Calculation rules for construction equipment standby (downtime) fees, mobilization/demobilization fees, and erection/dismantling fees
Standby fee = depreciation + labor + other costs (excluding overhaul, maintenance, power); mobilization/demobilization falls into three classes: self-propelled machines—none; light machines—amortized into shift rates; large machines—separately listed per "machine x trip" (total = trips x quantity x all-in unit rate, including erection/dismantling + loading/haulage + fixed device erection/dismantling); erection/dismantling fee: not charged for machines needing none, amortized into shifts for simple ones as "budget price x coefficient / total durable shifts," listed separately for complex ones; rental equipment pricing must be agreed by owner and contractor, avoiding double counting.
Applicable Codes
- TB/T 10814-2024 铁路工程施工机具台班费用定额
- GB/T 50500-2024 建设工程工程量清单计价标准
- 山东省建设工程施工机械台班费用编制规则
- 湖北省建筑安装工程费用定额(2024)
Topic Positioning
This card covers the charging basis and formulas for three special construction equipment costs—standby (downtime) fee, mobilization/demobilization (off-site haulage) fee, and erection/dismantling fee—applicable to claim pricing, preliminary-item pricing, and understanding shift-rate quotas.
Core Conclusions
- Standby fee: costs during downtime not attributable to the machine itself, charged as "standby fee = depreciation + labor + other," excluding overhaul, maintenance, and power; maintenance already covers "downtime maintenance" within the shift rate—no double counting; if the operator leaves site during downtime, labor is not counted.
- Mobilization/demobilization in three classes: machines needing no erection/dismantling, self-propelled, or fixed in position—no off-site haulage fee; light machines with simple erection/dismantling but needing crane/transport assistance—amortized into the shift rate; large machines (tower cranes, piling rigs, etc.)—listed separately, measured per "machine x trip," total = trips x quantity x all-in unit rate, comprising erection/dismantling + loading and haulage (incl. one haulage within 25km) + erection/dismantling of fixed devices; same-type machines at different prices are listed separately.
- Erection/dismantling fee in three classes: not charged for machines needing none; simple ones amortized into the shift rate as "erection/dismantling fee = budget price x erection/dismantling coefficient / total durable shifts"; complex ones (tower cranes, shields, etc.) not covered by quotas—listed per actual scheme, including labor, materials, machinery, trial runs, and amortized erection/dismantling of auxiliary facilities.
- Rental machines: the rental mode must be agreed between owner and contractor; where the lease already includes mobilization/erection-dismantling, avoid double counting.
Applicable Boundaries
The above is the general basis, applicable to railway, highway, building, and other shift-rate quota systems; parameters such as residual-value rate, erection/dismantling coefficient, and maintenance coefficient follow the appendices of each regional shift-rate quota and vary by region; where the contract stipulates standby fees, the contract governs.
Further Reading
See TB/T 10814-2024 Quota for Shift Rates of Construction Machinery and Tools in Railway Works, Articles 1.0.4-1.0.6 (shift-rate composition, three erection/dismantling fee classes and formula, residual-value rate); Shandong Compilation Rules for Construction Equipment Shift Rates, Article 4.4 (three types of erection/dismantling and off-site haulage) and Article 6.0.1 (standby fee formula); GB/T 50500-2024 Appendix E.3.4 (breakdown table for large equipment mobilization and erection/dismantling costs); Hubei Expense Quota (2024) (rental equipment pricing and material price adjustment clauses).
Keywords
- 停置费
- 停滞费
- 进出场费
- 安拆费
- 场外运费
- 机械停滞费
- plant rate per machine-shift
Cited By
- ←
Pricing-form determination and machine-shift rate value for site-owned diesel generator sets: own units by machine-shift (TB/T 10814-2024 power machinery items 9101243/9101253 plus Appendix A base data), leased units by certified rent, standby non-running units by idle cost (depreciation plus labour plus others), and the boundary against permanent-equipment procurement and installation (TB/T 10833-2024 JY-260 to JY-267)
One generator set takes exactly one pricing channel: (1) own units enter the plant and small tools cost as quota machine-shift consumption x machine-shift rate (TB 10801-2024 clause 3.3.2; the rate set under TB/T 10814-2024, its seven components in clause 1.0.4); (2) leased units are certified on actual rent with the lease contract and rental settlement - 'use of leased construction machinery requires agreement between Employer and Contractor' - and idle cost for leased units also follows the actual rental; (3) emergency standby units that never run take no operating machine-shift, only idle cost = depreciation plus labour plus other charges (no overhaul, maintenance or power). Railway diesel generator sets are graded in TB/T 10814-2024 chapter 2 section 2 (power machinery) by capacity with computer codes (300 kW = 9101243, 500 kW = 9101253; fifteen grades from 120 to 1000 kW); depreciation, overhaul, maintenance and erection/dismantling derive from the Appendix A budget prices, residual value rates, total durable machine-shifts and three coefficients; as permanent equipment the set runs equipment procurement plus installation cost (TB/T 10833-2024 volume 12, JY-260 to JY-267), mutually exclusive with the construction-machinery machine-shift rate.
- ←
Suspension of the works in four categories (employer-caused / contractor-caused / force majeure / government-ordered suspension): comparison of cost treatment - entitlement rules for personnel wages, time-related overheads during suspension, idle plant costs and suspension profit, extension of time and evidentiary requirements (clause-level comparison)
Suspension is classified by responsible party into three categories, with administrative suspension listed separately. (1) Employer-caused (GB/T 51262-2017 clause 5.8.3 item 2; GB/T 50500-2024 clauses 8.11.9/8.11.10): workers' wages, reasonable time-related overheads during suspension, idle plant costs, and the costs of protection, safekeeping and resumption preparations are all recoverable, profit may additionally be claimed, and time is extended. (2) Contractor-caused (clause 5.8.3 item 3; clause 5.7.4 item 2): all costs are self-borne with no extension of time, and T/YJXB 0001-2023 clause 1.0.3 expressly excludes such pricing. (3) Force majeure (GB/T 50500-2024 clause 8.11.12): losses are allocated by statute - only 'the wages of necessary management and security personnel required by the employer to remain on site and the wages of idle workers', together with the costs of care, clearance and repair and the acceleration costs, fall on the employer, while damage to construction plant and the suspension losses fall on the contractor; time is extended. (4) Government-ordered suspension (clause 8.11.13): time is extended and each party bears its own losses, with Section 8.8 policy-based price adjustment and clause 8.11.12 items 4 and 5 retained as exceptions. Each cost item is calculated under T/YJXB 0001-2023 Chapter 5 on the principle of 'actual-expenditure method first, rule-and-standard method as fallback', with evidence prepared under clauses 6.0.3/6.0.5/6.0.8/6.0.9.
- ←
Liability and pricing basis for plant standby (idle machine-shift) costs: a comparison of four scenarios, employer-caused, contractor-caused, force majeure and abnormally adverse weather, with the code and contract clause authority and the rate-reduction rules for standby machine-shifts
Who bears the plant standby cost is decided by who caused the standstill, not by whether the plant stands on site: for an employer-caused standstill the employer bears the cost and profit may additionally be claimed (GB/T 50500-2024 Articles 8.11.9 and 8.11.10; GF-2017-0201 clause 7.8.1); for a contractor-caused standstill the contractor bears it alone (GB/T 51262-2017 Article 5.8.3 paragraph 3; T/YJXB 0001-2023 Article 1.0.3); under force majeure, 'damage to the contractor's construction plant and its costs of suspension' are borne by the contractor while the time for completion is extended (Article 8.11.12 paragraphs 2 and 5); abnormally adverse weather follows the contract, the extra cost of reasonable measures being borne by the employer (GF-2017-0201 clause 7.7). In pricing, the standby machine-shift rate = depreciation + labour cost (idle machine operators) + other charges, excluding overhaul, maintenance and fuel and power, with no uniform percentage discount.
- ←
Organising evidence for suspension cost claims: itemised proof lists for labour, plant and overheads, and the three conditions of an established claim (T/YJXB 0001-2023 Chapter 6; GB/T 50326-2017 Article 7.5.8)
A suspension cost claim must satisfy three conditions at once: claiming per the contract (failing or unclear terms, per laws and regulations), collecting claim materials comprehensively, and giving notice of claim intention and the report within the agreed or statutory periods - the three indispensable conditions (GB/T 50326-2017 Article 7.5.8). Proof is itemised by cost: production workers' wages need minutes, construction logs, labour / service contracts, attendance sheets, payroll, payment records and site clock-ins, plus proof of the necessity and objectivity of the wages having to be paid; plant standby needs entry / exit acceptance sheets, hire contracts, plant lists, hire settlements and reconciliation statements; suspension overheads need documents proving total overheads and contract duration - tender documents, budgets, drawings, contract - and one must provide sufficient evidence of the overhead amount for each day (T/YJXB 0001-2023 Articles 6.0.5, 6.0.3, 6.0.8). Where site certifications exist they govern (Article 3.0.3).
- ←
Fixing the rent-commencement point in leases of tower cranes and other construction hoisting machinery, and the nature of the charge for the delivered-but-not-installed period: rent versus occupation charges, three fault scenarios, points of proof, and the Civil Code and Decree No. 166 basis
Rent is consideration for use and income (Civil Code Arts. 703 and 708), and under Art. 16 of the Rules on Safety Supervision and Administration of Construction Hoisting Machinery (MOC Decree No. 166) such machinery may not be used before passing acceptance, so the period when the machine is on site but not installed, tested or accepted in principle carries no rent: where the delay is the lessor's, no rent accrues and delay damages may be claimed on top; where it is the lessee's, only a machinery occupation or custody charge runs (depreciation or a set proportion of the daily rate + on-site custody and watchkeeping labour + capital occupation, excluding power and maintenance costs); where neither party is at fault, the loss is shared per the agreement or by equity. With no agreement, rent starts on the day the machine is installed, tested, accepted and fit for use; 'rent from delivery' stands only where the contract expressly says so and the machine was ready for installation on schedule. On proof, the delivery receipt evidences only transfer of possession and the start of custody, not the rent-commencement date; the start and rent-free periods must be proved by chaining installation records, the supervision-inspection report, the acceptance form and the use-registration date.
- ←
Start and end dates for calculating standby rent and standby costs of standing construction plant (hired or owned): to which date they run absent a demobilisation site record, the presumption of the due demobilisation date, and the boundary set by the duty to mitigate
Absence of a demobilisation site record does not defeat the standby-cost claim; it only changes the mode of proof (T/YJXB 0001-2023, Art. 3.0.3: a site record governs where one exists; otherwise the standard applies). Standby rent claimable against the employer runs to the earlier of the 'actual demobilisation date' and the 'due demobilisation date': the due date = suspension date + about 30 days + a reasonable removal period (Art. 4.0.12 takes 'a fairly long suspension, generally more than 30 days' as the yardstick for when demobilisation should occur); where the employer instructs in writing that plant remain on site or demobilisation is objectively impossible, the boundary is the date the instruction ends or the actual demobilisation date; any overstay beyond that is enlarged loss under Article 591 of the Civil Code, borne by the contractor itself. Towards the lessor, rent runs under the hire contract until the plant is actually returned.
- ←
The turnover-material supplement for works suspended on site: definition, scope limits and the two calculation bases of hired versus owned (T/YJXB 0001-2023 clause 4.0.4)
Turnover materials of the contractor remaining on site during suspension earn a turnover-material supplement (T/YJXB 0001-2023 clause 4.0.4). Turnover materials are those usable repeatedly while keeping their form and transferring value gradually - chiefly forms, square timbers, steel pipes, clips and jacks; in that standard the term covers only turnover materials serving scaffolding works and concrete formwork and supports (falsework), excluding the pipes and clips of HSE provisions. Hired turnover materials charge the hire payable over the suspension per the hire contract; owned materials incur standby costs over the suspension, computed by reference to the relevant documents.
- ←
Determining plant and small tools cost within the all-in unit rate: consumption × plant rate per machine-shift, 7-item/4-item composition of the plant rate per machine-shift, and adjustment for price differentials
Plant and small tools cost = construction machinery usage cost + construction instrument and meter usage cost, both determined as machine-shift consumption under quota norms (prescribed resource consumption standards) × plant rate per machine-shift (GB/T 51095-2015 Clause 5.3.9; TB 10801-2024 Section 3.3). The plant rate per machine-shift for construction machinery has 7 items = depreciation + overhaul + maintenance + assembly and disassembly + labour + power + other costs; the plant rate per machine-shift for instrument and meter has 4 items = depreciation + maintenance + verification + power; both are computed on an 8-hour working shift. Where machine-shift cost quota norms exist, take the price per the quota norms (railway TB/T 10814-2024, base-period price excluding deductible input value added tax (VAT)); the difference between base period and compilation period is listed as an adjustment for price differentials of plant and small tools cost. When fuel and power prices fluctuate beyond the agreed risk band (no-adjustment tolerance, e.g. ±5%; where not agreed, 5%), price adjustment (for fluctuation) applies; the price difference carries VAT only, with no management fee or profit (GB/T 50500-2024 Clauses 8.7.2, 3.3.5).
- ←
Dividing the cost boundaries of vertical transport (011703), super-high construction increase (011704) and entry-exit and erection/dismantling of large plant and machinery (011705), with tests against double counting, the eave-height and storey thresholds, and the quota chapter mapping
The three charges have three different cost objects. Vertical transport (011703) covers the machine-shifts of large vertical-transport plant and the attendant labour (measured by gross floor area or by the calendar days of the construction period). Super-high construction increase (011704) covers only the efficiency loss, the pressurisation pump machine-shifts and the vertical communication caused by excessive height (measured by the gross floor area of the super-high portion), and does not count the machinery machine-shifts again. Entry-exit and erection/dismantling of large plant and machinery (011705) is a one-off charge for machinery transport and transfer and for erection and dismantling, counted by the number of machines (machine-trips); tower crane and hoist bases and track laying and removal are counted separately. The super-high increase is triggered where the eave height of a single-storey building exceeds 20m or a multi-storey building exceeds 6 storeys (basement storeys not counted); reaching either the height or the storey criterion suffices.
- ←
Determining whether vertical transport preliminaries double count the machine-shift rates of tower cranes and builder's hoists: the BOQ item coding basis, the inclusion and exclusion boundaries in provincial consumption quota chapter notes, and a method of checking whether the plant rate is included or excluded via the machine-shift content and unit of measurement of quota line items
No double counting. The machine-shift running rates of tower cranes and builder's hoists are already embedded in the pricing of the vertical transport preliminary item (GB/T 50854-2024 Table R.1.1 preliminary items, code 011601; former GB 50854-2013 Table S.3, code 011703); the vertical transport charge is the very pricing carrier of those machine-shifts, and no separate 'tower crane machine-shift charge' or 'builder's hoist machine-shift charge' may be listed. Only the parts expressly excluded by the quota chapter notes may be priced separately: off-site transport of plant, first-time erection and dismantling, subgrade bedding, track laying and removal, plus the foundations of tower cranes and hoists and the connections of cranes and hoists to the building. Determination uses a three-step check: read the inclusion and exclusion lists in the chapter notes -> check whether the labour, material and plant columns of the line item already list those machine-shifts -> check the unit of measurement and pricing basis (pricing per gross floor area is a lump-sum basis; pricing by hired machine-days must not also be charged by area).
- ←
Calculation of plant standby costs when the works stand suspended for reasons attributable to the employer: standby cost = standby rate per machine-shift x number of standby machine-shifts, the cost components of the standby machine-shift rate, whether overheads and profit are taken, and the difference in compensation scope between contractor-owned plant (priced on machine-shift rate norms) and hired plant (priced on hire charges)
Plant standby cost = sum of (standby rate per machine-shift x number of standby machine-shifts); the number of standby machine-shifts is fixed as 'idle plant units x days of suspension x machine-shift conversion factor per day (an 8h working day = 1 machine-shift per unit per day)'. Under T/YJXB 0001-2023 Clause 5.0.3: hired plant is priced on the hire charges actually incurred during the suspension, and contractor-owned plant on the machine-shift rate norms. The standby rate per machine-shift is built up from depreciation + labour cost + other charges (the Shandong and Jiangsu scope); the Hunan scope takes machine-shift depreciation only, with idle operator and banksman costs calculated separately per certified site records; repair, maintenance and power charges are excluded. The standby rate carries no uplift for overheads or profit; where the employer is liable, profit may be claimed separately under GB/T 50500-2024 Clause 8.11.10 (listed alone under the suspension-profit rule, not duplicated inside the machine-shift rate).
- ←
Computing and compensating suspension and idle-resource losses caused by the employer: idle labour costs, plant standby costs (hired vs owned plant), suspension overheads and suspension profit
Where the employer causes the suspension, the employer bears the costs (GB/T 51262-2017 Article 5.8.3); the contractor may claim, under GB/T 50500-2024 Article 8.11.9, idle costs of mobilised labour, losses of mobilised materials, plant standby costs and other losses, and Article 8.11.10 allows a further profit claim for employer-fault causes (including suspension and failure to resume on time). Computation per T/YJXB 0001-2023: the actual-outlay method first for wages with the rule-based method as fallback, and outlays objectively unnecessary are not counted (5.0.5 / 4.0.5); plant standby costs - hired plant at the hire charges actually incurred, owned plant at the machine-shift quota (5.0.3); suspension overheads = daily overheads (total contract overheads / contract duration) x reasonable ratio x suspension days, neither above normal construction nor zero (5.0.8 / 4.0.8); suspension profit = daily profit x reasonable ratio x suspension days, being loss of expectation interest (5.0.9 / 4.0.9).
- ←
Claimable scope and profit-claim boundary under GB/T 50500-2024: the nine event classes of Article 8.11.9 with the four-way split of suspension losses, the eight employer-fault situations where Article 8.11.10 adds profit, and the independent-assessment rule for EOT claims in Article 8.11.7
GB/T 50500-2024 Article 8.11.9 lists nine claimable event classes for non-contractor causes (losses of labour, materials, plant and utilities from stoppage, waiting and reduced efficiency; direct costs of cost fluctuation from programme adjustment; site-protection measures on suspension and resumption; direct costs of rework, alteration and scrapped materials; extra inspection and testing costs; losses from price not paid as agreed; suspension effects from unearthing antiquities; other provable losses and VAT; and reasonable extension of time), with suspension losses split into idle labour, unusable mobilised materials, plant standby and other losses; save as the contract provides otherwise, only claims arising from the employer's breach may include profit (Article 8.11.10 lists eight such situations), losses caused by government authorities being borne by each party with time extended accordingly.
- ←
Deciding when large plant mobilisation and erection charges are priced separately, and the cost make-up (with quota item codes, trip counts and haul-distance rules)
Large-plant mobilisation and erection charges follow a three-type test: plant needing no erection, self-moving or fixed in position is uncounted; light plant with simple erection but needing cranes and transport to move is spread into the machine-shift rate (erection charge = budget price x erection coefficient / total durable machine-shifts); heavy plant with complex erection and crane / transport moves (tower cranes, builder's hoists, shields) is itemised per machine per trip and computed separately. The same sum must not be counted both in the machine-shift rate and as preliminaries; tower crane and builder's hoist bases and ground improvement are charged separately. Codes: building 011601, structures 070304, landscape 050404, urban rail per GB/T 50861-2024 Appendix M M.2.4.
- ←
Deciding the settlement of tower-crane base, erection-and-dismantling and off-site transport charges (including where the tower crane was never installed): three charges kept in separate accounts + the "charge as actually incurred" principle + recomputation of preliminaries at final account under BOQ pricing
The tower-crane base is a plant machine-shift "separately computed charge" - in neither the machine-shift rate nor the erection-and-dismantling charge - measured on the physical work actually completed. Erection-and-dismantling is a one-off charge per erection and dismantling (including trial running), counted per actual set-ups and not counted where none occurred. Off-site transport is counted per set-up and generally once per project location. Piling under the base, ground improvement and floor strengthening are outside the items and follow the construction method statement or actual occurrence. At final account of BOQ-priced works the preliminaries are recomputed per GB/T 50500-2024 clauses 10.3.3 and 10.2.7, charging only "the full preliminaries contained in the completed works"; amounts listed in interim (process) settlements do not bind and adjust up or down on recomputation - where the tower crane was never installed, the corresponding preliminaries are reduced.
- ←
Claiming idle-labor and standstill machinery losses after cancellation of business-line construction plans (blockades/windows): elements, cost composition, calculation, procedure and time limits
Where a business-line blockade/window plan is cancelled for reasons not attributable to the contractor, the contractor may claim idle-labor costs and machinery standstill costs: rented machinery at actual rent, owned machinery at machinery-shift cost quotas (T/YJXB 0001-2023, Clause 5.0.3); costs include idle labor, management and protection staff wages, materials/equipment safekeeping, resumption-preparation costs, etc. (GB/T 51262-2017, Clause 5.8.3); three elements must be met — direct loss + non-contractor cause + claim pursued per procedure (TB 10402-2019, Clause 9.3.1); notice of claim within 28 days, claim report within a further 28 days (GB/T 50500-2024, Clause 8.11.3).
- ←
Work suspension caused by suppliers' delayed delivery: the contractor's loss composition, calculation methods, and legal boundaries (T/YJXB 0001-2023)
A supplier's delayed delivery is a breach of the sales contract; suspension losses are calculated item by item as "idle labor + plant standby + material losses + suspension management fee + suspension profit + site maintenance + increased statutory fees": the actual-expenditure method first, the rule-standard method as fallback (T/YJXB 0001-2023, Chapters 4, 5; GB/T 50500-2024, Clause 8.11.9). Claims are triple-limited by the Civil Code's foreseeability rule (Article 584), the duty to mitigate (Article 591), and the evidence chain, and the contractor simultaneously runs the 28-day extension procedure with the employer.
- ←
Panorama of suspension cost items for non-contractor-caused stoppages (T/YJXB 0001-2023: protection / standstill / wages / management / profit / demobilization / price rises / statutory fees)
For non-contractor-caused stoppages, the contractor may claim suspension costs (= cost increases + reasonable profit): completed-works protection (only if measures taken), construction machinery standstill, on-site production worker wages (only if actually paid), reasonable suspension management fees (not above normal, not zero), reasonable suspension profit, suspension demobilization (generally > 30 days), labor/machinery price rises where the extension crosses them, and increased statutory fees. Attribution follows the contract first; employer-caused stoppages are borne by the employer (GB/T 51262-2017 §5.8.3).
- ←
Railway 2024 quota norms: erection/dismantling and commissioning of large plant (special line items GY-1~GY-5) versus plant rate per machine-shift and plant entry/exit cost — boundary rules: erection/commissioning must be booked separately, entry/exit must not, and the three never overlap
Under the railway 2024 quota norms (TB/T 10825-2024, TB/T 10814-2024, TB 10801-2024, effective 2025-01-01), for large plant such as track-laying machines and rail-welding trains: (1) erection/dismantling and commissioning must be booked separately via the special line items GY-1~GY-5 of "Section 1: erection/dismantling and commissioning of large plant", Chapter 1 of the track works quota manual, measured per "occurrence", listed independently (composite preliminary estimate/budget chapter table, Chapter 1 track laying, (9)); (2) plant entry/exit cost is not booked separately — contractor entry/exit and site-transfer costs are already inside the on-costs (indirect costs) item of overheads (company and site) (base (base-period labour cost + base-period plant and small tools cost) x on-cost percentage rate), and must not appear as a separate line; (3) no overlap with plant rates per machine-shift — decision rule: where the erection/dismantling column of the shift-cost norms (TB/T 10814-2024) reads "book separately" or "—" (long-rail flash-butt welding line 9114095 "book separately"; welding trains 9114091/9114092 etc. "—"), the cost is landed via the GY line items, booked separately without duplication; where the column carries a specific amount (e.g., long-rail flat wagon 9114081, 5.21 yuan/machine-shift), it is already amortized in the plant rate per machine-shift and the GY line items must not be applied. For the single-sleeper-method track-laying machine, erection/dismantling and commissioning is compiled on a combined basis of 60% major dismantling and 40% minor dismantling of the machine set, with no adjustment for the actual dismantling mode when the line item is applied.
- ←
Composition and pricing rules of the variable costs in highway plant shift prices (JTG/T 3833-2018, items 5-7)
Per the general notes of the "Highway engineering plant shift-cost quota" (JTG/T 3833-2018), items 5-7 of the 7 cost components of a plant shift price are variable costs: labor cost (wages of operators attending the plant, incl. wages, allowances, subsidies, auxiliary wages, labor protection, etc.); power and fuel cost (electricity, solid fuels - coal/firewood, liquid fuels - gasoline/diesel/heavy oil, and water consumed in operation); vehicle and vessel tax (per state and provincial regulations). When compiling, labor and power/fuel consumptions are taken from this quota; labor and fuel unit prices are computed per JTG 3830-2018; shift prices for engineering vessels and diving equipment follow local provisions; other costs enter per annual working shifts at the standards of the provinces and departments of the State Council.