Identifying anomalous data in machine-shift records: a four-layer verification method (field checks -> quantity cross-footing -> unit pricing -> aggregate statistics)
Machine-shift record anomalies concentrate in four types: fabricated shifts, wrong model applied, duplicate charging of idle time, and amounts exceeding certification and sign-off. Investigate in four layers: "field-level checks -> cross-footing of shift count against quantities (actual shifts ≈ quantity ÷ shift output) -> verification of the 7-component plant rate per machine-shift and the price-difference basis -> aggregate statistics to screen anomalies"; shifts of machinery not reported for approval must not be charged; quota norms already include reasonable idle and no-load time, so listing it separately is duplicate charging.
Applicable Codes
- TB/T 10814-2024 铁路工程施工机具台班费用定额
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
- GB/T 50500-2024 建设工程工程量清单计价标准
- T/HAEC 011-2024
- TB 10402-2019
Topic Positioning
Machine-shift records are the direct voucher for plant-cost settlement; anomalies concentrate in four types: fabricated shifts, wrong model applied, duplicate charging of idle time, and exceeding certification and sign-off. This card gives a four-layer verification method for quickly locating suspect records in construction cost control and final account review.
Core Conclusions
Layer 1, field-level checks: anomalous dates (full shifts still reported in severe weather/on holidays/before entry or after exit), single shifts over 8h without overtime basis, machinery model inconsistent with the entry inspection form (shifts of unreported machinery must not be charged), the same machine charged at two work points on the same day (stacked hours over 24h is hard evidence), and missing driver/site-manager/supervisor certification and sign-off or retrospective/proxied signatures. Layer 2, quantity cross-footing (most effective): actual shifts ≈ corresponding quantity ÷ shift output, back-calculated; obvious multiples beyond that are suspects; shift records must correspond day by day with construction and supervision logs — "shifts reported with no corresponding work content that day" is the most frequent fabrication; shift count ÷ calendar days exceeding the daily shift upper limit is anomalous. Layer 3, unit price and charging rules: the plant rate per machine-shift consists of 7 components — depreciation, overhaul, maintenance, assembly and disassembly, labour, power, and other fees; quota-norm shift consumption already includes reasonable idle, no-load, and standby amounts, so separately listing "idle/awaiting-materials/standby shifts" is duplicate charging; the base-period versus compilation-period difference is charged as a plant price difference and must not be mixed into the unit price for repeated fee accrual; check quota line items against the actually used model to prevent using large machines for small jobs. Layer 4, aggregate statistics: a single machine's shifts taking an abnormally high share of the whole project, inconsistent plant rates per machine-shift of the same model across periods, plant cost as a share of divisional-work cost outside the empirical range (generally 5%~15%), and shifts exceeding the contract lump-sum amount without a certified basis.
Applicable Boundaries
Applies to final account review and process cost control under unit-rate/lump-sum contracts; must be mutually corroborated with inspection forms, construction/supervision logs, rental contracts, and price-confirmation slips — the shift sheet alone is insufficient for a verdict; employer-caused idle time is claimed separately per the contract claim procedure and must not be mixed into normal shifts; for rental pricing, first judge the shift-rental versus monthly-rental basis by "critical shift count = monthly rent ÷ plant rate per machine-shift", then check consistency of the settlement pricing method.
Further Reading
See TB/T 10814-2024 "Quota for shift costs of construction machinery and tools of railway works" Clauses 1.0.4, 1.0.5 (7 components of the plant rate per machine-shift and formulas); TB 10801-2024 "Methods for compiling design estimates (budgets) of railway capital construction works" Clauses 3.3.3~3.3.6 (calculation and price-difference charging of plant and small tools cost); GB/T 50500-2024 Chapter 10 (validity of stage settlement during construction and the final account); no shifts for unreported machinery and daily supervisor log entries per T/HAEC 011-2024; basis for checking entered machinery per TB 10402-2019 Appendix B machinery inspection form.
Keywords
- machine-shift
- 台班记录
- 虚报台班
- 台班审核
- plant and small tools cost
- 机械费结算
- plant rate per machine-shift
- 异常数据识别