Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-25

Constituent documents of the final account (cover / signature page / contents / compilation notes / tiered summary tables and their standard sources) and the list of compilation bases (GB/T 51095-2015, GB/T 50326-2017, DB37/T 5130-2018 etc.)

Per GB/T 51095-2015 Article 8.2.2, final account documents shall include the cover, signature page, contents, compilation notes, the final account summary and the project-wise and unit-works final account summaries, with BOQ-priced outputs per Appendix F; compilation bases per Article 8.2.4 (10 items), GB/T 50326-2017 Article 18.3.3 (5 items) and DB37/T 5130-2018 Article 8.2.4 (9 items); under BOQ pricing the cover, title page, notes and summary formats follow GB/T 50500-2024 Appendix B Table B.4.1, Appendix C Table C.4.1, Appendix D Table D.3.1 and Appendix E Table E.6.1.

Applicable Codes

  • GB/T 51095-2015 · Code for construction cost consultation 第8.2.2条(文件组成)、第8.2.4条(编制依据)、App. F(清单计价成果文件表式)
  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works App. D Table D.3.1(竣工(过程)结算编制(审核)说明)
  • GB/T 50500-2024 第10.3.1、10.3.2、10.3.8、10.3.12条
  • GB/T 50326-2017 · Code for Construction Project Management 第18.3.3条(结算依据)

Scope of the question

What documents make up the final account, the standard source of each constituent (table), and the list of materials the final account is compiled from (per GB/T 51095-2015, GB/T 50500-2024 etc.).

Core conclusions

1. Document composition - GB/T 51095-2015 Article 8.2.2 Final account documents shall include cover, signature page, contents, compilation notes, the final account summary and the project-wise and unit-works final account summaries; BOQ-priced final account outputs may follow Appendix F of the code.

2. BOQ pricing table formats - GB/T 50500-2024 appendices

  • Final (interim) account cover: Appendix B Table B.4.1;
  • Final (interim) account title page: Appendix C Table C.4.1;
  • Final (interim) account compilation (review) notes: Appendix D Table D.3.1, covering project overview, scope, bases and other matters needing explanation;
  • Final (interim) account summary: Appendix E Table E.6.1 (note: provisional sums for nominated specialist works are VAT-inclusive and excluded from the VAT computation base; amounts from BOQ-defect adjustments are listed against the corresponding work-item and preliminaries lines as contract price adjustments; works itemised per project or unit works may be summarised in that table by reference).

3. Notes content - GB/T 51095-2015 Article 8.2.3 The notes shall cover project overview, compilation scope and basis and method, statements on measurement, pricing and the rates adopted for labour, materials and equipment, and other matters.

4. Compilation bases (several standards, complementary) 1 GB/T 51095-2015 Article 8.2.4 (10 items): laws, regulations and normative documents affecting the price; site re-survey records; the construction contract, specialist subcontracts and supplements, material and equipment purchase contracts; pricing bases published by cost authorities; tender and tender pricing documents; construction drawings, the approved execution plan, design changes, negotiations, claims and site instructions, and minutes; material and equipment price approval sheets; contract price additions or deductions confirmed by both parties; approved start, completion, suspension and resumption reports; other relevant materials. 2 GB/T 50326-2017 Article 18.3.3 (5 items): contract documents; as-built drawings and variation documents; technical and material-substitution approvals; pricing documents and bills of quantities; confirmed site instructions and claim records. 3 DB37/T 5130-2018 Article 8.2.4 (9 items, local): laws and normative documents; contracts and subcontracts and purchase contracts; tender documents; drawings, as-built drawings, geological reports, the approved execution plan, variations, negotiations, claims and instructions, minutes, site survey records, concealed-works acceptance records and photos; price approval sheets; confirmed price additions and deductions; published pricing bases; approved start, completion, suspension and resumption reports; other relevant materials. 4 RISN-TG 012-2011 Article 18.4.1 commentary (6 items): contract documents; as-built drawings and variations; technical and substitution verifications; pricing documents, BOQs, charging standards and adjustment rules; instructions and claim records; other rules and materials.

5. Review outputs - GB/T 51095-2015 Article 8.3.1 Final account review cover, signature page, review report, approved-signature sheet, review comparison summaries and project-wise / unit-works comparison tables may follow Appendix G.

Applicability limits

Applies to final account compilation and review of building and municipal works under BOQ pricing and GB/T 50500-2024 / GB/T 51095-2015. Both are recommendatory national standards whose force arises through contract; express contract terms prevail. DB37/T 5130-2018 is a Shandong local standard; RISN-TG 012-2011 is a practice guideline. This card settles only what the documents comprise and the bases of compilation; the fuller materials list (with practice-level classification) is in the companion card. Submission, checking, review and confirmation procedures follow GB/T 50500-2024 Article 10.3.4 etc.; cost line items and adjustment matters follow Articles 10.3.2 and 8.1.1.

Further reading

  • GB/T 51095-2015 Code for Construction Cost Consultancy: Articles 8.2.2 (composition), 8.2.3 (notes), 8.2.4 (bases), 8.3.1, Appendix F (BOQ final account formats), Appendix G (review outputs).
  • GB/T 50500-2024 China national pricing standard for BOQ: Appendix B Table B.4.1, C Table C.4.1, D Table D.3.1, E Table E.6.1.
  • GB/T 50326-2017 Code for Construction Project Management, Article 18.3.3; DB37/T 5130-2018 Article 8.2.4; RISN-TG 012-2011 Article 18.4.1.