basic (physical) contingency
- 01
Definition, chapter attribution and computation of the basic contingency and the price fluctuation provision in railway works (TB 10801-2024 Sections 3.13 / 3.14; TB 10811-2024 Article 2.14.1)
The railway basic contingency means costs reserved for the construction…
TB 10801-2024 铁路基本建设工程设计概(预)算编制办法(第2.5.1、3.13、3.14节)TB 10811-2024 铁路基本建设工程设计概(预)算费用定额(第2.14节)JTG 3830-2018 公路工程建设项目概算预算编制办法(第3.4节)2026-10-12 - 02
Railway basic contingency: scope of use and drawdown discipline — definition of unforeseeable factors, distinction from price-difference contingency, approval procedures (TB 10801-2024 clause 3.13 etc.)
Railway 2024 quota system (TB 10801/10811-2024) basic contingency: (1) r…
TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works 第2.13节TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第2.5节、第3.13节铁建〔1990〕191号《铁路基本建设管理暂行办法》第33条2026-09-25 - 03
Highway estimate (budget) contingency rules: basic contingency rates by stage (design estimate 5% / revised estimate 4% / construction-drawing budget 3%), price-difference contingency formula, values of n and i, and the exemption clause (JTG 3830-2018 section 3.4)
Per section 3.4 of JTG 3830-2018: contingency = basic contingency + pric…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.4节2026-09-25 - 04
Railway basic contingency (基本预备费) charging rule: base and rate (TB 10811-2024 clause 2.13.1) and applicability by compilation stage
Railway estimate (budget) basic contingency is computed on the base of t…
TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works 第2.13.1条TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第2.5.1、2.5.2、3.13条TB 10504-2018 · Measures for Compilation of Pre-Feasibility Study, Feasibility Study and Design Documents of Railway Construction Projects2026-09-25