The computation programme of a single-item railway building and installation estimate (TB 10801-2024 Table 2.6.2): the 16-step accumulation order, each step's charging base, and where the special construction addition sits

Per TB 10801-2024 Table 2.6.2's sixteen accumulating steps: quota direct works cost = (1)+(2)+(3); direct works cost = (4)+(5)+(9)+(10) (including extra-price freight, price differences total, fill material); construction-measures cost = [(1)+(3)] x the measures rate; the special construction addition 'is computed on the compilation-period labour and compilation-period plant'; direct cost = (11)+(12)+(13); on-costs = [(1)+(3)] x the on-costs rate; single-item estimate value = (14)+(15). Key base rules: the measures and on-costs bases are base-period labour + base-period plant; the special construction addition enters the direct cost only and never rolls into other charging bases. Equipment runs its own programme: equipment freight = (1) x the freight rate; value = (1)+(2).

Applicable Codes

  • TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第2.6.2条及Table 2.6.2
  • TB 10801-2024 第2.6.1条及图2.6.1(费用项目组成)
  • TB 10801-2024 第2.6.3条及Table 2.6.3(设备单项概预算计算程序)
  • TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works 第2.7节、Table 2.9.1

Positioning

The standardised computation chain of single-item building and installation estimates in railway design estimates - the cost composition (Figure 2.6.1) and the 16-step programme (Table 2.6.2) - fixing at which step each cost (including construction-measures cost, the special construction addition and on-costs) is charged and on what base. Basis: TB 10801-2024 clause set 2.6.

Core conclusions

  1. Cost composition (Figure 2.6.1) Direct cost = direct works cost + construction-measures cost + special construction addition; direct works cost holds labour, materials, plant, extra-price freight and fill material; the special construction addition holds five sub-items - wind-sand region, plateau region, primeval-forest region, traffic interference and line-blockade additions. Static investment covers the works cost, equipment procurement, other costs, VAT and basic contingency; dynamic investment adds the price fluctuation provision and interest on construction-period loans.

  2. The programme (Table 2.6.2, verbatim) 1 base-period labour: design quantities x base-period prices; 2 base-period materials: likewise; 3 base-period plant: likewise; 4 quota direct works cost = (1)+(2)+(3); 5 extra-price freight: freight listed separately, per the material supply scheme of the execution plan and this rule; 6 labour price difference, 7 material price difference, 8 plant price difference: base-to-compilation-period differences per this rule; 9 differences total = (6)+(7)+(8); 10 fill material: design quantities x surveyed prices; 11 direct works cost = (4)+(5)+(9)+(10); 12 construction-measures cost = [(1)+(3)] x the measures rate; 13 special construction addition: on the corresponding compilation-period labour and compilation-period plant; 14 direct cost = (11)+(12)+(13); 15 on-costs = [(1)+(3)] x the on-costs rate; 16 single-item estimate value = (14)+(15).

  3. Three base rules for review 1 The special construction addition sits inside the direct cost (step 13) on compilation-period labour and plant - not base-period values, not the quota direct works cost, not the whole direct works cost. 2 Construction-measures cost (12) and on-costs (15) both base on [(1)+(3)] - base-period labour + base-period plant; excluding differences, fill material and extra-price freight, and excluding the special addition - the addition never rolls into other bases. 3 Differences (labour, material, plant) and fill material enter the direct works cost (11), listed apart from the base-period costs, never double-counted.

  4. Equipment programme (Table 2.6.3): equipment cost = design quantities x original prices; freight = (1) x the freight rate; value = (1)+(2). Equipment never enters the 16-step works chain.

Applicable boundaries

  • For railway building and installation single-item estimates under TB 10801-2024 only; the building / municipal BOQ basis (GB/T 50500) and the highway 2018 system (JTG 3830-2018) differ in composition and bases - no mixing.
  • The rates (measures, on-costs, special addition, quota uplifts) are not in the programme table - they follow TB 10811-2024 (measures and on-costs Table 2.9.1; special addition clause set 2.7).
  • The table is the single-item (unit works) chain; rolling up to the total estimate adds other costs, VAT and contingency by chapter - the single-item value is not the static investment.
  • Listing at step 13 does not mean the five special-addition sub-items are unconditional - each has its own triggers and bases.

Further reading

TB 10801-2024 clause set 2.6: 2.6.1 and Figure 2.6.1; 2.6.2 and Table 2.6.2; 2.6.3 and Table 2.6.3; clauses 3.6~3.9 (measures, special addition, on-costs); TB 10811-2024 clause set 2.7 and Table 2.9.1.