The turnover-material supplement for works suspended on site: definition, scope limits and the two calculation bases of hired versus owned (T/YJXB 0001-2023 clause 4.0.4)
Turnover materials of the contractor remaining on site during suspension earn a turnover-material supplement (T/YJXB 0001-2023 clause 4.0.4). Turnover materials are those usable repeatedly while keeping their form and transferring value gradually - chiefly forms, square timbers, steel pipes, clips and jacks; in that standard the term covers only turnover materials serving scaffolding works and concrete formwork and supports (falsework), excluding the pipes and clips of HSE provisions. Hired turnover materials charge the hire payable over the suspension per the hire contract; owned materials incur standby costs over the suspension, computed by reference to the relevant documents.
Applicable Codes
- T/YJXB 0001-2023《建设工程停工承包人费用计算标准》第4.0.4条、第5.0.4条
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11.9条
Topic Positioning
The "turnover-material supplement" payable for turnover materials held on site through a suspension (work stoppage): the term's bounds, scope limits and the hired / owned calculation bases, per T/YJXB 0001-2023 Standard for Computing Contractor's Costs in Suspension of Construction Works, clause 4.0.4. For compiling suspension cost (loss) statements, claim pricing and review.
Core Conclusions
Clause 4.0.4 of T/YJXB 0001-2023: turnover materials of the contractor remaining on site through a suspension earn a turnover-material supplement. Key points:
- Term: turnover materials are those a contractor uses repeatedly in construction, keeping broadly their original form while transferring value gradually - chiefly forms, square timbers, steel pipes, clips and jacks.
- Scope: in this standard, turnover materials mean those serving scaffolding works and concrete formwork and supports (falsework) - NOT the pipes, clips and the like of the statutory HSE provisions.
- Why and how: hire charges usually run by time (month or day) and continue through the suspension per the contract - charge the suspension hire; even owned materials incur standby over the suspension - compute standby by reference to the relevant documents. That is: hired basis = the hire actually payable over the suspension per the hire contract; owned basis = standby computed by reference to the relevant documents.
Companion suspension-cost and claim rules (same system):
- T/YJXB 0001-2023 clause 4.0.3: construction plant and tackle held on site through suspension earn plant standby - the turnover-material supplement and plant standby are sibling suspension cost items.
- GB/T 50500-2024 clause 8.11.9: for suspension, waiting, lost efficiency or extended duration not caused by the contractor, the contractor may claim, the loss covering "the cost of materials already delivered that cannot be put to use"; GB/T 51262-2017 clause 5.8.3 lists, for employer-caused suspension, costs borne by the employer including "the custody of materials and plant delivered to site".
- T/YJXB 0001-2023 clause 1.0.3: the standard does not apply to pricing where the contractor caused the suspension; clause 3.0.9: after suspension the contractor shall mitigate - losses enlarged by inaction rest with the contractor.
Applicability Boundaries
- Only for turnover materials held on site through a suspension; contractor-caused suspensions fall outside (clause 1.0.3).
- Scope as limited: only turnover materials serving scaffolding works and concrete formwork / supports count; HSE pipes and clips are outside and earn nothing here.
- One suspension cost item among several, beside plant standby (4.0.3); cost bearing follows contract first, employer-caused on the employer, contractor under a duty to mitigate.
- Owned materials' standby "by reference to the relevant documents" - no unified formula; parameters per the location's, sector's and contract's current rules.
- This card settles the basis and chargeability only, not the compilation of turnover consumption (amortisation) quotas or formwork and scaffolding preliminaries pricing.
Further Reading
- T/YJXB 0001-2023, clauses 1.0.3 (exclusions), chapter 2 (terms), 3.0.9 (mitigation), 4.0.3 (plant standby), 4.0.4 (turnover supplement), chapter 5 (methods), chapter 6 (basis and records).
- GB/T 50500-2024 clause 8.11.9 (claims not caused by the contractor, material loss costs); GB/T 51262-2017 clause 5.8.3 (suspension claims assessment).
Keywords
- 周转材料增加费
- 停工
- 租赁费
- 停滞摊销费
- 模板
- 方木
- 钢管扣件
- 费用计算标准