Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Determining the drawing basis for the final account: as-built drawings govern (as-built drawings + variation/site instruction records jointly verify the work actually completed), with construction drawings serving as the benchmark for contract-scope definition and variation-difference comparison

The final account is based on the as-built drawings — more fully stated: the qualified work actually completed is verified by 'as-built drawings + design changes, variations, site instructions / variation records and other variation documents'. GB/T 50326-2017 Clause 18.3.3 lists 'as-built drawings and variation documents' as bases for the final account without separately listing construction drawings; JGJ/T 185-2009 Clause 4.2.4 provides that absent changes, construction drawings stamped as as-built become the as-built drawings (the two being equivalent), and where changes exist, the changed content must be redrawn into the as-built drawings; the construction (contract) drawings recede in the final account to the benchmark defining the contract scope and comparing variation differences (GB/T 50500-2024 Clause 7.4.1).

Applicable Codes

  • GB/T 50326-2017 第18.3.3条
  • GB/T 50500-2024 第7.1.1条
  • GB/T 50500-2024 第7.1.8条
  • GB/T 50500-2024 第7.4.1条
  • GB/T 51095-2015 第8.2.4条
  • GB/T 51095-2015 第8.3.4条
  • JGJ/T 185-2009 第4.2.4条
  • T/ZBD 100.5-2023 第2.2.4条
  • DB37/T 5130—2018 第8.2.4条

Topic Positioning

This card answers the drawing-basis question in the final account: whether the final account follows the as-built or the construction drawings, and what role each plays in measurement for the final account. For employer and contractor in handling the final account and compiling/reviewing final account documents to fix the graphical basis of measurement and verification.

Core Conclusions

Conclusion: the final account is based on the as-built drawings — more fully: the qualified work actually completed is jointly verified by 'as-built drawings + design changes, variations, site instructions / variation records and other variation documents'; the original construction drawings do not serve alone as the measurement basis for the final account.

1. In the final account basis list, the graphical entry is 'as-built drawings'. GB/T 50326-2017 Code for Construction Project Management, Clause 18.3.3: the final account shall be based on: (1) contract documents; (2) as-built drawings and variation documents; (3) relevant technical data and material-substitution approvals; (4) pricing documents and BOQs; (5) site instructions / variation records and claim materials confirmed by both parties. — The list names only 'as-built drawings', not construction drawings separately.

2. The object of measurement for the final account is 'qualified work completed and due for measurement'. GB/T 50500-2024 Clause 7.1.1: the contract works are measured per the work the contractor has completed per the contract and that is due for measurement, quantities computed per the calculation standards and supplementary rules agreed by the parties; re-measurement, variation measurement, and additional works measurement proceed from the qualified work completed and due for measurement and from the construction drawings and variation instructions issued by the employer. Clause 7.4.1: whether the works use a re-measurable (unit-rate) or lump-sum contract, comparison of the variation instructions issued or confirmed by the employer and the actual construction drawings against the contract drawings identifies the difference BOQ items as variation items; differences between the contract drawings and the contract BOQ are BOQ defects — corrected per the rules for re-measurable contracts, not adjusted for lump-sum contracts. — The construction (contract) drawings are the 'comparison benchmark'; the as-built state (recorded by the as-built drawings) determines the quantities for the final account.

3. Relation between as-built and construction drawings (JGJ/T 185-2009 Specification for Management of Construction Documentation, Clause 4.2.4). As-built drawings shall truthfully reflect the actual state of the completed works and shall be drawn from the construction drawings, drawing-review records, designer's change instructions, and negotiation records (including technical verifications); where the construction drawings are unchanged, they may be stamped with the as-built drawing certification stamp to become the as-built drawings; as-built drawings shall carry the as-built drawing certification stamp and responsible persons' signatures. The clause commentary: negotiation content that changes drawing content must be redrawn onto the drawings; commercial negotiations unrelated to drawing content need not be reflected. — No changes: the stamped construction drawings are the as-built drawings, equivalent; with changes: the changed content is redrawn into the as-built drawings, and the final account follows the as-built drawings.

4. Measurement results signed by both parties are the final account basis. GB/T 50500-2024 Clause 7.1.8: measurement results signed and confirmed by the parties serve as the basis for contract-price adjustment and the final account, except where the contract provides otherwise, the parties expressly limit them to progress payment purposes, or the results are rough estimates.

5. Final account compilation/review bases must come as 'drawings + variation formalities'. GB/T 51095-2015 Clause 8.2.4 (compilation basis) includes: laws/regulations affecting the contract price; site survey and re-inspection records; construction contracts, specialty subcontracts and supplements, material/equipment purchase contracts; pricing bases issued by cost authorities; tendering and bid documents; construction drawings, approved project execution plans (construction methodology and site organization), design changes, negotiations, claims and site instructions / variation records, meeting minutes; employer's approvals of material and equipment prices; price additions or reductions confirmed by both parties; approved commencement/completion or stoppage/resumption reports; other relevant materials. Clause 8.3.4 (review basis) adds the review-consultancy contract and submitted final account documents. — Construction drawings alone cannot verify the work actually completed.

6. Match by scenario:

  • No changes at all: the stamped construction drawings are the as-built drawings — equivalent;
  • With design changes/negotiations: verify by as-built drawings (changes redrawn in) + variation formalities;
  • Changes not redrawn/confirmed: verify by confirmed variation documents and site instructions / variation records; parts not reflected in the as-built drawings (especially concealed works) lack support and are easily reduced at final account;
  • Lump-sum contracts: adjust only the agreed adjustable contents per the contract; the tender construction drawings define the lump-sum scope.

Applicable Boundaries

  • Applies to determining the drawing basis at the domestic employer-contractor final account stage; both re-measurable (unit-rate) and lump-sum contracts (measurement differences per GB/T 50500-2024 Clause 7.4.1).
  • Contractual agreement takes precedence: express contractual provisions on final account bases and measurement rules govern (Clause 7.1.8's 'unless otherwise agreed by the contract').
  • Final account drawings shall be jointly confirmed per the contract by the employer, contractor, designer, and supervisor, forming complete final account drawings with schedules of each discipline (paper and electronic); lump-sum contracts shall also provide the tender construction drawings and electronic versions (T/ZBD 100.5-2023 Clause 2.2.4).
  • As-built drawings must be truthful: if as-built drawings of concealed foundations, structures, underground pipelines, etc., disagree with the physical works, great difficulty and loss will be caused to the user (JGJ/T 185-2009 Clause 4.2.4 commentary).
  • This card does not replace review of specific contract clauses; final account risks where variations were not carried into the drawings should be judged against the contract's variation procedures and evidence requirements.

Further Reading

  • GB/T 50326-2017 Code for Construction Project Management, Clause 18.3.3: final account basis list (graphical entry 'as-built drawings and variation documents').
  • GB/T 50500-2024 Standard for BOQ Valuation of Construction Works, Chapter 7 'Measurement of contract works': Clause 7.1.1 (principle), 7.1.8 (use of measurement results), 7.4.1 (variation measurement and BOQ defects).
  • GB/T 51095-2015 Code for Construction Cost Consultancy, Clauses 8.2.4 and 8.3.4: compilation and review basis lists.
  • JGJ/T 185-2009 Specification for Management of Construction Documentation, Clause 4.2.4 with commentary, Appendix D (as-built drawing methods), Appendix E (folding methods).
  • T/ZBD 100.5-2023 Work Guideline for Final Account Review of Construction Works, Clause 2.2.4: four-party confirmation of final account drawings and as-built documentation requirements.
  • Local reference: DB37/T 5130-2018 Specification for Construction Cost Consulting Services, Clause 8.2.4 (compilation basis list, consistent with the national caliber).