Difference between free float and total float, and graded handling of schedule deviations in practice
Free float (FF) = the slack usable without delaying the earliest start of succeeding activities — it protects "downstream starts"; total float (TF) = the slack usable without delaying the total duration — it protects "the project duration"; FF ≤ TF, and the activities with the least TF are critical. Graded handling: delay ≤ FF — plan unchanged; FF < delay ≤ TF — successors postponed but total duration unaffected; delay > TF — critical activities must be compressed or the unfinished plan recompiled. Duration claims recognize only the portion exceeding total float (GB/T 50500-2024, Clause 8.11.8).
Applicable Codes
- JGJ/T 121-2015 工程网络计划技术规程
- GB/T 50358-2017 建设项目工程总承包管理规范
- GB/T 50500-2024 建设工程工程量清单计价标准
Topic Positioning
The conceptual difference between free float (FF) and total float (TF) in network plans, and how the two are used in actual schedule management for graded deviation handling, criticality judgment, duration claims, and resource optimization.
Core Conclusions
① Definition comparison (JGJ/T 121-2015, Clauses 2.1.32–2.1.33): free float is the slack usable without affecting the earliest start of succeeding activities (and related time limits), protecting "downstream on-time starts"; total float is the slack usable without affecting the total duration (and related time limits), protecting "the project duration". Numerically FF ≤ TF — free float is a safe subset of total float, usable only by the activity itself and not transferable downstream. ② Graded deviation handling: delay ≤ FF — neither successors nor total duration affected, plan may stay unchanged; FF < delay ≤ TF — successors postponed but total duration unaffected, handle flexibly per the nature of following work; delay > TF — the total duration is threatened: compress unfinished critical activities with low resource intensity or low direct-cost rate, or recompile the unfinished portion as a new plan. ③ Duration claims (GB/T 50500-2024, Clause 8.11.8): for critical-path delays the delay time is the claimable duration; for non-critical delays beyond total float, the excess is claimable; within total float no claim arises. ④ Non-critical adjustments are limited to total float (shifting activities, lengthening/shortening durations), with time parameters recalculated after each adjustment to confirm no global impact; in time-scaled networks the horizontal projection of the wave line is the free float, readable directly.
Applicable Boundaries
Applies to schedules prepared by AOA, AON, and time-scaled network methods, assuming activity logic and durations are fixed. Bar charts and milestone tables show no logic, so floats cannot be computed. Earned-value management gives intuitive deviation analysis but cannot determine the critical path and cannot replace network analysis (GB/T 50358-2017, Clause 10.3.3). Duration-claim rules give priority to contract agreement; the standard is the general basis absent agreement.
Further Reading
See JGJ/T 121-2015, Specification for Engineering Network Planning Technique, Clauses 2.1.32–2.1.33 (float terminology), Clauses 4.5.1–4.5.2 (AOA critical activities / time-scaled wave-line method), Clauses 5.5.1–5.5.2 (AON critical activities), Clauses 7.3.2–7.3.3 (critical/non-critical adjustments); GB/T 50358-2017, Code for Management of Engineering Procurement Construction (EPC) Projects, Clause 10.3.3 (earned-value plus network deviation-analysis procedure); GB/T 50500-2024, Clause 8.11.8 (delay claim duration calculation).
Keywords
- 自由时差
- total float
- 进度偏差
- 关键工作
- claim for extension of time (EOT)
- 时差调整