Appendix D “Pricing Statements” of GB/T 50500-2024: required contents of the four statement tables and dispute risks of omissions (tender price ceiling / tender (priced offer) / final account statement + method of measurement statement for the bill of quantities (BOQ))
GB/T 50500-2024 Appendix D has four statement tables: D.1.1 tender price ceiling preparation (review) statement must include project overview, scope, basis of preparation (review), special requirements (if any), and other issues to be explained; D.2.1 tender (priced offer) statement must include scope, item description (work item specification), planned duration, site conditions, project execution plan (construction methodology and site organization) features, and other issues to be explained; D.3.1 final account (interim) preparation (review) statement must include project overview, scope, basis of preparation (review), and other issues; D.4.1 statement of method of measurement for the BOQ must specify the names and numbers of the national/industry measurement standards adopted and list supplementary rules of measurement (with 4.1.3). Omitting basis details, scope delimitation, supplementary rules of measurement, and explanations of price and percentage rate determination (GB/T 51095-2015 8.2.3) are high-frequency final account dispute triggers.
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works App. D(Table D.1.1/D.2.1/D.3.1/D.4.1)及第4.1.3条
- GB/T 51095-2015 · Code for construction cost consultation 第8.2.3条
Topic Positioning
The required contents of the four statement tables of Appendix D “Pricing Statements” of GB/T 50500-2024 (D.1.1 tender price ceiling preparation/review statement, D.2.1 tender (priced offer) statement, D.3.1 final account (interim) preparation/review statement, D.4.1 statement of method of measurement for the BOQ), and the high-risk omissions that directly trigger final account disputes. For writing statement pages when preparing/reviewing tender price ceilings, tenders (priced offers), final accounts, and BOQ documents.
Core Conclusions
Appendix D's four tables and their required contents (as stated in the standard):
- D.1.1 Tender price ceiling preparation (review) statement: shall include project overview, project scope, basis of preparation (review), special requirements (if any), and other issues to be explained.
- D.2.1 Tender (priced offer) statement: shall include project scope, item description (work item specification), planned duration, site conditions, project execution plan (construction methodology and site organization) features, and other issues to be explained.
- D.3.1 Final account (interim) preparation (review) statement: shall include project overview, project scope, basis of preparation (review), and other issues to be explained.
- D.4.1 Statement of method of measurement for the BOQ: Note 1 — where national/industry measurement standards are adopted, their names and numbers shall be specified; Note 2 — where the rules of measurement are supplemented according to the characteristics of the project, the detailed rules of measurement for the BOQ shall be listed.
Companion requirement (4.1.3): BOQ deliverables include cover, signature page, explanatory notes, statement of method of measurement, BOQ and pricing tables; the explanatory notes shall list project overview, tender (or contract) scope, basis of preparation, etc.; the statement of method of measurement shall specify the national/industry measurement standards used for the BOQ and the rules of measurement supplemented according to the actual needs of the project, etc. Where the measurement standards are not clear or rules of measurement are supplemented according to the actual project conditions, the supplemented or adjusted rules of measurement shall be stated in the statement of method of measurement — i.e., the D.4.1 statement page mandatorily exists at the BOQ preparation stage together with the deliverables and echoes the final account stage.
Price basis supplement (GB/T 51095-2015 8.2.3): final account preparation statements shall include project overview, scope of preparation, basis of preparation, preparation method, explanations of the measurement of the works, pricing, and the determination of prices and percentage rates for labour, materials, equipment, etc., and other matters to be explained.
High-risk omissions (ranked by dispute impact):
- Vague basis of preparation (review) — merely “per the contract” means nothing; it must specify contract numbers, supplementary agreements, tender documents, bid documents, drawing review minutes, variation orders/site instruction record numbers, material price adjustment clauses (agreed scope, base price (reference price for adjustment), risk band (no-adjustment tolerance, e.g. ±5%)) — otherwise “which contract version applies, and whether the price adjustment clause applies” loses its written anchor;
- Undefined project scope — the scope of free-issue materials (by the employer), specialist subcontract interfaces, directly awarded works, the content of the main contractor's attendance and coordination provisions, and whether omitted/added works fall within this final account must be stated — otherwise “does this cost enter the final account” becomes the biggest source of dispute;
- Missing supplementary rules of measurement (D.4.1's dedicated minefield) — where the national/industry measurement standards are unclear (e.g. earthwork slope coefficients, working face widths, extra-high scaffolding measurement, rebar lap and anchorage measurement bases), omission of supplementary rules means both sides take opposing positions when quantities are re-measured for the final account;
- Unstated determination of prices and percentage rates — which period of labour cost is used, which period of published price information (government guidance prices) (or which quotation) is used for materials, the basis for statutory levies and fees/taxes and duties (VAT under the current standard), and the method of substituting actual prices for provisional sums for specified materials — omission invites endless disputes over the “price source”;
- Unfixed legacy disputes — D.3.1's “other issues to be explained” should list disputes that have arisen but not been agreed, together with both parties' positions; without contemporaneous written records, it will be difficult to prove the case when old disputes are reopened after the final account.
Practice advice: final account statements should trace the amount composition along the chain “contract price -> accumulated adjustment items (variations/site instruction records/claims/price adjustment for fluctuation) -> final account price”; the statement is signed with the deliverables and forms part of the contract documents.
Applicable Boundaries
- Applies to pricing documents prepared under GB/T 50500-2024 for building and municipal works; the 2024 edition has changed from mandatory GB 50500-2013 to a recommended national standard (GB/T), and the effect of its provisions depends on contractual citation (contractual agreement takes precedence).
- The four tables correspond to four document types (tender price ceiling, tender (priced offer), final account (interim), and statement of method of measurement for the BOQ); use the matching table for the document type and do not mix them.
- Where sector-specific measurement standards exist, D.4.1 requires their names and numbers to be specified; where sector and national standards conflict, the contractual agreement and the applicable sector standard prevail.
- This card covers only the required contents of the statement pages; for specific rule values (slope coefficients, working face widths, etc.) and final account measurement methods, see the referenced extension cards.
Further Reading
- GB/T 50500-2024 China national pricing standard for BOQ, Appendix D Tables D.1.1, D.2.1, D.3.1, D.4.1 (core evidence of this card); companion Clause 4.1.3 (composition of BOQ deliverables, requirements for explanatory notes and the statement of method of measurement).
- GB/T 51095-2015 “Code for construction cost consultancy” Clause 8.2.3 (final account preparation statement includes explanations of price and percentage rate determination).
- Extensions: determination of quantities for the final account (measurement–final account linkage), general rules of measurement, chain of evidence management (statement pages as written anchors of the basis for settlement), tender price ceiling preparation framework (the D.1.1 stage).