments, the contractor shall re-check them within the agreed time of receipt; if it accepts them, it shall notify the employer in writing; if it does not accept them, it shall reply to the employer in writing with its re-checking comments; if it neither confirms nor raises re-checking comments, the comments raised by the employer shall be deemed accepted by the contractor.' Clause 8.1.6: 'The employer and the contractor shall sign the determined measurement and pricing output documents for the contract price adjustment, as the basis for payment of the contract price under chapters 9 and 10 of this standard. The additional (or reduced) contract price confirmed by both parties through adjustment shall be paid concurrently with the progress payments and the interim settlement payments by construction stage.' Reading of the second sentence: 'the increased (or decreased) contract price determined by the measurement and pricing output documents on which both parties agree shall be paid or deducted in the current progress payment and interim settlement payment by construction stage.'
II. The five-step chain and the action at each step. Submission (contractor: measure the quantities under chapter 7, price the adjustment under sections 8.2 to 8.11, attach the documents, report to the employer within the agreed time) -> checking (employer: verify within the agreed time, with three outcomes - confirmation, written checking comments, or silence) -> re-checking (contractor: respond to the checking comments within the agreed time, with the same three outcomes) -> further review and confirmation (covered by the procedure names in clause 8.1.2; clause 8.1.5 is the dedicated clause for the further-review step - see the original text for its details) -> sign the output documents and pass into payment. Key structural feature: every link is a two-way 'respond or forfeit' design - the employer's silence deems the contractor's report accepted; the contractor's silence deems the employer's comments accepted. The whole procedure therefore turns on one single action: 'respond in writing within the agreed time'.
III. Three deemed-approval consequences and the evidentiary points. (1) If the employer, after receiving the report, neither confirms nor raises checking comments -> the contract price adjustment report submitted by the contractor is deemed accepted by the employer. (2) If the contractor, after receiving the checking comments, neither confirms nor raises re-checking comments -> the comments raised by the employer are deemed accepted by the contractor. (3) Clause 8.9.7 lays down a like rule for preliminaries (if the contractor fails in time to submit the proposed implementation scheme or to raise the additional claim -> deemed not to change the preliminaries cost and the additional right waived; if the employer fails to review in time -> the contractor's scheme deemed approved), which applies to preliminaries and not to the general procedure of this section. Practical point: the party invoking deemed approval must prove that the report / comments were served as agreed, that the documents were complete, and that the other party made no written reply within the agreed period; the period itself is set by contract - the standard prescribes no uniform number of days - and where the contract is silent the burden of proof on the invoking party rises sharply.
IV. Payment linkage after confirmation. The adjusted price is not held to the final account for one-off settlement but handled 'concurrently': once confirmed by both parties (or deemed accepted by law) and the measurement and pricing output documents signed, the increased price is paid with the current progress payment and interim settlement payment by construction stage, and the reduced price deducted at the same time; the signed documents are the payment basis for chapter 9 (payment of the contract price) and chapter 10 (final account and payment). A re-rated unit price or an adjustment amount claimed at the stage-settlement stage without completing this confirmation procedure therefore fails procedurally; conversely, an adjustment amount covered by signed output documents should not be held back by the employer and cut again at final account.
V. Boundaries against neighbouring procedural clauses. (1) Clauses 8.9.6 and 8.9.7: where a variation changes the preliminaries, the disadvantaged party must submit the proposed implementation scheme before execution, detailing the changes against the original scheme, and only after confirmation may the preliminaries be adjusted under clauses 8.9.4 and 8.9.5 - a 'prior scheme submission' requirement for preliminaries, stricter than this section's 'report after the event'. (2) Clause 8.10.2: additional works require the project execution plan or implementation scheme, the works programme and the priced offer to be submitted to the employer for review before execution, with the employer approving within a reasonable time. (3) Chapter 10 (settlement stage) has its own checking, objection and lapse rules, which do not replace the adjustment procedure of this section.
Applicability Boundaries
1 Scope of application: all contract price adjustment matters arising during performance (section 8.2 BOQ errors; 8.3 provisional sums; 8.4 provisional prices; 8.5 main contractor's attendance and coordination provisions; 8.6 others; 8.7 cost fluctuation; 8.8 changes in laws, regulations and policies; 8.9 variations; 8.10 additional works; 8.11 claims); it does not apply to final account review and final closure of accounts after the defects period (chapter 10 has its own rules). 2 Periods: the clauses uniformly say 'within the agreed time'; the standard sets no uniform number of days and the actual periods follow the particular conditions of the contract; absent agreement, they must be argued through contract interpretation and course of dealing, and 28 days should not be applied directly (28 days is the default period in other clauses - the Notice of Claim, settlement objections - not the general period of this section). 3 Hierarchy: GB/T 50500-2024 is a recommended national standard; its 'deemed approval' clauses bind only through incorporation in or agreement of the contract; in litigation, the settlement-stage 'failure to reply in time deems acceptance' follows a separate judicial interpretation test (Fa Shi [2020] No. 25, article 21, three elements), and the two must not be cited interchangeably. 4 This section governs procedure only, not the calculation methods of each adjustment matter - the substantive rules on rate conversion, price differential adjustment and claim computation sit in sections 8.2 to 8.11.
Further Reading
GB/T 50500-2024: clauses 8.1.1 to 8.1.6 (adjustment procedures; clause 8.1.5 is the dedicated further-review clause); chapter 7 (measurement of adjustment quantities); sections 8.2 to 8.11 (substantive calculation rules by adjustment matter); chapter 9 (payment of the contract price); chapter 10 (final account and payment). Prior scheme submission and lapse for preliminaries: clauses 8.9.6 and 8.9.7. Prior price review for additional works: clause 8.10.2. The judicial test of 'failure to reply in time deems acceptance' at settlement stage: 'Interpretation of the Supreme People's Court on the Application of Law in Cases of Disputes over Construction Contracts' (Fa Shi [2020] No. 25), article 21.