plant rate per machine-shift
- 01
Pricing-form determination and machine-shift rate value for site-owned diesel generator sets: own units by machine-shift (TB/T 10814-2024 power machinery items 9101243/9101253 plus Appendix A base data), leased units by certified rent, standby non-running units by idle cost (depreciation plus labour plus others), and the boundary against permanent-equipment procurement and installation (TB/T 10833-2024 JY-260 to JY-267)
One generator set takes exactly one pricing channel: (1) own units enter…
TB/T 10814-2024 · Quota for Shift Costs of Construction Machinery and Tools of Railway Engineering Ch. 1总则 1.0.3~1.0.5、Ch. 2第二节动力机械(9101231~9101271)、App. A 施工机械基础数据表TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第3.3节 施工机具使用费(3.3.1~3.3.6)TB 10833-2024《铁路工程预算定额 第十二册 机务车辆机械工程》第一章第七节 柴油发电机组 JY-260~JY-2672026-11-12 - 02
Deciding when large plant mobilisation and erection charges are priced separately, and the cost make-up (with quota item codes, trip counts and haul-distance rules)
Large-plant mobilisation and erection charges follow a three-type test…
GB/T 50500-2024 App. E Table E.3.4GB/T 50854-2024 App. R Table R.1.1(code 011601)GB 50860-2013 App. C Table C.4(code 070304)2026-10-11 - 03
Identifying anomalous data in machine-shift records: a four-layer verification method (field checks -> quantity cross-footing -> unit pricing -> aggregate statistics)
Machine-shift record anomalies concentrate in four types: fabricated shi…
TB/T 10814-2024 铁路工程施工机具台班费用定额TB 10801-2024 铁路基本建设工程设计概(预)算编制办法GB/T 50500-2024 建设工程工程量清单计价标准2026-09-25 - 04
Unit price of electricity for electric plant under self-generated power in highway works: A = 0.15 x K / N (JTG 3830-2018 Clause 3.1.2; K per the JTG/T 3833-2018 shift-cost quota)
With self-generated power, the unit price per kW.h of electricity for el…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.2条(公式3.1.2)JTG/T 3833-2018 · Quota for Shift Costs of Highway Engineering MachineryJTG 3820-2018 · Measure for Compilation of Investment Estimates of Highway Construction Projects 第3.1.2条2026-09-25 - 05
Pricing chain of plant shift labor cost in the highway 2018 system: quota locks consumptions, price from the provincially published comprehensive shift price (JTG/T 3833-2018 general note 6 + JTG 3830-2018 Clause 3.1.2)
In the 2018 highway system, the machine-shift labour cost does not lock…
JTG/T 3833-2018 · Quota for Shift Costs of Highway Engineering Machinery 总说明第五条、第六条JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.2条JTG 3820-2018 · Measure for Compilation of Investment Estimates of Highway Construction Projects 机械台班费用计算表(21表)填表说明2026-09-25 - 06
Calculation rules for construction equipment standby (downtime) fees, mobilization/demobilization fees, and erection/dismantling fees
Standby fee = depreciation + labor + other costs (excluding overhaul, ma…
TB/T 10814-2024 铁路工程施工机具台班费用定额GB/T 50500-2024 建设工程工程量清单计价标准山东省建设工程施工机械台班费用编制规则2026-09-25 - 07
Railway 2024 quota norms: erection/dismantling and commissioning of large plant (special line items GY-1~GY-5) versus plant rate per machine-shift and plant entry/exit cost — boundary rules: erection/commissioning must be booked separately, entry/exit must not, and the three never overlap
Under the railway 2024 quota norms (TB/T 10825-2024, TB/T 10814-2024, TB…
TB/T 10825-2024 铁路工程预算定额 Vol. 4 轨道工程 Ch. 1第一节 大型机械安拆与调试(GY-1~GY-5)TB/T 10814-2024 铁路工程施工机具台班费用定额 Ch. 3第三节 轨道工程机械TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第3.3.4条2026-09-25