Contract price adjustment caused by missing items in the tender bill of quantities: the clause chains of the three entries of GB 50500-2013 section 9.5 (9.5.1 to 9.3.1, 9.5.2 / 9.5.3 to 9.3.2), the four-tier valuation of all-in unit rates for new divisional and sub-divisional works items, the three-tier determination of new preliminaries, the itemisation test between unit-rate and lump-sum preliminaries, and the distinction from the quantity-deviation preliminaries linkage trigger path of clause 9.6.3

GB 50500-2013 splits 'missing BOQ items' into three mutually non-substitutable clause chains: 9.5.1 (missing divisional and sub-divisional items) fixes the rate under the four tiers of 9.3.1; 9.5.2 (new works items bringing changes to preliminaries) adjusts under 9.3.2 after the implementation plan is approved; 9.5.3 (missing preliminaries items themselves) both fixes rates under 9.3.1 and adjusts preliminaries under 9.3.2, and the plan must be submitted to the employer for approval first. The three tiers of 9.3.2: mandatory HSE provisions are calculated per 3.1.5; unit-rate preliminaries have their rates set per 9.3.1; lump-sum (or factor-based) preliminaries follow the actual adjustment amount x the contractor's quoted-price fluctuation rate. Failure to submit the plan in advance is deemed no adjustment of the preliminaries or waiver of the right to adjust. Missing items go through 9.5 / 9.3; only quantity deviations of original BOQ items over 15% (exclusive) go through 9.6.2 to adjust the all-in unit rate, with 9.6.3 adjusting factor-based or single lump-sum preliminaries up or down - the two paths must not be mixed.

Applicable Codes

  • GB 50500-2013 第9.5.1条
  • GB 50500-2013 第9.5.2条
  • GB 50500-2013 第9.5.3条
  • GB 50500-2013 第9.3.1条
  • GB 50500-2013 第9.3.2条
  • GB 50500-2013 第3.1.5条
  • GB 50500-2013 第9.6.1~9.6.3条
  • GB 50500-2013 第9.1.2~9.1.5条
  • GB/T 50500-2024 第3.2.1条
  • GB/T 50500-2024 第3.2.5条
  • GB/T 50500-2024 第8.2节
  • GB/T 50500-2024 第8.9.1条
  • GB/T 50500-2024 第8.10节
  • GB/T 50500-2024 第7.4.4条
  • TB 10801-2024 第3.11.11条

Topic positioning

Answers 'when missing items in the tender bill of quantities lead to new divisional and sub-divisional works items or new preliminaries, how are the rates and the preliminaries determined'. Taking the three clauses of section 9.5 of GB 50500-2013 as the entries, it strings together the valuation clause they lead to (9.3.1), the preliminaries adjustment clause (9.3.2), the quantity deviation linkage clauses (9.6.1~9.6.3) and the 14-day confirmation procedure (9.1.2~9.1.5), and gives the itemisation test between unit-rate and lump-sum preliminaries.

Core conclusions

1. Missing items must first be split into three entries (different clause chains, not interchangeable)

Section 9.5 has only three clauses, matching three facts:

  • 9.5.1 (missing divisional and sub-divisional items): 'During performance of the contract, where the tender bill of quantities is missing items and divisional and sub-divisional works BOQ items are added, the unit rate shall be determined per clause 9.3.1 of this code and the contract price adjusted.'
  • 9.5.2 (new items bringing changes to preliminaries): 'Where the added divisional and sub-divisional works BOQ items cause changes to preliminaries, the contract price shall be adjusted per clause 9.3.2 of this code after the implementation plan submitted by the contractor is approved by the employer.'
  • 9.5.3 (missing preliminaries items themselves): 'Where the tender bill of quantities is missing preliminaries items, the contractor shall submit the implementation plan for the new preliminaries to the employer for approval and then adjust the contract price per clauses 9.3.1 and 9.3.2 of this code.'

Key differences: 9.5.2 is a derivative consequence of added divisional works items, with the preliminaries going only through 9.3.2; 9.5.3 is omission of preliminaries items in the tender BOQ itself - rates are fixed both under 9.3.1 (rate build-up) and the preliminaries adjusted under 9.3.2. Their common precondition: the implementation plan is approved by the employer before pricing begins.

2. Valuation path for added (missing) divisional and sub-divisional items: the four tiers of 9.3.1, entering the next tier only when the previous one fails

'Where a variation causes priced BOQ items or their quantities to change, adjustment shall be made as follows: 1 Where a priced BOQ item is applicable to the varied works, the unit rate of that item shall be adopted; but where the variation causes the quantity of that BOQ item to change and the quantity deviation exceeds 15%, the unit rate of that item shall be adjusted per clause 9.6.2 of this code. 2 Where no priced BOQ item is applicable but one is analogous to the varied works, the unit rate of the analogous item may be referenced within a reasonable range. 3 Where no priced BOQ item is applicable or analogous to the varied works, the contractor shall propose the unit rate of the varied works from the variation documents, the measurement rules and the pricing method, the published price information issued by the construction cost administration and the contractor's quoted-price fluctuation rate, and shall report it to the employer for confirmation before adjustment. 4 Where no priced BOQ item is applicable or analogous to the varied works and the published price information issued by the construction cost administration lacks a price, the contractor shall propose the unit rate of the varied works from the variation documents, the measurement rules, the pricing method and lawfully based market prices obtained through market investigation, and shall report it to the employer for confirmation before adjustment.'

Tier Pricing basis Multiplied by fluctuation rate Employer confirmation needed
9.3.1-1 applicable Unit rate of that BOQ item already in the contract No No (quantity deviation over 15% goes to 9.6.2 for rate adjustment)
9.3.1-2 analogous Analogous item rate referenced within a reasonable range No Conversion basis generally needs confirmation
9.3.1-3 neither applicable nor analogous, published price available Variation documents + measurement rules + pricing method + published price information + contractor's quoted-price fluctuation rate Yes Yes
9.3.1-4 published price also unavailable Variation documents + measurement rules + pricing method + lawfully based market prices from market investigation Listed for tier 3, not listed for tier 4 Yes

Note: the two formulas for the contractor's quoted-price fluctuation rate (tendered works, non-tendered works) appear as formula images in the electronic text; they must be checked against the paper original before application and must not be presumed from the gaps in the scanned text.

3. Rules for determining new preliminaries: the plan is approved first, then pricing per the three tiers of 9.3.2

'Where a variation changes the construction method and causes the preliminaries to change, and the contractor proposes adjusting the preliminaries, it shall submit the proposed implementation plan to the employer for confirmation in advance and explain in detail the changes compared with the preliminaries of the original plan. The proposed plan is executed after confirmation by both parties, and the preliminaries shall be adjusted as follows: 1 Mandatory HSE provisions shall be calculated per clause 3.1.5 of this code on the basis of the preliminaries actually changed. 2 Preliminaries priced by unit rates shall, on the basis of the preliminaries actually changed, have their unit rates determined per clause 9.3.1 of this code. 3 Preliminaries priced on a lump-sum (or factor) basis are adjusted for the preliminaries actually changed, but the contractor's quoted-price discount shall be considered, that is, the adjustment amount is calculated as the actual adjustment amount multiplied by the contractor's quoted-price fluctuation rate per clause 9.3.1 of this code. If the contractor fails to submit the proposed implementation plan to the employer for confirmation in advance, it shall be deemed that the variation does not cause adjustment of the preliminaries or that the contractor waives the right to adjust them.'

On this basis, 'building up rates from the actual project execution plan' does not mean free pricing under the code, but: (1) the implementation plan confirmed by both parties is the factual basis for measurement and pricing; (2) unit-rate (measurable) preliminaries - the contract rates are followed or analogous rates converted for the actual changes, through tiers 1 and 2 of 9.3.1, with new rates built up through tiers 3 and 4 where nothing is applicable or analogous; (3) lump-sum (or factor) preliminaries - the actual adjustment amount multiplied by the contractor's quoted-price fluctuation rate; (4) mandatory HSE provisions are listed separately and calculated per 3.1.5.

4. Whether new preliminaries are itemised as unit-rate or lump-sum preliminaries

The 2013 edition itemises by 'unit-rate preliminary items / lump-sum preliminary items': preliminaries that can be measured as quantity x all-in unit rate under the measurement rules (scaffolding, formwork and falsework, vertical transport, entry and exit and erection and removal of large plant, dewatering and drainage, etc.) are unit-rate preliminaries, whose variation adjustment path falls in tier 2 of 9.3.2 (rate follows quantity, unit rate per 9.3.1); preliminaries that cannot be measured by quantity and are charged per item or per factor (base x percentage rate) (mandatory HSE, night works, secondary handling, winter and rainy season works, temporary facilities, etc.) are lump-sum preliminaries, whose adjustment path falls in tier 3 (multiplied by the quoted-price fluctuation rate). The test is essentially whether the preliminary can be measured under the national or sector quantity take-off standard; the itemisation mode directly determines the later adjustment basis. GB/T 50500-2024 clause 3.2.1 has changed the approach: 'For items in the divisional and sub-divisional works list and the preliminaries list priced on a unit-rate basis, the price of each BOQ item shall be its quantity multiplied by the corresponding all-in unit rate; for items priced on a lump-sum basis, the price of the BOQ item shall be calculated per item. The divisional and sub-divisional works list should preferably be priced on a unit-rate basis, and the preliminaries list on a lump-sum basis.' It also provides that, where the employer agrees in the contract that the construction method plan of dedicated preliminary items that must pass expert panel review may be priced on a unit-rate basis, it is itemised in the divisional and sub-divisional works list.

5. Distinction of the trigger paths against the 9.6.3 quantity-deviation preliminaries linkage (missing items vs quantity deviation)

  • 9.6.1: 'During performance of the contract, where the quantities to be paid deviate from the tender bill of quantities and the conditions of clauses 9.6.2 and 9.6.3 of this code are met, both parties shall adjust the contract price.'
  • 9.6.2: 'For any tender BOQ item, where the quantity deviation due to the quantity deviation provisions of this section and the variations under section 9.3 and other causes exceeds 15%, adjustment may be made. Where the quantity increases by more than 15%, the all-in unit rate of the increased portion of the quantity shall be adjusted down; where the quantity decreases by more than 15%, the all-in unit rate of the remaining portion of the quantity after the decrease shall be adjusted up.'
  • 9.6.3: 'Where the quantity change of clause 9.6.2 of this code causes corresponding changes in the related preliminaries, for preliminaries priced by factor or as a single lump sum, the preliminaries are adjusted up when the quantity increases and down when the quantity decreases.'

Path distinction: (1) missing items (an item from nothing) - 9.5 - 9.3.1 / 9.3.2; there is no premise of 'deviation against the tender BOQ quantity', and 9.6.3 must not be applied to adjust the preliminaries; (2) quantity deviation of original BOQ items (increase or decrease of the quantity of the same BOQ item) - 9.6.2 adjusts only the portion beyond (over +15% the increased portion is adjusted down) or the remaining portion (below -15% the remaining portion after the decrease is adjusted up), and only where both 'the change causes corresponding changes in the preliminaries' and 'the preliminaries are priced by factor or as a single lump sum' are met does 9.6.3 adjust the preliminaries up or down; (3) the 'quantity deviation over 15% referring back to 9.6.2' within 9.3.1-1 is a rate correction inside variation valuation, not the same as the preliminaries channel of 9.6.3, and the two are not interchangeable.

6. Settlement confirmation procedure (the 14-day time-limit chain)

  • 9.1.2: within 14 days after an event of contract price increase (excluding quantity deviation, dayworks, site instruction records and claims), the contractor shall submit an increase report with supporting documents; failure to submit within 14 days is deemed that the contractor makes no price adjustment claim for that event.
  • 9.1.3: within 14 days after an event of decrease (excluding quantity deviation and claims), the employer shall submit a decrease report with supporting documents; failure to submit is deemed that the employer makes no adjustment claim.
  • 9.1.4: the employer (contractor) verifies within 14 days of receiving the report and documents and, where confirming, gives written notice; failure to confirm or raise negotiation comments within 14 days is deemed that the submitted report has been approved; where the other party raises negotiation comments, they shall be verified and confirmed in writing within 14 days of receipt, and failure to confirm or comment within 14 days is deemed approval of the other party's comments.
  • 9.1.5: where the parties disagree on the adjustment, so long as it does not materially affect performance, the contractual obligations shall continue to be performed until the dispute is resolved as agreed in the contract. Practical upshot: the full chain for new preliminaries from missing items = plan (submitted and approved first) -> measurement (per the approved plan / actual occurrence) -> pricing (four tiers of 9.3.1 / three tiers of 9.3.2) -> reporting and review (14-day confirmation or deemed approval); missing the time limit at any link may mean the right is deemed waived.

Applicability boundaries

  • The factual premise of each clause of 9.5 is missing items in the tender BOQ (the list provided by the tenderer omits divisional works items or preliminaries items); omissions in the contractor's own quotation, or pricing preliminaries at zero at tender, are outside the adjustment scope of these clauses and follow the rules of lump-sum preliminaries and self-borne risk.
  • Quantity deviation of the same BOQ item does not fall under 9.5 but under 9.6.2 / 9.6.3; the threshold of 9.6.2 is 'exceeds 15%' - exactly 15% does not trigger.
  • Tier 4 of 9.3.1 does not list the quoted-price fluctuation rate, while tier 3 of 9.3.2 expressly multiplies it; the two must not be simply stacked or swapped. The fluctuation rate formulas must be checked against the paper original.
  • Mandatory HSE provisions (called the statutory work safety levy in railway practice) are calculated separately per 3.1.5, are non-competitive and do not follow the other preliminaries in fluctuation-rate adjustment.
  • GB/T 50500-2024 has changed the approach: missing BOQ items fall under 'BOQ errors and omissions', handled in section 8.2 by contract type (lump-sum contracts are not adjusted except items priced by unit rate at provisional quantities), and works added outside the contract scope go to section 8.10; the 2024 edition is a recommended standard and special contractual agreement prevails.
  • Sectors (railway, highway, water conservancy, power) differ in the division of preliminaries items and the charging basis; itemisation follows the sector pricing standard and local supplementary rules applicable to the project.

Further reading

  • GB 50500-2013: clauses 9.5.1, 9.5.2 and 9.5.3 (the three entries for missing items); clause 9.3.1 (four-tier valuation), clause 9.3.2 (three tiers for preliminaries), clause 3.1.5 (calculation basis of mandatory HSE provisions); clauses 9.6.1~9.6.3 (quantity deviation and preliminaries linkage); clauses 9.1.2~9.1.5 (14-day time limits and deemed approval).
  • GB/T 50500-2024 (old vs new approach): clause 3.2.1 (unit-rate / lump-sum pricing and preliminaries preferably lump-sum), clause 3.2.5 (non-competitiveness of statutory safety provisions), section 8.2 (BOQ errors and omissions), clause 8.9.1 (five-tier variation valuation), clauses 8.9.5~8.9.7 (additionally added preliminaries and loss of the right on late submission), section 8.10 (additional works), clause 7.4.4 (measurement of varied preliminaries).
  • Railway wording: the term statutory work safety levy, TB 10801-2024 clause 3.11.11.

Keywords

  • 清单缺项
  • 措施项目缺项
  • 新增措施项目
  • preliminaries
  • 9.5.1
  • 9.5.2
  • 9.5.3
  • 9.3.1
  • 9.3.2
  • 承包人报价浮动率