Charging channels for protection personnel and protection facilities on existing (business) lines (business-line construction cooperation fee + work-safety fee + formal-works chapters)

Railway estimates (budgets) have no separate "protection fee" item: operator cooperation and safety-supervision costs go to the business-line construction cooperation fee (compilation-period labor + machinery cost x reference rates 1.1%~20.5%, TB 10811-2024 2.11.8); temporary protection facilities and safety spending go to the work-safety fee (construction-installation cost x 3.0%, usage limited to TB 10801-2024 Table 3.11.11 and not to be double listed elsewhere); permanent protection works are listed in formal-works chapters and priced by quotas.

Applicable Codes

  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
  • TB 10811-2024 铁路基本建设工程设计概(预)算费用定额

Topic Positioning

This card answers: for construction on existing (business) lines, which item protection-personnel and protection-facility costs go under in railway estimates (budgets) and how they are charged, to avoid omission or double listing.

Core Conclusions

The railway estimate (budget) cost system has no separate "protection fee" item; by cost nature there are three channels: (1) Operator cooperation personnel (station watchmen, safety supervisors, etc.) -> business-line construction cooperation fee (other costs): base = compilation-period labor cost + construction machinery cost, multiplied by reference rates by work category, mostly 1.1%~18.0% near business lines (subgrade 1.1%, bridges 3.2%, tunnels 3.6%, track 2.5%, signaling 18.0%, etc.); higher for business-line rebuilding (turnout laying 6.5%, signaling 20.5%); the computation scope is mostly within 20 m of the embankment toe/cutting crest/equipment edge, and within 1000 m for rock blasting. (2) Temporary protection facilities and safety spending (hoarding, isolation barriers, warning signs, protection communication equipment, protective gear, etc.) -> work-safety fee: charged as construction-installation cost x 3.0%, usage limited to the ten categories of Table 3.11.11; items in the table must not be double listed in other parts of the estimate (budget). (3) Permanent protection works (physical facilities set per design safety measures for operational safety) -> listed in the relevant formal-works chapters and priced by quotas as physical works. The wages of the contractor's own protection staff (site watchmen, station liaisons) are already in quota labor costs and are not listed separately.

Applicable Boundaries

All rates are reference rates — investigate per operating-enterprise rules and market factors when compiling; applies only to railway construction project estimate (budget) compilation. The work-safety fee is non-competitive and must not be a competitive bid item. The train-interference and business-line blockade additional fees charge for efficiency loss/blockade of existing-line works and belong to different items from protection fees — do not mix them.

Further Reading

TB 10801-2024 Clause 3.11.10 (business-line construction cooperation fee), Clause 3.11.11 and Table 3.11.11 (work-safety fee usage scope and no-double-listing rule); TB 10811-2024 Clause 2.11.8 Table 2.11.8 (rates by work category and computation scope), Clause 2.11.9 (work-safety fee 3.0%).