Composition and booking of "other costs" in railway estimates (budgets) (TB 10801-2024 Clause 3.11; Chapter 11 other costs)

Other costs are "static-investment costs payable from capital construction investment and included in the project investment, other than cost of works (construction and installation), permanent equipment procurement cost, value added tax (VAT), and basic contingency" (TB 10801-2024, Clause 3.11.1), placed in Chapter 11 of the estimate (budget), with 19 sub-items (3.11.2-3.11.20). The project construction management fee, employer stamp duty and other taxes, project preliminary costs, statutory work safety levy (earmarked funds), production-preparation fee, plateau and alpine-region railway health-safeguard fee, living-supplies transport subsidy, joint commissioning and testing and related costs, etc. are expressly booked "per the Norms for On-Costs and Expenses for Design Estimates (Budgets) of Railway Capital Construction Projects, TB 10811" (rates/standards); land acquisition (lease) and demolition compensation is booked per the relevant regulations and prices of the state authorities and of the province (autonomous region, municipality) where the project is located; construction supervision fee, survey and design fee, design document review fee, other consultancy fees, third-party monitoring fee, and whole-process engineering consultancy fee — "the costs actually incurred shall be determined by the market"; foreign-capital-related costs are booked per current state regulations in combination with TB 10811; research and testing costs are booked upon approval by the construction authority.

Applicable Codes

  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法(第 2.5 节、2.6 节、3.11 条)
  • TB 10811-2024 铁路基本建设工程设计概(预)算费用定额

Topic Positioning

This card sets out the complete composition (19 sub-items) and booking-mode classification of "other costs" under Clause 3.11 of the Measures for Compiling Design Estimates (Budgets) of Railway Capital Construction Projects, TB 10801-2024: which items are booked by on-cost norms/rates and which by actual occurrence/market/government-set prices — for quick location of the pricing basis during compilation, review and Q&A on estimates (budgets).

Core Conclusions

Definition (3.11.1): other costs are "static-investment costs payable from capital construction investment and included in the project investment, other than cost of works (construction and installation), permanent equipment procurement cost, value added tax (VAT), and basic contingency". They are placed under Chapter 11 "other costs" of Part 1, static investment, and map one-to-one to the "other costs" branch of the cost-composition diagram in Clause 2.6.1.

The 19 sub-items (3.11.2-3.11.20): land acquisition (lease) and demolition compensation; project construction management fee; employer stamp duty and other taxes; project preliminary costs; construction supervision fee; survey and design fee; design document review fee; other consultancy fees; in-service line construction cooperation fee; statutory work safety levy (earmarked funds); research and testing fee; joint commissioning and testing and related costs; foreign-capital-related costs; production-preparation fee; third-party monitoring fee; plateau and alpine-region railway health-safeguard fee; living-supplies transport subsidy; whole-process engineering consultancy fee; other related costs.

1. Booked by on-cost norms/rates ("per TB 10811"):

  • Project construction management fee (3.11.3), employer stamp duty and other taxes (3.11.4), project preliminary costs (3.11.5), statutory work safety levy (3.11.11), production-preparation fee (3.11.15 — comprising production staff training, office and living furniture purchase, and tools and production furniture purchase), plateau and alpine-region railway health-safeguard fee (3.11.17), living-supplies transport subsidy (3.11.18): all expressly "per the Norms for On-Costs and Expenses for Design Estimates (Budgets) of Railway Capital Construction Projects, TB 10811".
  • Joint commissioning and testing and related costs (3.11.13): static inspection fee, joint commissioning and testing fee (dynamic detection and testing + cooperation fee), safety assessment fee, electricity fee, operation trial fee, comprehensive inspection-train overhaul cost, etc.; "computed per TB 10811". Locomotives, cars and inspection vehicles used for tests during joint commissioning are provided by the operator "without depreciation"; emergency repair materials are provided by the project owner, paid provisionally from the materials advance, and settled per actuals.
  • In-service line construction cooperation fee (3.11.10): base = compilation-period labour cost + compilation-period plant and small tools cost, multiplied by the TB 10811 reference rate.

2. Booked by actual occurrence/market/contract/government-set prices:

  • Land acquisition (lease) and demolition compensation (3.11.2): land acquisition compensation, demolition compensation, temporary land use, soil-and-water conservation compensation, etc. "in accordance with the construction land areas and relocation quantities proposed by the design, and the relevant regulations and prices of the state authorities and of the province (autonomous region, municipality) where the project is located"; land acquisition and demolition working expenses, land boundary survey fee, land pre-examination fee, forest vegetation restoration fee, mineral-overburden compensation, grassland vegetation restoration fee, wetland restoration fee, etc. "per the relevant regulations and prices of the state and of the province (autonomous region, municipality) where the project is located".
  • Construction supervision fee (3.11.6), survey and design fee (3.11.7), design document review fee (3.11.8), other consultancy fees (3.11.9): "may be computed (applied) per TB 10811; the costs actually incurred shall be determined by the market". Other consultancy fees cover 14 items: tendering consultancy, survey supervision and consultancy, equipment (material) procurement inspection, construction-drawing review (verification), third-party price audit, environmental-protection special supervision, soil-and-water conservation monitoring, blasting-safety supervision, track-laying condition assessment, environmental-protection facility acceptance report, soil-and-water conservation facility acceptance report, occupational-hazard control effect evaluation, third-party testing, and computer software development and purchase.
  • Third-party monitoring fee (3.11.16): "shall comply with the relevant state regulations; the costs shall be booked by analysis of the design monitoring scheme; the costs actually incurred shall be determined by the market".
  • Whole-process engineering consultancy fee (3.11.19): may be booked separately; the costs actually incurred shall comply with the relevant state regulations and be determined by the market; "when booked separately, the corresponding consultancy costs of the individual services must not be double-counted".
  • Foreign-capital-related costs (3.11.14): booked per current state regulations and the requirements of the foreign lending institution, in combination with TB 10811.
  • Research and testing fee (3.11.12): booked per the research and testing content and requirements proposed by the design, upon approval by the construction authority.
  • Other related costs (3.11.20): costs that, beyond the above, should be included in the design estimate (budget) per the regulations of the state, the relevant ministries and the province (autonomous region, municipality) where the project is located; estimated costs of special works treatments that cannot be accurately determined at the design stage; and royalties for railway patents and know-how and related financial costs of payment guarantees, etc.

Applicable Boundaries

  • Applies to the compilation and review of design estimates (budgets) for railway capital construction projects (new build, reconstruction, expansion); other costs are static investment and exclude dynamic investment (price fluctuation provision, investment loan interest during construction), locomotive and car (EMU) procurement, and initial working capital.
  • This card locates only the composition and booking modes; rates/indices are found in the companion Norms for On-Costs and Expenses for Design Estimates (Budgets) of Railway Capital Construction Projects, TB 10811-2024, and are not listed here.
  • For items of the type "may be computed per TB 10811; the costs actually incurred shall be determined by the market" (supervision, survey and design, review, consultancy, third-party monitoring, etc.): book at the norm reference during compilation; actual execution follows the contract and market prices.
  • When the whole-process engineering consultancy fee is booked separately, the consultancy service costs it already covers must not be double-counted; the civil works (cost of works) part has its own item estimate (budget) computation schedule under Clause 2.6, and other costs do not participate in that schedule.

Further Reading

  • TB 10801-2024: Clause 3.11 "other costs" (3.11.1-3.11.20); Section 2.5 "division of chapters and static-investment cost categories" (four parts, seventeen chapters; six categories of static investment costs); Section 2.6 "cost composition and item estimate (budget) computation schedule" (Fig. 2.6.1).
  • TB 10811-2024: on-cost rates, indices and computation details for each sub-item (e.g. statutory work safety levy at 3.0% of the cost of works; in-service line construction cooperation fee reference rates 1.1%-20.5% — see the related cards).
  • Further reading: the four-part, seventeen-chapter cost system (TB 10801-2024, Section 2.5); booking channels for the in-service line construction cooperation fee and the statutory work safety levy; implementation of land acquisition and demolition and who bears the cost (Chapter 1 of the estimate); office and living furniture purchase (design staffing × composite index basis).