Claiming idle-labor and standstill machinery losses after cancellation of business-line construction plans (blockades/windows): elements, cost composition, calculation, procedure and time limits
Where a business-line blockade/window plan is cancelled for reasons not attributable to the contractor, the contractor may claim idle-labor costs and machinery standstill costs: rented machinery at actual rent, owned machinery at machinery-shift cost quotas (T/YJXB 0001-2023, Clause 5.0.3); costs include idle labor, management and protection staff wages, materials/equipment safekeeping, resumption-preparation costs, etc. (GB/T 51262-2017, Clause 5.8.3); three elements must be met — direct loss + non-contractor cause + claim pursued per procedure (TB 10402-2019, Clause 9.3.1); notice of claim within 28 days, claim report within a further 28 days (GB/T 50500-2024, Clause 8.11.3).
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- TB 10402-2019 铁路建设工程监理规范
- T/YJXB 0001-2023 建设工程停工承包人费用计算标准
- GB/T 51262-2017 建设工程造价鉴定规范
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
- TB 10811-2024 铁路基本建设工程设计概(预)算费用定额
Topic Positioning
After a business-line (blockade/window) construction plan is cancelled, how to qualify liability, calculate costs, and claim per procedure for the idle-labor and standstill losses of personnel and machinery already mobilized — applicable to cost claims in railway business-line and adjacent-line construction contract performance.
Core Conclusions
(1) Three acceptance elements: direct economic loss already incurred + cause not attributable to the contractor (plan cancellations are usually due to operating organization/construction unit) + claim intention submitted with evidence per contract conditions, time limits, and procedures (TB 10402-2019, Clause 9.3.1); exceptions: non-provision of windows due to the contractor's own fault, or contract terms that "plan cancellation is within risk wrap-up". (2) Cost composition: idle-labor costs, on-site management and protection staff wages, rented/owned machinery standstill costs, safekeeping of mobilized materials and equipment, resumption-preparation costs, protection of completed works (GB/T 51262-2017, Clause 5.8.3). (3) Calculation calibers: rented machinery at actual rents incurred during the standstill, owned machinery at machinery-shift cost quotas of the same period (T/YJXB 0001-2023, Clause 5.0.3), labor at actual idled headcount x idle-rate standard (contract first). (4) Procedure: serve written notice of claim within 28 days of the event, then submit the claim report within a further 28 days; late submission is deemed waiver; the other party's failure to reply in time is deemed acceptance (GB/T 50500-2024, Clause 8.11.3).
Applicable Boundaries
This card is at the contract-claim level (extra losses from plan cancellation), distinct from the business-line blockade construction additional fee in estimate/budget compilation (TB 10811 Table 2.7.5 charges the normal quota efficiency loss of blockade work — do not confuse the two); not applicable to contractor-caused cases or force-majeure exemption terms; indirect losses such as profit need separate contract basis; each cancellation should be evidenced and claimed one by one.
Further Reading
Claim procedure and time limits see GB/T 50500-2024 Section 8.11; supervisor acceptance and handling see TB 10402-2019 Section 9.3 (notice of claim per Appendix C Table C.0.2, cost-claim review form per Appendix B Table B.0.15); machinery standstill calculation see T/YJXB 0001-2023 Clause 5.0.3; suspension cost bearing see GB/T 51262-2017 Clause 5.8.3; normal charging of blockade works see TB 10801-2024 Clause 3.7.6 and TB 10811-2024 Clause 2.7.5.
Keywords
- 营业线施工
- 封锁计划取消
- 天窗
- 费用索赔
- idle (standby) costs of labour and plant
- 施工机具停滞费
- costs of suspension
- 铁路