Pricing chain of plant shift labor cost in the highway 2018 system: quota locks consumptions, price from the provincially published comprehensive shift price (JTG/T 3833-2018 general note 6 + JTG 3830-2018 Clause 3.1.2)
In the 2018 highway system, the machine-shift labour cost does not lock the rate, only consumption: machine-shift labour cost = quota labour consumption per machine-shift (workdays/machine-shift, locked by JTG/T 3833-2018) × the all-in daily labour rate published by the provincial transport authority where the project is located (compilation-period price, JTG 3830-2018 Clause 3.1.2). The all-in daily labour rate is not differentiated by trade, includes the individual's pension/unemployment/medical insurance (excluding maternity) and housing fund contributions, and serves only as a basis of preparation, not as a basis for actual wage payments; daily labour rates for engineering vessels and diving equipment are calculated according to local provisions; the base to which percentage rates are applied uses the machine-shift base rate (base-period), and must not be mixed with the compilation-period plant rate per machine-shift.
Applicable Codes
- JTG/T 3833-2018 · Quota for Shift Costs of Highway Engineering Machinery 总说明第五条、第六条
- JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.2条
- JTG 3820-2018 · Measure for Compilation of Investment Estimates of Highway Construction Projects 机械台班费用计算表(21表)填表说明
Topic Positioning
The pricing chain of the "labor cost" within highway plant shift prices under the 2018 system: the shift quota locks only labor consumptions, prices follow the JTG 3830-2018 comprehensive shift price; plus the caliber details of the comprehensive price, form-21 flows, and the distinction from shift base prices. For analyzing plant shift prices (form 21) and taking plant costs in highway estimate/budget compilation and review.
Core Conclusions
The chain has three layers:
- Quantities locked to the quota: JTG/T 3833-2018 general note 6, verbatim — "when compiling plant shift prices, labor and power/fuel consumptions shall follow the values in this quota." Of the 7 cost components, items 1-4 (depreciation, overhaul, maintenance, erection/dismantling auxiliary) are fixed and adopted directly except in remote regions (Qinghai, Xinjiang, Tibet), where provincial authorities may set adjustment coefficients; items 5-7 (labor, power/fuel, vehicle and vessel tax) are variable. "Labor cost" means the working-day wages of operators attending the plant (wages, allowances, subsidies, auxiliary wages, labor protection, etc.).
- Price at the compilation-period comprehensive shift price: general note 6, verbatim — "labor and power/fuel unit prices are computed per the 'Measures for compiling estimates and budgets of highway engineering construction projects' (JTG 3830-2018)." Per Clause 3.1.2: labor cost = quota labor shifts x comprehensive shift price; the price is set, published, and dynamically adjusted by the provincial transport authority; it serves only estimate/budget compilation, not actual wages.
- Comprehensive shift price caliber (JTG 3830-2018 notes, verbatim): one comprehensive price for all highway labor regardless of trade; it already includes the individually paid pension, unemployment, and medical insurance (excluding maternity) and housing fund; it differs from the market price: normally 8 h/day (tunnels 7, diving 6); enterprise-paid insurances and fund, winter/rainy/night allowances, site transfer, heating, staple-food subsidy, and home-visit travel are computed separately. Form flow and exception: the plant shift cost computation form (form 21) notes state "labor and power/fuel unit prices are carried over from the material budget price computation form (form 22)" — the same project-location compilation-period comprehensive shift price; vessel and diving-equipment shift prices follow the local authorities. One-line conclusion: shift labor cost = quota labor consumption per shift (locked) x the provincial comprehensive shift price (compilation-period).
Applicable Boundaries
- Applies to the highway estimate/budget system (JTG/T 3833-2018 + JTG 3830-2018); not for railway (TB/T 10814-2024 comprehensive labor price in seven works classes), housing/municipal, or other calibers.
- The comprehensive price is a provincial publication (compilation-period), differing by province and dynamically adjusted; take the current provincial document — this card carries no local values.
- The shift price serves compilation only, not actual wages; shift labor uses the same comprehensive price as estimate/budget quota labor, no trade differentiation.
- Caliber distinction: compilation-period shift prices (incl. labor) serve the direct cost (plant cost); quota plant cost and the bases of measures costs and enterprise management cost use the JTG/T 3833 shift base prices (base-period) — the two must not be mixed.
Further Reading
- JTG/T 3833-2018 general notes: item 5 (fixed costs and remote-region coefficients), item 6 (variable costs and pricing, annual working shifts), item 7 (plant transfer excluded), item 8 (refueling/filtering and transmission losses included).
- JTG 3830-2018 Clause 3.1.2 (labor/material/plant calibers) and the comprehensive-price notes (no trade differentiation, individual four-insurance-one-fund, differences from market price); Clause 3.1.1 (quota direct cost and shift base-price caliber).
- JTG 3820-2018 plant shift cost form (form 21) filling notes (prices carried from form 22).
- No .gov.cn URL in this evidence; verify via the Ministry of Transport's official publication channels.