Unit price of electricity for electric plant under self-generated power in highway works: A = 0.15 x K / N (JTG 3830-2018 Clause 3.1.2; K per the JTG/T 3833-2018 shift-cost quota)
With self-generated power, the unit price per kW.h of electricity for electric plant is computed per Clause 3.1.2 of JTG 3830-2018: A = 0.15 x K / N, where A is the price per kW.h (yuan), K the generating-set shift price (yuan, per JTG/T 3833-2018, fixed + variable costs), N the total set power (kW), and 0.15 a code-given constant. A is used for the plant shift power cost = shift electricity consumption x A; purchased grid power does not use this formula; the same clause is JTG 3820-2018 Clause 3.1.2 at the estimate stage.
Applicable Codes
- JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.2条(公式3.1.2)
- JTG/T 3833-2018 · Quota for Shift Costs of Highway Engineering Machinery
- JTG 3820-2018 · Measure for Compilation of Investment Estimates of Highway Construction Projects 第3.1.2条
Topic Positioning
The standard method for the unit price per kW.h of electricity for electric plant under self-generated power in highway works: the Clause 3.1.2 formula A = 0.15 x K / N of JTG 3830-2018, and the pricing rule for the generating-set shift price K (JTG/T 3833-2018). For computing plant costs (electric plant shift power cost) in highway estimates, budgets, and investment estimates.
Core Conclusions
Per Clause 3.1.2 of the "Measures for compiling estimates and budgets of highway engineering construction projects" (JTG 3830-2018), where site power is self-generated, the unit price per kW.h for electric plant may be computed as:
A = 0.15 x K / N
where A = price per kW.h (yuan); K = shift price of the generating set (yuan); N = total power of the set (kW). 0.15 is a constant given by the code — adopt it directly, no derivation.
The generating-set shift price K follows the current "Highway engineering plant shift-cost quota" (JTG/T 3833-2018); the shift price consists of fixed and variable costs:
- Fixed: depreciation, overhaul, maintenance, erection/dismantling auxiliary — taken from the quota tables. Example: diesel generating set within 50 kW (quota code 8017004, class "9. power machinery") has fixed costs of 98.86 yuan/shift;
- Variable: operator labor, power/fuel, vehicle and vessel tax. Labor shifts and fuel consumptions are taken from the shift-cost quota; the labor price equals the production-worker price; fuel follows the material cost rules — diesel being a fuel-class material, the procurement and custody rate is 3.26% (JTG 3830-20118 rates: steel 0.75%, fuels and blasting materials 3.26%, other materials 2.06%).
The computed A serves the electric plant shift power cost: shift power cost of a machine = its shift electricity consumption (kW.h, per quota consumptions) x A. N is the total set power; parallel sets add their powers.
Applicable Boundaries
- Applies only where site power is self-generated; grid power does not use the formula — price per the local supplier at compilation.
- The same formula applies in the investment-estimate measures (JTG 3820-2018 Clause 3.1.2, identical wording).
- Labor shifts and fuel consumptions in K must be taken from JTG/T 3833-2018 — no self-estimates; unit prices at compilation-period values (labor as the production-worker price, fuel at compilation-period material budget prices).
- A is the computation price for shift power cost, not a settlement price for electricity.
Further Reading
See JTG 3830-2018 Clause 3.1.2 (plant cost, with formula 3.1.2) and the procurement-custody rates (steel 0.75%, fuels and blasting 3.26%, others 2.06%); JTG/T 3833-2018 "Highway engineering plant shift-cost quota" — diesel generating sets in "9. power machinery" series 8017 (codes 8017001-8017004 etc.), fixed/variable composition per the general notes (variable = items 5-7); the estimate-stage counterpart is JTG 3820-2018 Clause 3.1.2.
Keywords
- JTG 3830
- 自办发电
- 自行发电
- 电单价
- 电动机械
- 发电机组
- plant rate per machine-shift
- JTG/T 3833
- plant rate norms per machine-shift