The railway estimate/budget counterparts of "construction interference fees": train-interference and business-line blockade additional fees (TB 10801-2024 / TB 10811-2024)
The railway estimate (budget) cost system has no separate "construction interference fee" item: slow running (no blockade, traffic kept running) falls under the train-interference construction additional fee (interference work-days x composite wage rate x quantity x trains per 24 h, rate 0.22%, catenary 0.30%); blockades/windows fall under the business-line blockade construction additional fee (base = compilation-period labour cost + plant and small tools cost; by work category and window of 3/4/5/6 h, Table 2.7.5 increases of 40%~200% linearly interpolated; < 3 h taken as 3 h, > 6 h not charged).
Topic Positioning
The corresponding items and complete calculation method for the "construction interference fee" in railway estimates/budgets: the charging scope, rate-table values and interpolation rules of the train-interference construction additional fee (slow running / traffic kept running without blockade) and the business-line blockade construction additional fee (blockade/window situations) (TB 10801-2024, Section 3.7; TB 10811-2024, Section 2.7).
Core Conclusions
The cost system has no separate "construction interference fee" item: slow-running cases go into the train-interference construction additional fee; blockades/windows go into the business-line blockade construction additional fee. Train-interference fee (TB 10811-2024, Clause 2.7.4): earthwork and cross-track transport = interference work-days x compilation-period composite wage rate x interfered quantity x trains per 24 h x 0.22%; catenary works 0.30%; other works 0.22%. Train counts follow the compilation-period planned diagram; unplanned transfer runs, track cars, banker locomotives and extra trains are not counted. Interference work-days per Table 2.7.4 (work-days/100 m3 natural in-situ (undisturbed) volume): excavation/loading only 15.7 soil / 7.7 rock; unloading only 6.5 / 9.9; excavate-load-unload all within the interference range 22.2 / 17.6; plane crossing of the first track 15.7 / 23.1; each additional track crossed 6.5 / 9.9. Blockade (window) fee (Clause 2.7.5): base = compilation-period labour cost + plant and small tools cost; by work category x window duration 3/4/5/6 h, read Table 2.7.5 quota increase (%) with linear interpolation: manual track lifting/laying and turnout lifting/laying 200/120/80/60; mechanical track lifting/laying and track-related works 160/100/70/50; granular ballast and ballastless bed 170/110/70/50; erecting prestressed concrete girders and overpass structures 120/70/50/40; tunnel works 190/120/80/70; catenary works 170/110/70/60; other works 1 (inside fence) 160/110/70/60; other works 2 (outside fence) 110/70/50/40. Windows under 3 h take the 3 h value; over 6 h not charged. Example: mechanical track lifting/laying with a 3.5 h window, interpolation = 160% - (160% - 100%) x 0.5 = 130%.
Applicable Boundaries
Applies only to railway estimates (budgets) compiled under the 2024 editions of the two compiling measures; the interference scope of Table 3.7.5 (on the traffic line or within 25 m horizontal distance of the traffic line centre; track and electric traction power supply including adjacent lines with line spacing <= 25 m) is a reference — investigate and determine in conjunction with operating-enterprise rules when compiling; works on lines not yet handed over to operation, and refuge/safety/storage sidings and depot tracks, do not carry interference fees; windy-sand, plateau and primeval-forest regions are environmental-factor fees, not interference; for business lines with train speeds > 200 km/h, it is not appropriate to itemise costs on the basis of an inter-train-interval construction method statement.
Further Reading
TB 10801-2024 Clauses 3.7.5, 3.7.6 and Table 3.7.5 (train-interference charging scope); TB 10811-2024 Clauses 2.7.4, 2.7.5 and Table 2.7.4 (earthwork interference work-day quotas), Table 2.7.5 (blockade construction quota increases, linearly interpolated per table notes).