Determining settlement quantities when drawings disagree with actual site dimensions: characterize first (variation / unauthorized work / measure-as-executed), then quantify

Where drawings and site dimensions disagree, one must not uniformly settle "per drawings" or "per actuals" — characterize first: employer changes baselines/levels/positions/dimensions -> variation, measured per the revised drawings (lump-sum contracts measure only the confirmed variation portion; unit-rate contracts re-measure per the final construction drawings); contractor builds not per drawings without authorization -> quantities beyond the drawings are not measured and no site instruction or variation record may be issued for them; design explicitly requires site verification -> a site instruction / variation record confirms per actuals. In disputes referred for construction cost expert assessment, determination follows the five-tier progression: valid confirmation signed by both parties -> one-party confirmation (no rebuttal) -> re-check or site inspection -> inspection measurement -> if still undeterminable, no measurement with explanation.

Applicable Codes

  • T/ZBD 100.5-2023 建设工程结算审核作业指引
  • T/ZBD 100.4-2023 建设工程造价鉴定作业指引
  • GB/T 50500-2024 建设工程工程量清单计价标准
  • T/SDJZXH 004.1-2022 城市轨道交通工程监理工作标准
  • GB/T 51262-2017 建设工程造价鉴定规范

Topic Positioning

When drawings disagree with actual site dimensions (enlarged members, shifted positions, changed levels), settlement quantities must be characterized before being quantified — not simply "per drawings" or "per actuals". This card gives a three-category characterization framework and the measurement paths.

Core Conclusions

(1) The employer changing baselines, levels, positions or dimensions constitutes a variation, measured per the revised drawings. Under lump-sum contracts, any inconsistency of the actually-constructed drawings (except detailing design) with the contracted drawings is a variation; only the confirmed variation portion is re-measured; under unit-rate contracts, the actually-built quantities are re-computed per the final construction drawings (not as-built drawings) (T/ZBD 100.4-2023 clauses 4.3.4, 4.3.5). (2) Quantities beyond the drawings from the contractor's unauthorized non-compliance with drawings, or from foreseeable conditions not raised in time, are not measured and no site instruction or variation record may be issued for them (T/SDJZXH 004.1-2022 clause 10.6.1). (3) Where design explicitly requires site verification or unforeseeable underground obstructions are handled, a site instruction / variation record measures per actuals; the record contains items, basis, calculation process and result. Measurement results signed by both parties are the settlement basis (GB/T 50500-2024 clause 7.1.8). Disputes entering construction cost expert assessment follow the five-tier determination (T/ZBD 100.4-2023 clause 4.3.6): valid confirmation signed by both parties -> one-party confirmation without valid rebuttal by the other -> re-check or site inspection -> inspection measurement -> if still undeterminable, no measurement with explanation.

Applicable Boundaries

Applies to disputes over quantities in settlement and construction cost expert assessment where drawings do not match the site. Version disputes over measurement rules are resolved in the order: contract agreement -> national measurement standard consistent with the contract category -> industry/local standard (T/ZBD 100.4-2023 clauses 4.3.1, 4.3.2). Quality deviations due to the contractor's own causes are handled as rework and are outside this card.

Further Reading

T/ZBD 100.5-2023 clause 3.1.8 (variation establishment and pricing principles); T/ZBD 100.4-2023 clauses 4.3.1-4.3.6; GB/T 50500-2024 clauses 7.1.8, 4.1.5; T/SDJZXH 004.1-2022 clause 10.6.1; GB/T 51262-2017 clause 4.6 (site inspection). May be cross-checked with the cards "five-tier expert assessment of variations without site records" and "four elements of a site instruction / variation record".

Keywords

  • 图纸与现场不一致
  • 结算工程量认定
  • 工程变更计量
  • 现场签证按实确认
  • 不予计量
  • 造价鉴定工程量
  • 五级递进认定
  • 计量成果结算依据