Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Cost-bearing rules for relocation of existing underground utilities (whoever proposes it or causes it bears the cost)

Where a normal project requires relocation of existing utilities, the cost is borne by the employer (project owner) (Highway Safety Protection Regulations, Article 15); relocation of communication lines is borne by the unit proposing the relocation (Guo Fa [1982] No. 28, Article 10); relocation of radio and television facilities is borne by the unit causing the relocation (SARFT Order No. 8, Article 31); liability for damaged utilities depends on the employer's data-supply obligation and the contractor's protection obligation (Construction Law, Article 40; GB 50268-2008, Clause 4.1.1).

Applicable Codes

  • 公路安全保护条例(国务院令第593号)第十五条
  • 国发〔1982〕28号 关于保护通信线路的规定 第十条
  • 广播电视无线传输覆盖网管理办法(广电总局令第8号,2021修订)第三十一条
  • 建筑法 第四十条
  • GB 50268-2008 第4.1.1条

Topic Positioning

Compliance rules for determining who bears the cost of relocating (rerouting) existing underground utilities in construction: the general principle, expressly laid down in national regulations, is "whoever proposes the relocation or causes it bears the cost".

Core Conclusions

  1. Where new or reconstructed highways cross existing urban roads, railways, communication lines, etc. and relocation is required, the construction cost is borne by the new-build or reconstruction body (i.e., the employer); costs increased by a demand to raise the standard of existing facilities are borne by the department or unit making the demand (Highway Safety Protection Regulations, Article 15, State Council Order No. 593).
  2. Communication lines shall generally not be relocated; where special circumstances genuinely require relocation, the consent of the communication department must first be obtained, and the costs and materials for relocation are the responsibility of the unit proposing the relocation (Guo Fa [1982] No. 28, Article 10).
  3. Relocation of radio and television facilities follows the principle of "build first, demolish later"; the relocation costs are borne by the unit causing the relocation (Measures for the Administration of Radio and Television Wireless Transmission Coverage Networks, Article 31, SARFT Order No. 8, 2021 revision).
  4. The employer's statutory obligation is to provide the contractor with data on the underground utilities (structures) within the area affected by construction, and the contractor shall take measures to protect them (Construction Law, Article 40; GB 50268-2008, Clause 4.1.1): where utilities are damaged because the employer failed to provide the data or provided inaccurate data, the employer bears liability; where the contractor causes damage by failing in its protection obligation, the contractor bears liability.

Applicable Boundaries

This card sets out nationally applicable liability rules and does not deal with pricing or amounts; where local provisions on utility management exist, those provisions prevail. In settlement practice, the responsible party must be supported by a chain of evidence such as meeting minutes, approvals of the relocation scheme, site instructions and certified records, and photographic records; where utilities not disclosed in the handover are discovered during construction, work should be stopped first and the matter reported to the employer for coordination and confirmation.

Further Reading

See the Highway Safety Protection Regulations (State Council Order No. 593), Article 15; Guo Fa [1982] No. 28, "Provisions of the State Council and the Central Military Commission on the Protection of Communication Lines", Article 10; the Measures for the Administration of Radio and Television Wireless Transmission Coverage Networks (SARFT Order No. 8, 2021 revision), Article 31; the Construction Law of the People's Republic of China, Article 40; and GB 50268-2008, "Code for construction and acceptance of water and sewer pipeline works", Clause 4.1.1.

Keywords

  • 地下管线
  • 管线迁改
  • 管线排迁
  • 迁改费用
  • 费用承担
  • 通信线路
  • 广播电视设施
  • 管线保护