Railway 2024 quota all-in labour rate: composition, the seven base-period classes, and compilation-period labour cost price adjustment (TB 10811-2024 Table 2.1.1; TB 10801-2024 Sections 3.1/4.1)

The comprehensive labor rate comprises basic wages, allowances and subsidies, auxiliary wages of production workers, staff welfare, labor protection, the five insurances and one fund, trade-union outlays, and staff education outlays (TB 10801-2024 Clause 3.1.4); the base-period rate takes seven classes per TB 10811-2024 Table 2.1.1-1 (class I 140.11 to class VII tunnels 201.34 yuan/shift, all including the enterprise's five insurances and one fund); the compilation-period rate follows adjustment documents issued by the authorities. Labor cost = sum of (quota labor consumption x comprehensive labor rate); the compilation-period minus base-period difference is booked as a labor price difference = quota labor consumption (excluding labor inside plant shifts) x (compilation-period rate - base-period rate), entered in the item estimate (budget).

Applicable Codes

  • TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects
  • TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works

Topic Positioning

This card sets out the complete rules for the "all-in labour rate" under the railway 2024 cost standards: what cost contents it includes, the seven base-period classes by works category, special provisions such as the plateau allowance, and the method for adjusting labour cost differentials at compilation period. Based on TB 10801-2024 "Measures for compiling design estimates (budgets) of railway capital construction projects" and TB 10811-2024 "Norms for on-costs and expenses for design estimates (budgets) of railway capital construction projects".

Core Conclusions

(1) Contents of the all-in labour rate (TB 10801-2024 Clause 3.1.4): basic wages, allowances and subsidies, auxiliary wages of production workers, staff welfare, labour protection for production workers, basic pension, basic medical, work-injury, unemployment, and maternity insurance, housing provident fund, trade-union outlays, and staff education outlays. The 2024 edition folds the workers' "five insurances and one fund", trade-union outlays, and staff education outlays — formerly statutory fees — into the former labour cost, aligning the basis more closely with market prices. The clause commentary (3.1.4) flags three differences not to be simplistically compared with railway labour-market wages: (1) the all-in workday is 8 hours; (2) workers' own small tools and auxiliary materials are already in the quotas; (3) extra output achieved by labour crews through higher efficiency is paid in the estimate (budget) through extra quantities.

(2) Values (TB 10811-2024 Clause 2.1.1): the base-period all-in labour rate follows Table 2.1.1-1; the compilation-period rate follows adjustment documents issued by the authorities. Table 2.1.1-1, seven base-period rates (yuan/workday): Class I 140.11 — subgrade (excluding graded crushed stone and sand-gravel of the subgrade bed surface layer and transition sections), culverts, ordinary production buildings and appurtenances, water supply and drainage, station yards (excluding passenger subways, footbridges, canopies), spoil/rock disposal, large temporary works; Class II 143.13 — graded crushed stone and sand-gravel of the subgrade bed surface layer and transition sections; Class III 149.18 — bridges (excluding box-girder prefabrication, transport, erection, and cast-in-place, and bridge deck systems), telecommunication, signalling, information, disaster monitoring, electric power, electric traction power supply, locomotive and car depots, EMUs, track works, and other buildings and equipment; Class IV 154.88 — equipment installation works (excluding the installation works of telecommunication, signalling, information, disaster monitoring, electric power, and electric traction power supply); Class V 160.93 — box girders (prefabrication, transport, erection, cast-in-place), steel girders, steel-pipe arch erection, bridge deck systems, granular ballast, station buildings (including complexes), passenger subways, footbridges, canopies; Class VI 166.80 — track (excluding granular ballast) and the equipment installation works of telecommunication, signalling, information, disaster monitoring, electric power, electric traction power supply; Class VII 201.34 — tunnels. Table-note essentials: Note 1 — the base-period rates exclude special-region allowances and subsidies, computed per the state authorities and the province (autonomous region, municipality) and booked as a labour cost differential; the plateau wage allowance for regions at 3000 m and above takes the basic wage as its base (the basic wage being 20% of the base-period all-in rate) at the Table 2.1.1-2 percentages: 3000 (inclusive)-3500 (inclusive) m 70%, above 3500 to 4000 (inclusive) m 130%, above 4000 to 4500 (inclusive) m 185%, above 4500 m 225%; once the plateau wage allowance is booked, the region's cost-of-living allowance and hardship-area allowance are no longer booked. Note 2 — the base-period rates already include the enterprise-paid five insurances and one fund: basic pension 16%, basic medical 8%, unemployment 1%, work injury 1%, maternity 0.8%, housing provident fund 8%; the designer may adjust the compilation-period all-in labour rate per local-government standards, with the excess over the base period booked as a labour cost differential. Note 3 — transitional works use the all-in labour rate of the same class of permanent works. Note 4 — works outside the listed classes use the class I rate.

(3) Compilation-period labour cost price adjustment (TB 10801-2024 Clauses 3.1.2, 3.1.3, 4.1.2): labour cost = sum of (quota labour consumption x all-in labour rate); the compilation-period minus base-period difference is booked as a labour cost differential. Method: the quota-counted labour consumption (excluding labour inside machine-shifts) multiplied by the difference between the compilation-period and base-period all-in labour rates, computed by the designer when compiling the estimate (budget) and entered in the item estimate (budget). That is: labour cost differential = quota labour consumption (excluding in-shift plant labour) x (compilation-period rate - base-period rate) — the adjustment touches only quota labour consumption; machine-shift labour joins the plant rate per machine-shift differential line instead.

Applicable Boundaries

Applies to compiling railway design estimates (budgets) under the 2024 standards (TB 10801-2024, TB 10811-2024, effective 1 January 2025, replacing TZJ 1001-2017, TZJ 3001-2017, and other old editions). The base-period rates are a uniform national base level, excluding special-region allowances and subsidies (booked separately as labour cost differentials); compilation-period all-in labour rates follow National Railway Administration and provincial adjustment documents — this card gives no compilation-period values. The adjustment basis covers quota labour consumption only; labour inside machine-shifts does not join this line. The plateau wage allowance and the construction additional fee for plateau regions (altitude >=2000 m) are two different cost items and must not be mixed.

Further Reading

See TB 10801-2024 "Measures for compiling design estimates (budgets) of railway capital construction projects": Section 3.1 (labour cost) with the commentary on 3.1.4; Clause 4.1.2 item 1 (labour cost differential method, alongside the material and plant cost differential methods in the same clause); TB 10811-2024 "Norms for on-costs and expenses...": Clause 2.1.1 with Tables 2.1.1-1 and 2.1.1-2. Related: the plateau construction additional fee is stepped per quota workday x compilation-period all-in labour rate x workday-increase percentage (TB 10811-2024); for the old-new standards interface see National Railway Administration Announcement No. 28 of 2024 (published 25 September 2024; 18 new standards effective 1 January 2025, superseding TZJ 1001-2017 and 20 other old standards the same day).