Calculation rules for construction equipment standby (downtime) fees, mobilization/demobilization fees, and erection/dismantling fees

Standby fee = depreciation + labor + other costs (excluding overhaul, maintenance, power); mobilization/demobilization falls into three classes: self-propelled machines—none; light machines—amortized into shift rates; large machines—separately listed per "machine x trip" (total = trips x quantity x all-in unit rate, including erection/dismantling + loading/haulage + fixed device erection/dismantling); erection/dismantling fee: not charged for machines needing none, amortized into shifts for simple ones as "budget price x coefficient / total durable shifts," listed separately for complex ones; rental equipment pricing must be agreed by owner and contractor, avoiding double counting.

Applicable Codes

  • TB/T 10814-2024 铁路工程施工机具台班费用定额
  • GB/T 50500-2024 建设工程工程量清单计价标准
  • 山东省建设工程施工机械台班费用编制规则
  • 湖北省建筑安装工程费用定额(2024)

Topic Positioning

This card covers the charging basis and formulas for three special construction equipment costs—standby (downtime) fee, mobilization/demobilization (off-site haulage) fee, and erection/dismantling fee—applicable to claim pricing, preliminary-item pricing, and understanding shift-rate quotas.

Core Conclusions

  1. Standby fee: costs during downtime not attributable to the machine itself, charged as "standby fee = depreciation + labor + other," excluding overhaul, maintenance, and power; maintenance already covers "downtime maintenance" within the shift rate—no double counting; if the operator leaves site during downtime, labor is not counted.
  2. Mobilization/demobilization in three classes: machines needing no erection/dismantling, self-propelled, or fixed in position—no off-site haulage fee; light machines with simple erection/dismantling but needing crane/transport assistance—amortized into the shift rate; large machines (tower cranes, piling rigs, etc.)—listed separately, measured per "machine x trip," total = trips x quantity x all-in unit rate, comprising erection/dismantling + loading and haulage (incl. one haulage within 25km) + erection/dismantling of fixed devices; same-type machines at different prices are listed separately.
  3. Erection/dismantling fee in three classes: not charged for machines needing none; simple ones amortized into the shift rate as "erection/dismantling fee = budget price x erection/dismantling coefficient / total durable shifts"; complex ones (tower cranes, shields, etc.) not covered by quotas—listed per actual scheme, including labor, materials, machinery, trial runs, and amortized erection/dismantling of auxiliary facilities.
  4. Rental machines: the rental mode must be agreed between owner and contractor; where the lease already includes mobilization/erection-dismantling, avoid double counting.

Applicable Boundaries

The above is the general basis, applicable to railway, highway, building, and other shift-rate quota systems; parameters such as residual-value rate, erection/dismantling coefficient, and maintenance coefficient follow the appendices of each regional shift-rate quota and vary by region; where the contract stipulates standby fees, the contract governs.

Further Reading

See TB/T 10814-2024 Quota for Shift Rates of Construction Machinery and Tools in Railway Works, Articles 1.0.4-1.0.6 (shift-rate composition, three erection/dismantling fee classes and formula, residual-value rate); Shandong Compilation Rules for Construction Equipment Shift Rates, Article 4.4 (three types of erection/dismantling and off-site haulage) and Article 6.0.1 (standby fee formula); GB/T 50500-2024 Appendix E.3.4 (breakdown table for large equipment mobilization and erection/dismantling costs); Hubei Expense Quota (2024) (rental equipment pricing and material price adjustment clauses).