Railway basic contingency (基本预备费) charging rule: base and rate (TB 10811-2024 clause 2.13.1) and applicability by compilation stage

Railway estimate (budget) basic contingency is computed on the base of the total of Chapters 1-12 of the general estimate (budget) at a rate of 5% (TB 10811-2024 clause 2.13.1); the same 5% applies uniformly to the preliminary-design general estimate and the construction-drawing general budget with no distinction of stage; at the pre-feasibility/feasibility investment-estimate stage there is no unified rate provision — the compiling organization determines it and states the basis.

Applicable Codes

  • TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works 第2.13.1条
  • TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第2.5.1、2.5.2、3.13条
  • TB 10504-2018 · Measures for Compilation of Pre-Feasibility Study, Feasibility Study and Design Documents of Railway Construction Projects

Topic Positioning

The calculation rules for "basic (physical) contingency" in railway capital construction design estimates (budgets): base scope, rate value and applicability by compilation stage, per TB 10811-2024 clause 2.13.1 and TB 10801-2024 sections 2.5 and 3.13.

Core Conclusions

Per the "Railway Capital Construction Design Estimate (Budget) Norms for On-Costs and Expenses" TB 10811-2024 clause 2.13.1, as written: "Basic (physical) contingency is calculated on the base of the total of Chapters 1-12 of the general estimate (budget), multiplied by a rate of 5%." This is an on-cost clause shared by estimates and budgets, uniformly applicable to both the preliminary-design general estimate and the construction-drawing general budget at the same 5% rate, without distinguishing stage.

Definition of basic (physical) contingency (TB 10801-2024 clause 3.13.1, as written): "costs reserved for the construction stage that may increase due to various unforeseeable factors." Its calculation follows the "Railway Capital Construction Design Estimate (Budget) Norms for On-Costs and Expenses" TB 10811 (clause 3.13.2).

The "total of Chapters 1-12" follows the four-part, seventeen-chapter division of TB 10801-2024 clause 2.5.1, specifically: Chapter 1 demolition and land acquisition; Chapter 2 subgrade; Chapter 3 bridges and culverts; Chapter 4 tunnels and open cuts; Chapter 5 track; Chapter 6 communication, signalling, information and disaster monitoring; Chapter 7 power and electric traction supply; Chapter 8 housing; Chapter 9 other operating-production equipment and buildings; Chapter 10 heavy temporary works and transition works; Chapter 11 other costs; Chapter 12 value added tax (VAT). That is, the base = the total of static investment including VAT but excluding basic (physical) contingency itself (Chapter 13); it excludes Chapter 14 price fluctuation provision, Chapter 15 construction-period loan interest, Chapter 16 locomotive and rolling stock (EMU) purchase costs, and Chapter 17 initial working capital. Also, per clause 2.5.2, static investment divides by cost composition into construction works, installation works, permanent equipment procurement cost, other costs, VAT and basic (physical) contingency — six cost kinds.

Applicable Boundaries

  • This card's rate rule applies to railway design estimates and budgets (preliminary design and construction-drawing stages), both at 5%.
  • Pre-feasibility and feasibility studies belong to the feasibility-stage cost estimate system under the "Measures for compiling pre-feasibility studies, feasibility studies and design documents of railway construction projects" TB 10504-2018, which only requires each stage to show "basic (physical) contingency (rate adopted and basis)" without fixing a unified rate — the compiling organization determines it per the project's design depth and scheme maturity and states the basis; in practice the estimate-stage rate is often above 5% (commonly 6%-10%), but that is not an explicit railway provision — defer to the rate and basis fixed at project review.
  • Basic (physical) contingency is static investment (Part 1, Chapter 13); it differs in nature from Chapter 14 price fluctuation provision, which is dynamic investment — do not confuse the bases or the scope.
  • The versions relied on are TB 10811-2024 and TB 10801-2024 (effective 1 January 2025, replacing TZJ 1001-2017 and other old standards); the rate basis of the old editions must no longer be applied.

Further Reading

  • TB 10811-2024 "Railway Capital Construction Design Estimate (Budget) Norms for On-Costs and Expenses", section 2.13 "basic (physical) contingency" (clause 2.13.1 is the rate clause verbatim).
  • TB 10801-2024 "Measures for compiling design estimates (budgets) of railway capital construction projects", clauses 2.5.1-2.5.2 (four parts and seventeen chapters; six cost kinds of static investment) and section 3.13 "basic (physical) contingency" (definition and calculation basis).
  • TB 10504-2018 "Measures for compiling pre-feasibility studies, feasibility studies and design documents of railway construction projects" (requirements for compiling basic (physical) contingency at the feasibility-stage cost estimate).
  • The full chapter division (Fig. 2.5.1, Chapters 1-17 and static/dynamic attribution) — see the card "railway estimate (budget) four-part, seventeen-chapter cost system".