Panorama of suspension cost items for non-contractor-caused stoppages (T/YJXB 0001-2023: protection / standstill / wages / management / profit / demobilization / price rises / statutory fees)
For non-contractor-caused stoppages, the contractor may claim suspension costs (= cost increases + reasonable profit): completed-works protection (only if measures taken), construction machinery standstill, on-site production worker wages (only if actually paid), reasonable suspension management fees (not above normal, not zero), reasonable suspension profit, suspension demobilization (generally > 30 days), labor/machinery price rises where the extension crosses them, and increased statutory fees. Attribution follows the contract first; employer-caused stoppages are borne by the employer (GB/T 51262-2017 §5.8.3).
Applicable Codes
- T/YJXB 0001-2023 第2.0.1、4.0.1~4.0.22条
- GB/T 51262-2017 第5.8.3条
- GB/T 50500-2024 第8.11.9、8.11.12条
Topic Positioning
A panorama of the cost items a contractor may claim during non-contractor-caused stoppages, per T/YJXB 0001-2023, Chapter 4.
Core Conclusions
Suspension costs = cost increases + reasonable profit (the standard's "costs" include profit). Claimable: (1) completed-works protection — only where protective measures were actually taken (§4.0.1); (2) construction machinery standstill — rental of retained machinery or standstill losses of owned machinery (§4.0.3); (3) on-site production worker wages — only where actually paid (§4.0.5); (4) reasonable suspension management fees — management not dispersed computed per actuals, not above the normal period and not zero (§4.0.8); (5) reasonable suspension profit (§4.0.9); (6) suspension demobilization costs — demobilizing after prolonged stoppage (generally > 30 days) to avoid enlarged losses, outside the project price (§4.0.12); (7)(8) labor and machinery price rises encountered where the stoppage-induced extension crosses them (§4.0.18/4.0.20); (9) increased statutory fees (§4.0.22). Attribution (GB/T 51262-2017 §5.8.3): contract agreement first; employer-caused stoppages borne by the employer (protection, custody, machinery rental, worker and manager wages, resumption preparation, etc.); contractor-caused self-borne.
Applicable Boundaries
Applies to non-contractor-caused suspension claims; each item presupposes actual occurrence; subject to the mitigation duty, evidence, and the 28-day claim procedure; this card is a panorama — item-specific rules in the dedicated cards.
Further Reading
T/YJXB 0001-2023, Clause 2.0.1 and Clauses 4.0.1-4.0.22; GB/T 51262-2017, Clause 5.8.3; GB/T 50500-2024, Clauses 8.11.9, 8.11.12.
Keywords
- costs of suspension
- 非承包人原因停工
- 机具停滞费
- time-related overheads during suspension
- 停工利润
- 撤场费
- protection of completed works
- 人工涨价费
- 规费增加费