price fluctuation provision
- 01
Definition, chapter attribution and computation of the basic contingency and the price fluctuation provision in railway works (TB 10801-2024 Sections 3.13 / 3.14; TB 10811-2024 Article 2.14.1)
The railway basic contingency means costs reserved for the construction…
TB 10801-2024 铁路基本建设工程设计概(预)算编制办法(第2.5.1、3.13、3.14节)TB 10811-2024 铁路基本建设工程设计概(预)算费用定额(第2.14节)JTG 3830-2018 公路工程建设项目概算预算编制办法(第3.4节)2026-10-12 - 02
Railway estimate (budget) price adjustment rules: the labour/materials/plant three-line adjustment method and its place in the item-estimate procedure (TB 10801-2024 section 4.1, Table 2.6.2)
TB 10801-2024 clause 4.1.1: price adjustment means the reasonable adjust…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第4.1节、第3.2节、第3.14节、第2.6节及Table 2.6.2TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway worksTB/T 10813-2024 · Base Period Prices of Materials for Railway Engineering2026-09-25 - 03
Railway preliminary estimate (and budget) four-part, seventeen-chapter cost system: static/dynamic investment division and cost attribution (TB 10801-2024 Section 2.5)
Per TB 10801-2024 2.5.1, design preliminary estimate (and budget) costs…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第2.5.1条、第2.5.2条TB 10801-2024 App. A 综合概(预)算章节Table A.0.1TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works2026-09-25 - 04
Railway basic contingency: scope of use and drawdown discipline — definition of unforeseeable factors, distinction from price-difference contingency, approval procedures (TB 10801-2024 clause 3.13 etc.)
Railway 2024 quota system (TB 10801/10811-2024) basic contingency: (1) r…
TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works 第2.13节TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第2.5节、第3.13节铁建〔1990〕191号《铁路基本建设管理暂行办法》第33条2026-09-25 - 05
Highway estimate (budget) contingency rules: basic contingency rates by stage (design estimate 5% / revised estimate 4% / construction-drawing budget 3%), price-difference contingency formula, values of n and i, and the exemption clause (JTG 3830-2018 section 3.4)
Per section 3.4 of JTG 3830-2018: contingency = basic contingency + pric…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.4节2026-09-25 - 06
Railway 2024 quota-norm system price fluctuation provision: formula, annual growth-rate selection, and distinction from compilation-period adjustment for price differentials (TB 10801/10811-2024)
The price fluctuation provision (TB 10811-2024 clause 2.14.1) is compute…
TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第3.14节、第4.1节、第2.5.1条、Table 2.6.2TB 10811-2024 铁路基本建设工程设计概(预)算费用定额 第2.14节(公式2.14.1)2026-09-25