The force majeure processing chain: immediate notice -> continuing interim reports -> final report within 28 days after the end of the event -> Notice of Claim and claim report -> review and reply by the other party -> confirmation, signing and concurrent payment, plus the 84-day/140-day termination exit (GF-2017-0201 Clauses 17.2/17.4/19 and GB/T 50500-2024 Clauses 8.11.3/8.11.5/8.11.21)
After a force majeure event occurs, the party shall immediately notify the other party and the supervising engineer in writing with supporting proof; while the event continues, interim reports must be submitted, and the final report within 28 days after the event ends (GF-2017-0201 Clause 17.2); cost and time claims merge into the claims procedure: within the contractual period after the event (28 days if not agreed), a written Notice of Claim is submitted, and within the same period after its issue the claim report; for continuing effects, further notices at intervals of no more than 28 days or at reasonable intervals, and the final report within the period after the end; the employer may, within 14 days (if not agreed) after receiving the Notice of Claim, request further particulars in writing, and shall reply in writing within 28 days (if not agreed) after receiving the report, failing which the claim may be treated as approved (GB/T 50500-2024 Clauses 8.11.3 and 8.11.5; GF Clauses 19.1~19.4); the parties shall confirm and sign the adjusted duration and the claim costs as the basis for progress payments and settlement, paid concurrently (Clause 8.11.21); where force majeure prevents performance of the contract continuously for more than 84 days or cumulatively for more than 140 days, both parties are entitled to terminate (Clause 17.4).
Applicable Codes
- GF-2017-0201 建设工程施工合同(示范文本)第17.2款〔不可抗力的通知〕
- GF-2017-0201 第17.4款〔因不可抗力解除合同〕
- GF-2017-0201 第19.1~19.5款〔索赔〕、第20条〔争议解决〕、第4.4款〔商定或确定〕
- GB/T 50500-2024 第8.11.3条、第8.11.5条、第8.11.21条
Positioning
The processing chain of a force majeure event from occurrence through claim confirmation to payment, with the time limits, document contents and consequences of delay at each link - aligning the time limits of GF-2017-0201 Clauses 17.2, 19 and 20 with those of GB/T 50500-2024 Clauses 8.11.3, 8.11.5 and 8.11.21 for combined use, and giving the termination exit (Clause 17.4).
Core conclusions
1. Notice and reports (GF-2017-0201 Clause 17.2 [Notice of force majeure])
Where a party to the contract encounters a force majeure event that obstructs its performance of contractual obligations, it shall immediately notify the other party and the supervising engineer, explaining in writing the force majeure and the obstructed performance in detail and providing the necessary proof. Where the force majeure continues, the party shall submit interim reports to the other party and the supervising engineer in good time, explaining the force majeure and the obstruction of performance, and shall submit the final report with the relevant materials within 28 days after the end of the force majeure event. Evidence and disagreement: both parties shall collect evidence proving the occurrence of the force majeure and the loss caused, and carefully count the loss in time (Clause 17.1); where they disagree on whether an event is force majeure or on the loss caused, the supervising engineer handles it under Clause 4.4 [agreement or determination], and any dispute is handled under Clause 20 [resolution of disputes].
2. Duty of mitigation (also a precondition of recovery on claim)
GF-2017-0201 Sub-clause 17.3.2, final paragraph: 'After the force majeure occurs, the parties to the contract shall all take measures to avoid and reduce escalation of the loss as far as possible; any party that has failed to take effective measures, so that the loss escalates, shall bear responsibility for the escalated part.' The written traces of mitigation (caretaker arrangements, covering and sealing, clean-up and drainage, photographic records) are both evidence of performing the duty and the pricing basis for the costs of 'care, clean-up and repair as required by the employer'.
3. Cost and time claims: merged into the works claims procedure (GB/T 50500-2024 Clause 8.11.3)
- Within the contractual period after the event occurs (28 days if the contract is silent), submit to the employer a written Notice of Claim for the event, explaining the cause of the claiming event and the claim intention; where it is not issued in time, the matter is handled as agreed in the contract. Umbrella clause: where the suffering party fails to claim within the agreed time, it may be treated as having abandoned the relevant works claim, unless otherwise agreed in the contract or otherwise provided by laws and regulations.
- Within the contractual period after the Notice of Claim is issued (28 days if the contract is silent), submit a written claim report explaining in detail the cause, the contractual clauses relied on, and the costs claimed and (or) the days of extension of time claimed, and provide the necessary records and supporting materials together with the itemised calculation sheet of the claimed costs.
- Where the claiming event involves both additional costs and extension of time, they shall be claimed together.
- Where the event has continuing effects, continue to submit further Notices of Claim at the contractual intervals (no more than 28 days if the contract is silent) or at reasonable intervals, explaining the actual situation, providing records, and listing the cumulative claimed costs and (or) days of extension of time.
- Within the contractual period after the end of a continuing event (28 days if the contract is silent), submit the final claim report explaining the cause of the whole event, the clauses relied on and the total costs and (or) days of extension of time, with the records, supporting materials and the cost calculation sheet.
4. Review and reply by the other party (GB/T 50500-2024 Clause 8.11.5; GF Clauses 19.1/19.2)
- The employer shall examine the records and supporting materials within the prescribed time after receiving the Notice of Claim; where it considers supplementation necessary, it shall request further particulars from the contractor in writing within the contractual period (14 days if the contract is silent) after receiving the Notice of Claim.
- The employer shall reply in writing with its handling opinion within the contractual period (28 days if the contract is silent) after receiving the claim report or the supplementary supporting materials; late reply or no reply is handled as agreed in the contract, and where the contract is silent, the contractor's works claim may be treated as accepted by the employer.
- Where a claim involves both costs and time, the employer shall approve the cost claim and the extension of time together.
- Once the parties have agreed the claim costs, the employer shall pay them at the contractual payment percentage in the current progress payment and the interim settlement payments by construction stage, and pay the remainder in the final account payment.
- GF-2017-0201 Clauses 19.1~19.2 are the same mechanism: the contractor shall send the Notice of Claim to the supervising engineer within 28 days after knowing or being expected to know of the claiming event, failing which it 'loses the right to claim additional payment and (or) extension of time'; within 28 days after issue, the claim report; for continuing effects, further claim notices at reasonable intervals; within 28 days after the effects end, the final claim report. The supervising engineer completes its examination and reports to the employer within 14 days after receiving the claim report; within 28 days after the supervising engineer receives the claim report or further supporting materials, the employer shall have the supervising engineer issue the claim decision signed by the employer, failing which the employer is deemed to have accepted; accepted claim amounts are paid in the current progress payment.
- The employer's claims apply symmetrically (Clauses 19.3/19.4): the employer shall send its Notice of Claim to the contractor through the supervising engineer within 28 days after knowing or being expected to know of the claiming event, and submit the claim report within 28 days after issue; the contractor shall reply within 28 days after receiving the claim report or further supporting materials, failing which it is deemed to accept the employer's claim.
- Claim limitation (Clause 19.5): once the contractor receives the completion payment certificate under Clause 14.2, it is deemed no longer entitled to bring any claim arising before issue of the taking-over certificate for the works; the final closure application is limited to claims arising after issue of the taking-over certificate, and the period for raising them ends on acceptance of the final closure certificate.
5. Confirmation, signing and payment (GB/T 50500-2024 Clause 8.11.21)
After the relevant claiming event, the parties shall follow the procedures of Clauses 8.11.3~8.11.6 of this standard, and shall confirm and sign the adjusted duration and the claimed costs, as the basis for the progress payments and the settlement price of the works. The confirmed claim costs shall be paid concurrently in the progress payments and the interim settlement payments by construction stage. - Procedural compliance plus confirmation and signature are the two indispensable steps that convert force majeure loss into payable amounts.
6. Disputes and the termination exit
- Dispute resolution: Clause 20.1 amicable settlement; 20.2 mediation (by the construction administration authority, an industry association or a third party); 20.3 dispute review (one or three reviewers selected within 28 days after signing or within 14 days after the dispute arises; the review panel makes a written determination within 14 days after receiving the review application report; binding once signed and confirmed by both parties); 20.4 arbitration or litigation; 20.5 the dispute resolution clauses survive independently (amendment, termination, invalidity or revocation of the contract does not affect their effect).
- Termination exit: where force majeure renders the contract incapable of performance continuously for more than 84 days or cumulatively for more than 140 days, both the employer and the contractor are entitled to terminate the contract (GF Clause 17.4); after termination, the amounts payable by the employer are agreed or determined under Clause 4.4 (the price of the work executed; the price of materials and equipment already ordered and delivered, or to be accepted on delivery; the costs and losses arising from returns or termination of the purchase contracts; the costs of leaving the site and dismissing personnel; other sums payable before termination; the sums payable by the contractor to be deducted; other sums agreed or determined by the parties), to be paid within 28 days after the agreement or determination unless the particular conditions provide otherwise. The complete list of the seven payments and the loss allocation rules are in the sibling card on the allocation rules for the same topic.
Boundaries of application
- 28 days and 14 days are fallback values 'where the contract is silent': GB/T 50500-2024 always reads 'the period agreed in the contract (28/14 days if none)', and the parties' agreement prevails; GF-2017-0201 Clause 19 writes the 28 days directly into the model text.
- The strength of the consequence of delay has two tiers: GF-2017-0201 Clause 19.1 is a time-bar formulation in the model text ('loses the right to claim additional payment and (or) extension of time'); GB/T 50500-2024 Clause 8.11.3 changes this to 'handled as agreed in the contract' and retains the exception of 'other provisions of laws and regulations' - a softer treatment that returns the strength of the bar to the contract.
- 'No reply in time is deemed approval' can produce effect at settlement and in litigation only where the contract expressly so agrees; relying solely on the model text or the recommended national standard finds limited support in practice.
- The reporting duties and the claims procedure are two parallel lines: the immediate notice, interim reports and final report under Clause 17.2 are contract duties and evidence preservation, while the 28-day Notice of Claim under Clause 19 / Clause 8.11.3 preserves rights. Neither substitutes for the other, and missing either leaves a gap in proof or in the time limits.
- GF-2017-0201 is a model text that binds only if adopted by the parties; GB/T 50500-2024 is a recommended national standard that becomes contract obligation when invoked by the contract.
- This card covers only 'how the procedure runs'; the constitutive requirements and allocation rules for who bears each loss (including excepted events, and force majeure encountered after delay) are in the sibling card on the allocation rules for the same topic.
Further reading
GF-2017-0201 model construction contract, general conditions: Clause 17.1 [confirmation of force majeure], Clause 17.2 [notice of force majeure], Clause 17.4 [termination due to force majeure], Clauses 19.1~19.5 [claims], Clauses 20.1~20.5 [resolution of disputes], Clause 4.4 [agreement or determination], Clauses 14.2/14.4 [final account review / final closure of accounts]. GB/T 50500-2024 Standard for pricing of bills of quantities for construction works: Clause 8.11.3 (the contractor's works claims), Clause 8.11.5 (the employer's handling of works claims), Clause 8.11.6, Clause 8.11.21 (confirmation, signing and concurrent payment of claim costs).
Keywords
- 不可抗力通知
- 中间报告
- 最终报告
- Notice of Claim
- 28天期限
- deemed approval upon lapse of the response period
- 确认签署
- 84天140天解除合同