Responsibility division for land acquisition, demolition, and "three networks" relocation in railway works: implementing bodies, cost bearing, and Chapter 1 estimate listing

Railway land acquisition and demolition is implemented in a unified manner by local governments (including cost wrap-up), with costs borne by the railway construction unit and listed in Chapter 1 of the estimate, "demolition and land acquisition costs"; relocation of the three networks (power, communication, water/sewer, oil and gas pipelines) follows "the later builder / the proposing party bears the cost, the asset owner implements, agreement precedes" — construction may start only after agreement with the asset owner.

Applicable Codes

  • 《中华人民共和国铁路法》(2015修正) 第36条
  • 计交通〔1993〕2209号 第15条
  • 《电力供应与使用条例》(2019修订) 第18条
  • 《电力设施保护条例》(1998修正) 第22条
  • 国发〔1982〕28号 第10条
  • 《石油天然气管道保护条例》第20条
  • TB 10801-2024 App. A Ch. 1

Topic Positioning

A framework for dividing responsibilities for land acquisition/demolition and three-network (power, communication, water/sewer, oil and gas pipeline) relocation in railway works: clarifying the implementing body, the cost-bearing body, and the cost-listing channel, reusable for estimate compilation, relocation-agreement negotiation, and compliance review.

Core Conclusions

  • Land acquisition and demolition: implementation rests with the local people's government — local governments uniformly acquire land, resettle demolition, and apply cost wrap-up (Railway Law, Article 36; Ji Jiao Tong [1993] No. 2209, Article 15); costs are borne by the railway construction unit and listed in Chapter 1 of the estimate, "demolition and land acquisition costs" (TB 10801-2024 Appendix A, covering works demolition, environmental-protection demolition, other demolition, temporary land fees, waste clearing and disposal fees).
  • Three-network relocation general principle: "the later/proposing builder bears the cost, the asset owner implements, agreement precedes": relocation or protection of power facilities must be negotiated in advance with the power supply facility manager, costs borne by the construction unit (Regulations on Electric Power Supply and Use, Article 18); where power facilities and the works mutually obstruct, agreement on relocation, protection, and compensation must be reached before construction (Regulations on Protection of Power Facilities, Article 22); communication-line relocation requires prior consent of the communication department, with costs and materials borne by the proposing unit (Guo Fa [1982] No. 28, Article 10); oil and gas pipeline rerouting, relocation, or protection costs are borne by the later builder (Regulations on Protection of Oil and Natural Gas Pipelines, Article 20).
  • Practice interface: the railway construction unit signs a land/demolition wrap-up agreement with the local government and relocation agreements with asset owners before implementation, with all costs booked into Chapter 1 of the estimate.

Applicable Boundaries

Applies to relocation of existing facilities and land acquisition caused by railway construction (as the later builder). The cost principle holds with "whoever builds later bears"; if the railway came first and another party later, liability reverses; "agreement before construction" is a hard precondition. The railway's own three-network facilities relocate with the main works per the formal design and costs go to the relevant works chapters — not the Chapter 1 relocation caliber — distinguish per the design documents. Specific compensation standards follow local rules and agreements; this card excludes amounts.

Further Reading

Laws: Railway Law (2015 amendment) Article 36; Ji Jiao Tong [1993] No. 2209 Article 15; Regulations on Electric Power Supply and Use (2019 revision) Article 18; Regulations on Protection of Power Facilities (1998 amendment) Article 22; Guo Fa [1982] No. 28 Article 10; Regulations on Protection of Oil and Natural Gas Pipelines Article 20. Codes: TB 10801-2024 "Measures for compiling design estimates (budgets) of railway capital construction projects", Appendix A "Composite estimate (budget) chapter table", Chapter 1 demolition and land acquisition costs.

Keywords

  • 征地拆迁
  • 三电迁改
  • 责任划分
  • 迁改费用
  • 拆迁及征地费用
  • 概算第一章
  • 管线迁改
  • 铁路建设单位