Railway preliminary estimate (and budget) four-part, seventeen-chapter cost system: static/dynamic investment division and cost attribution (TB 10801-2024 Section 2.5)
Per TB 10801-2024 2.5.1, design preliminary estimate (and budget) costs divide into four parts, seventeen chapters: Part I static investment (excluding price fluctuation provision and financing costs) (Chapters 1-13: demolition and land acquisition costs; subgrade; bridges and culverts; tunnels and open-cut tunnels; track; communications, signalling, information and disaster monitoring; power supply and electric traction power supply; buildings; other operating production equipment and structures; heavy temporary works and transition works; other costs; value added tax (VAT); basic (physical) contingency); Part II dynamic investment (Chapter 14 price fluctuation provision; Chapter 15 interest on investment loans during the construction period); Part III locomotive and rolling stock (EMU) procurement cost (Chapter 16); Part IV start-up working capital (Chapter 17). Price fluctuation provision and interest on investment loans during the construction period enter dynamic investment; locomotive and rolling stock (EMU) procurement cost is listed separately as Part III, entering neither static nor dynamic investment. 2.5.2: static investment divides by composition into construction works cost, installation works cost, permanent equipment procurement cost, other costs, value added tax (VAT), and basic (physical) contingency. Total preliminary estimate = sum of the four parts; the total preliminary estimate table is prepared per Appendix A chapter table.
Applicable Codes
- TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第2.5.1条、第2.5.2条
- TB 10801-2024 App. A 综合概(预)算章节Table A.0.1
- TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works
Topic Positioning
The overall cost framework of TB 10801-2024: the "four parts, seventeen chapters" system, the static investment (excluding price fluctuation provision and financing costs)/dynamic investment division, and where price fluctuation provision, interest on investment loans during the construction period, locomotive and rolling stock (EMU) procurement cost, and start-up working capital each go. For structuring and checking railway total preliminary estimates.
Core Conclusions
1. Four parts, seventeen chapters (2.5.1):
- Part I Static investment: Ch. 1 demolition and land acquisition costs; Ch. 2 subgrade; Ch. 3 bridges and culverts; Ch. 4 tunnels and open-cut tunnels; Ch. 5 track; Ch. 6 communications, signalling, information and disaster monitoring; Ch. 7 power supply and electric traction power supply; Ch. 8 buildings; Ch. 9 other operating production equipment and structures; Ch. 10 heavy temporary works and transition works; Ch. 11 other costs; Ch. 12 value added tax (VAT); Ch. 13 basic (physical) contingency;
- Part II Dynamic investment: Ch. 14 price fluctuation provision; Ch. 15 interest on investment loans during the construction period (domestic and foreign sub-items);
- Part III Locomotive and rolling stock (EMU) procurement cost: Ch. 16;
- Part IV Start-up working capital: Ch. 17.
2. Attribution of three common costs: price fluctuation provision -> Part II (Ch. 14); interest on investment loans during the construction period -> Part II (Ch. 15); locomotive and rolling stock (EMU) procurement cost -> Part III separately (Ch. 16), in neither static nor dynamic investment, listed as required in the total preliminary estimate; start-up working capital -> Part IV (Ch. 17).
3. Six cost types within static investment (2.5.2):
- Construction works cost: subgrade, bridges and culverts, tunnels and open-cut tunnels, track, communications, signalling, information, disaster monitoring, power supply, electric traction power supply, buildings, water supply and drainage, depots, rolling stock, EMU, station yards, track maintenance, other works, and pipelines, equipment foundations and work platforms within construction scope, plus relocation works and the construction works cost content of heavy temporary works and transition works.
- Installation works cost: assembly and erection of mechanical and electrical equipment needing installation, work platforms and ladders attached to equipment, piping attached to installed equipment, and insulation, painting, thermal insulation and commissioning of installed equipment.
- Permanent equipment procurement cost: production, power, weak-current, lifting and transport equipment needing or not needing installation (including spare parts), and tools and special tools (including spare parts) that constitute fixed assets.
- Other costs: land acquisition (lease) and demolition compensation, project management, owner stamp duty and other taxes, preliminary costs, construction supervision, survey and design, document review, other consultancy, operating-line construction cooperation, statutory work safety levy (earmarked funds), research and testing, joint commissioning and trial operation and related costs, foreign-capital use, production preparation, third-party monitoring, plateau/high-cold health protection, living-supplies transport subsidy, whole-process consultancy, others.
- Value added tax (VAT): computed per the design preliminary estimate (and budget) composition and state tax law.
- Basic (physical) contingency: reserved for the construction stage against unforeseeable increases.
4. Total preliminary estimate = sum of four parts (static investment + dynamic investment + locomotive and rolling stock (EMU) procurement cost + start-up working capital). The total preliminary estimate table is prepared per Appendix A comprehensive preliminary estimate (and budget) chapter table: Part I chapters total as "subtotal above", then Parts II, III and IV follow. Note: the 2024 edition makes value added tax (VAT) Chapter 12 (formerly inside each cost) — do not omit when structuring chapters.
Applicable Boundaries
- Applies to railway capital construction (new, second lines, electrification, etc. large and medium projects) design preliminary estimate (and budget) cost division and chapter attribution.
- This card resolves only "which part, which chapter"; percentage rates, quota norms (prescribed resource consumption standards), and calculation rules within chapters (preliminaries, on-costs (indirect costs), statutory work safety levy (earmarked funds), heavy temporary works, special-region construction increases, etc.) are in other cards.
- Chapter names and numbers per TB 10801-2024; highway, building and power sector systems differ — do not copy this framework.
- The "four parts" chapter hierarchy and the "six cost types" are two different dimensions: the six types classify static investment internally; the four parts are the total preliminary estimate's chapter levels — do not mix.
Further Reading
- TB 10801-2024 2.5.1 (chapter composition), 2.5.2 (six static cost types), Appendix A Table A.0.1 (chapter numbers, unit of measurement per main-line km, "subtotal above" sequence).
- Companion: TB 10811-2024 Norms for On-costs and Expenses (percentage rates and quota norms); the railway estimate and budget quota norms system and base-period price mechanism in referenced cards.
- Extensions (referenced cards): Chapter 10 preparation of heavy temporary works and transition works; composition and percentage rates of preliminaries and on-costs (indirect costs); calculation and ring-fenced (earmarked) use of the statutory work safety levy; wind-sand/plateau/primeval-forest construction increases; classification of temporary haul roads as heavy/minor temporary works; Chapter 1 responsibility allocation and preliminary estimate line items for demolition and land acquisition costs; methods for estimating start-up working capital at feasibility study stage.
Keywords
- TB 10801-2024
- static investment (excluding price fluctuation provision and financing costs)
- 动态投资
- 概算总额
- price fluctuation provision
- 建设期投资贷款利息
- 机车车辆购置费
- 铺底流动资金
- 四部分十七章
- 概预算编制办法