Recognition criteria for force majeure events, item-by-item sharing of losses, costs and time, supporting insurance, and the conditions for terminating the contract for force majeure (GF-2017-0201 clauses 17.1/17.3/17.4 compared with GB/T 50500-2024 clauses 8.11.12 to 8.11.15)

Force majeure is recognised by the three criteria of being unforeseeable at contract signing, unavoidable and insurmountable during performance (GF-2017-0201 clause 17.1). The sharing basis: the employer bears damage to the permanent works and to materials/construction equipment delivered to site, third-party casualties and property losses caused by damage to the works, wages that must be paid to workers during suspension, care/cleaning/repair costs and the wages of necessary personnel kept on site at the employer's request, and acceleration costs requested by the employer; the contractor bears damage to its own construction plant and preliminaries facilities, and each party bears its own casualties and other property; the contractor's other suspension costs are reasonably shared by both parties and the time for completion is extended accordingly; losses enlarged by failure to mitigate are borne by the party that failed to mitigate, and force majeure encountered during delayed performance does not relieve liability for breach (clause 17.3.2; GB/T 50500-2024 clause 8.11.12). Where force majeure prevents performance of the contract continuously for more than 84 days or cumulatively for more than 140 days, either party may terminate; after termination the seven heads of payment under clause 17.4 are paid within 28 days of being agreed or determined.

Applicable Codes

  • GF-2017-0201 建设工程施工合同(示范文本)通用合同条款 第17.1款〔不可抗力的确认〕
  • GF-2017-0201 第17.3.1项、第17.3.2项〔不可抗力后果的承担〕
  • GF-2017-0201 第17.4款〔因不可抗力解除合同〕
  • GF-2017-0201 第18.1、18.3、18.6、18.7款〔保险〕
  • GB/T 50500-2024 建设工程工程量清单计价标准 第8.11.12条
  • GB/T 50500-2024 第8.11.13条、第8.11.14条、第8.11.15条

What this card covers

The recognition criteria of force majeure events, the item-by-item rules for sharing casualties, property damage, additional costs and time delay between employer and contractor, the supporting insurance, and the conditions for termination - based jointly on clause 17 of the general conditions of GF-2017-0201 and clauses 8.11.12 to 8.11.15 of GB/T 50500-2024 (the two are substantially aligned; clause 8.11.12 of the 2024 edition opens by stating 'except where the contract provides that the employer insures against all risks for the works and third-party liability and/or otherwise agrees').

Core conclusions

1. Recognition criteria (GF-2017-0201 clause 17.1 [Confirmation of force majeure], original wording)

Force majeure refers to natural disasters and social emergencies that the contract parties could not foresee at the time of signing the contract and that are unavoidable and insurmountable during its performance, such as earthquakes, tsunamis, epidemics, riots, martial law, insurrection, war, and other situations agreed in the particular conditions.

The three criteria (unforeseeable, unavoidable, insurmountable) must all be present; the scope is the three parallel classes of 'natural disasters + social emergencies + other situations agreed in the particular conditions', which the particular conditions may expand or narrow. The same clause also provides: after force majeure occurs, the employer and the contractor shall collect evidence of its occurrence and of the losses it causes, and promptly and carefully compile the losses; where they disagree on whether an event is force majeure or on its losses, the supervising engineer handles it under clause 4.4 [agreed or determined], and disputes go to clause 20 [dispute resolution].

2. Sharing table for the consequences (GF-2017-0201 clause 17.3.2 and GB/T 50500-2024 clause 8.11.12)

# Loss/cost item Borne by Basis
1 Damage to the permanent works and to materials and construction equipment delivered to site, and repair costs Employer GF 17.3.2(1); GB/T 50500-2024 8.11.12-1
2 Casualties and property losses of third parties (within the site) caused by damage to the works Employer as above
3 Damage to the contractor's construction plant and machinery Contractor GF 17.3.2(2); 8.11.12-2
4 Damage to, and cleaning and repair of, preliminaries items (construction facilities) Contractor 8.11.12-2 (not separately listed in GF 17.3.2; falls to the contractor as its own property)
5 Wages that must be paid to workers during suspension Employer GF 17.3.2(4)
6 The contractor's other suspension costs (plant standing idle, idle labour, etc. beyond wages) Reasonably shared by both parties (ratio negotiated; failing that, agreed or determined under clause 4.4) GF 17.3.2(4); 8.11.12-2 records 'the contractor's costs of suspension'
7 Costs of care, cleaning and repair of the works during suspension as required by the employer Employer GF 17.3.2(6); 8.11.12-4
8 Wages of necessary management and security personnel kept on site and of waiting workers at the employer's request Employer 8.11.12-4
9 Each party's own casualties and each party's other property losses Each party itself GF 17.3.2(3); 8.11.12-3
10 Time for completion Corresponding extension (by the actual delay on the affected critical path) GF 17.3.2(4); 8.11.12-5
11 Additional acceleration costs where the employer requires acceleration Employer GF 17.3.2(5); 8.11.12-5
12 All-risks/third-party liability insurance: insurable parts claimed from the insurers first; deductibles and amounts beyond recovery borne by each party; recoveries may be passed on to the contractor through progress payments and interim settlement by construction stage Per the insurance terms 8.11.12(1)
13 Losses enlarged by failure to take effective measures Borne by the party failing to mitigate final paragraph of GF 17.3.2
14 Force majeure encountered during delayed performance Liability for breach not relieved final paragraph of GF 17.3.2

Key sentences of the original (final paragraph of GF 17.3.2): 'Where a party has failed to take effective measures and the loss is thereby enlarged, it shall be liable for the enlarged loss'; 'where a party delays performing its contractual obligations and encounters force majeure during the delay, it is not relieved of its liability for breach'.

3. Measurement and payment of completed works and adjustment within the extended time

GF 17.3.1: 'The consequences and losses caused by force majeure are borne by the contract parties according to law and as agreed in the contract. Works completed before the force majeure shall be measured and paid as agreed in the contract.' - force majeure relieves liability for breach, not the obligation to measure and pay for completed works. GB/T 50500-2024 8.11.14: where the time for completion is extended by force majeure and, within the extension, changes in costs or in laws, regulations and policies occur, the contract prices of the affected items are adjusted under clauses 8.7, 8.8 and 8.11.9.

4. Supporting insurance (GF-2017-0201 clause 18, complementary to clause 8.11.12)

  • Unless the particular conditions provide otherwise, the employer shall insure the works under all-risks insurance for construction or erection; where the employer entrusts the contractor to insure, the premium and the related costs of insuring are borne by the employer (18.1). Unless the particular conditions provide otherwise, the contractor shall take out property insurance for its construction plant and the like (18.3).
  • Remedies for failure to insure as agreed (18.6): where the employer fails to insure or to keep the insurance in force, the contractor may insure on its behalf, at the employer's cost; where full indemnity is thereby lost, the employer makes up the shortfall. Where the contractor fails to insure or to keep the insurance in force, the employer may insure on its behalf, at the contractor's cost; where full indemnity is thereby lost, the contractor makes up the shortfall.
  • After an insured event occurs, the policyholder shall report to the insurer promptly under the conditions and time limits of the policy, and the parties shall notify each other promptly on learning of the event (18.7).

5. Attribution over time (whoever delays bears it)

  • GB/T 50500-2024 8.11.15: where a party's fault causes delay and a force majeure event occurs within the extended time, the losses from the force majeure are borne by the party responsible for the delay; where both parties are at fault for the delay, liability is borne in proportion to their responsibility; where the force majeure event occurs within the contractual time, clauses 8.11.9 and 8.11.12 apply.
  • 8.11.13 (exceptional events of a force majeure nature): riots, commotions and similar events (excluding those occurring at the site), stoppage/suspension (deferred) construction, interrupted construction or regional construction control required by state or local government authorities, stoppage required by safety and environmental protection requirements, and stoppage required by public health and epidemic control - where these cause delay, the affected time is extended accordingly and the employer and the contractor each bear their corresponding losses. The clause opens with 'except as otherwise agreed in the contract and as provided in paragraphs 4 and 5 of clause 8.11.12 of this standard', i.e. paragraph 4 of 8.11.12 (care, cleaning and repair costs and the wages of necessary personnel kept on site at the employer's request borne by the employer) and paragraph 5 (corresponding extension of time, and acceleration costs where the employer requires acceleration, borne by the employer) still apply to these exceptional events.

6. Conditions for termination and payment after termination (GF-2017-0201 clause 17.4)

Where force majeure prevents performance of the contract continuously for more than 84 days or cumulatively for more than 140 days, both the employer and the contractor may terminate the contract. After termination the parties agree or determine under clause 4.4 [agreed or determined] the amounts the employer shall pay, comprising: (1) the price of the work the contractor completed before termination; (2) the price of materials, construction equipment and other goods ordered for the works and already delivered to the contractor, or which the contractor is under an obligation to accept; (3) costs arising where the employer requires the contractor to return goods or terminate purchase contracts, or losses where return or termination is impossible; (4) the contractor's costs of leaving the site and dismissing its personnel; (5) other amounts payable to the contractor under the contract before termination; (6) less the amounts the contractor owes the employer under the contract; (7) other amounts agreed or determined by the parties. Unless the particular conditions provide otherwise, the employer shall complete payment within 28 days after these amounts are agreed or determined.

Applicable boundaries

  • Contract prevails: the above is the fallback where the contract is silent or unclear. GB/T 50500-2024 is a recommended national standard; clause 8.11.12 is prefaced 'except where the contract provides that the employer insures against all risks for the works and third-party liability and/or otherwise agrees'. GF-2017-0201 is a model text; it binds the parties only if adopted and implemented through the particular conditions. A clause of the 'all risks are borne by the contractor' kind cannot displace the statutory sharing that applies to force majeure.
  • The ratio for 'reasonable sharing of the contractor's suspension costs' is not quantified by the standard - it must be negotiated or agreed/determined under clause 4.4, failing which clause 20 [dispute resolution] applies; the claiming party must separately prove that portion of the loss (quantification of idle labour and idle plant).
  • Insurance coverage affects sharing: where the contract has the employer insure all risks for the works and third-party liability, the insurance recovery comes first, and only deductibles and the excess beyond recovery fall back to the sharing table; where the contract has the employer insure the contractor's plant, the employer claims from the insurer, but the deductible and excess remain the contractor's responsibility.
  • Riots and commotions occurring outside the site are not exceptional events under 8.11.13; those occurring on site follow the general rule of 8.11.12.
  • The contractor's own plant, preliminaries facilities, own casualties and own other property are not shifted to the employer merely because the event is force majeure.
  • This card covers only 'recognition and sharing'; the procedural chain from timely notice, interim reports and the final report through claim submission, review and reply, confirmation, signing and payment (clause 17.2, clause 19, GB/T 50500-2024 clauses 8.11.3/8.11.5/8.11.21) is covered by a separate card.

Further reading

GF-2017-0201 Model Construction Contract, general conditions: clause 17.1 [confirmation of force majeure], 17.2 [notice of force majeure], 17.3.1, 17.3.2 [consequences of force majeure], 17.4 [termination for force majeure], with clauses 18.1/18.3/18.6/18.7 [insurance], clause 4.4 [agreed or determined] and clause 20 [dispute resolution]. GB/T 50500-2024 clause 8.11.12 (sharing of force majeure losses and costs), 8.11.13 (exceptional events of a force majeure nature), 8.11.14 (cost and policy changes during extended time), 8.11.15 (force majeure after delay), with clause 8.7 (changes in costs), clause 8.8 (changes in laws, regulations and policies) and clause 8.11.9.

Keywords

  • 不可抗力
  • 损失分担
  • 工期顺延
  • costs of suspension
  • 赶工费用
  • 保险配套
  • 解除合同条件
  • GB/T 50500-2024 第8.11.12条