Rules for fixing the scope and items of construction cost expert assessment on the variation part of the works: admission filtering of court-commissioned assessment, slicing of the scope, the valuation basis for variations, and cross-examination of assessment materials (Civil Procedure Law Article 79; Fa Shi [2020] No. 25 Articles 29/32/33/34; Fa [2020] No. 202 Articles 1-5; GB/T 51262-2017 Articles 5.5.2/5.5.3/5.6.1)

Assessment resolves only specialised issues in the ascertainment of facts, and the scope must be cut narrow and precise: assessment scope = disputed variation items x within specialised issues (computing money only) x not locked by a settlement agreement or express contractual agreement x assessment materials established through cross-examination. Whether a variation is established, how liability is apportioned, how the contract is interpreted, and the application of law must never be referred to the assessment institution. Where a lump-sum contract has a measurement dispute and no agreed measurement standard, assessment covers the variation part of the works only (GB/T 51262-2017 Article 5.5.3); valuation of variations follows a three-tier path: contract provides -> follow the agreement / provision unclear -> price per actual performance / no provision -> refer the decision to the commissioning party, and where it withholds its decision, an opinion may be issued under the current national pricing standard (Article 5.6.1).

Applicable Codes

  • 《中华人民共和国民事诉讼法》(2023修正)第七十九条
  • 《最高人民法院关于适用〈中华人民共和国民事诉讼法〉的解释》(法释〔2015〕5号,2022修正)第一百二十一条
  • 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》(法释〔2020〕25号)第二十九条、第三十二条、第三十三条、第三十四条
  • 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号,2026年6月30日施行)第十三条、第二十三条
  • 《最高人民法院关于人民法院民事诉讼中委托鉴定审查工作若干问题的规定》(法〔2020〕202号,2020年9月1日施行)第1~5条、第12~17条
  • 《建设工程造价鉴定规范》GB/T 51262-2017 第2.0.3、3.2.2、3.3.2、4.7.3、5.2.1、5.5.2、5.5.3、5.6.1条
  • 《建设工程造价鉴定作业指引》T/ZBD 100.4-2023 第2.1.4、2.1.5、3.1.7、4.2.3条
  • 《中华人民共和国民法典》第五百四十三条、第五百四十四条

Topic Positioning

This card resolves the procedural-plus-technical crossover question in litigation or arbitration: 'when the variation part of the works requires a construction cost expert assessment, how the court (or the commissioning party) fixes the assessment scope and the items referred for assessment'. First settle 'whether assessment is admissible, what is assessed, and to what extent', then 'how the money is computed'. It serves three scenarios: a cost consultancy commissioned to issue an assessment opinion, counsel cross-examining an assessment opinion, and a contractor claiming variation disputes.

Core Conclusions

1. The defining formula

Assessment scope = disputed variation items x within specialised issues (computing money only) x not locked by a settlement agreement or express contractual agreement x assessment materials established through cross-examination

Doctrinal basis: assessment resolves only specialised issues of fact-finding -- Article 79 of the Civil Procedure Law: 'A party may apply to the people's court for assessment of specialised issues in the ascertainment of facts... where no party applies for assessment but the people's court considers assessment necessary for a specialised issue, it shall commission a qualified assessor to conduct the assessment.' Article 121 of the Interpretation of the Supreme People's Court on the Application of the Civil Procedure Law: 'An application for assessment may be made before the expiry of the time limit for producing evidence. Where the matter applied for assessment has no bearing on the facts to be proven, or is meaningless for proving the facts to be proven, the people's court shall not permit it.' Once permitted, the scope is fixed by the court: Article 33 of the Interpretation on Construction Contract Cases (I) (Fa Shi [2020] No. 25): 'After permitting a party's application for assessment, the people's court shall, according to the party's application and the needs of ascertaining the facts of the case, determine the items, scope and time limit of the commissioned assessment, and organise the parties to cross-examine the disputed assessment materials.'

2. Seven operational steps for fixing the scope

Step Key points Basis
(1) Fix the list of disputes Itemise the disputed variation items from the statement of claim, the defence, the final account submission and the review report (item number / location / variation content / claimed amount / grounds of objection); undisputed variation items are kept out of the assessment scope Fa Shi [2020] No. 25 Article 33; T/ZBD 100.4-2023 Article 4.2.3 'list the focus and basis of each disputed item and assess the disputed part only'
(2) Negative-list admission filtering Screen each item against the scenarios in which assessment must not be commissioned (see the scenarios below) Fa [2020] No. 202 Article 1; Interpretation of the Civil Procedure Law Article 121(1)
(3) Exclude prices already locked Where the project price was settled by agreement before litigation, cost assessment is not permitted; for measurement results already signed off, mere objection without evidence leaves the original result, and only objection with specific evidence triggers re-checking Fa Shi [2020] No. 25 Article 29; GB/T 51262-2017 Article 5.5.2
(4) Slice the scope by contract type Lump-sum contract measurement dispute: where the contract prescribes the measurement standard, assess under it; where it does not, assess the variation part of the works only, without re-measuring all works under the contract GB/T 51262-2017 Article 5.5.3
(5) Fix the pricing basis before computing money Variation valuation ladder: contract provides -> assess under the agreement; provision unclear -> ascertain actual performance and price on the basis actually performed; no provision -> refer the decision to the commissioning party, and where it withholds its decision, assess under the current national pricing standard for its judgement GB/T 51262-2017 Article 5.6.1; Civil Code Articles 543 (variation by agreement) and 544 (variation with unclear content is deemed not made)
(6) Write into the commission letter and explain The commission letter must state the name of the assessment institution, the purpose of assessment, the scope and items, the assessment requirements and the name of the commissioning party; where the institution holds a different view on the scope it shall explain it to the commissioning party, and after the explanation assesses per the commissioning party's decision; where the parties dispute the scope again during assessment, the assessors shall promptly refer it to the commissioning party and may not enlarge or reduce the scope on their own GB/T 51262-2017 Articles 3.2.2, 3.3.2 and 5.2.1
(7) Send only after cross-examination; strike out out-of-scope opinions Materials not cross-examined in court (including supplementary materials) may not serve as assessment materials; disputed materials are determined by the court and may not be handed directly to the assessment institution or chosen by the assessors; where the assessors rely on disputed materials not cross-examined, the assessment opinion based on such materials may not serve as the basis for finding facts Fa [2020] No. 202 Articles 4 and 5; Fa Shi [2020] No. 25 Article 34

3. Negative list for admissible assessment items (Fa [2020] No. 202 Article 1) 'The proposed assessment item shall be strictly examined as to whether it is a specialised issue for ascertaining the facts of the case; where any of the following applies, the people's court shall not commission assessment: (1) facts that can be presumed from general knowledge or empirical rules; (2) issues unrelated to the facts to be proven; (3) issues meaningless for proving the facts to be proven; (4) non-specialised issues to be proven by the parties; (5) facts ascertainable through court investigation or inspection; (6) determinations on the apportionment of the parties' liability; (7) issues of application of law; (8) lie detection; (9) other circumstances unsuitable for commissioned assessment.' Article 2 adds: 'Where the assessment techniques and methods for the proposed item are seriously contested, their scientific reliability shall be examined first. Where those techniques and methods lack scientific reliability, assessment shall not be commissioned.' -> Practical implication: whether a variation 'is established, who bears responsibility, and how the contract clause is interpreted' belong to the court's adjudication; only 'the cost amount of the disputed variation item' may be sent for assessment.

4. Technical scope-fixing rules for the variation part

  1. Lump-sum contracts assess variations only: where the parties dispute measurement under a lump-sum contract and the contract prescribes a measurement standard for the works, assess under it; where it does not, assess the variation part of the works only (GB/T 51262-2017 Article 5.5.3).
  2. Treatment of measurement results already signed off (Article 5.5.2): where a party objects to the measurement result of a work item already signed off by both parties -- (1) objection raised without specific evidence: assess per the original measurement result; (2) objection raised with specific evidence: re-check the original measurement result, on site where necessary, and assess per the re-checked result.
  3. Variation valuation disputes (Article 5.6.1): where a change in quantities caused by a variation calls for adjustment of the all-in unit rate, or a dispute arises over the rate build-up for an additional work item -- (1) where the contract provides, assess per the contract; (2) where the provision is unclear, ascertain how the contract was performed: if performed per the contract, propose to the commissioning party to assess on that basis; if not performed, assessment may follow the relevant provisions of the current national pricing standard for the commissioning party's judgement; (3) where the contract is silent, refer the decision to the commissioning party and assess per its decision; where the commissioning party withholds its decision, assessment may proceed under the current national pricing standard for its judgement. The commentary to the standard points to the Code of Valuation with Bill of Quantities for Construction Works GB 50500, the rationale being that agreed terms prevail and that after a variation fairness must be rebuilt on the new premises (scope of contract works / design standard / construction conditions).
  4. Dispute types and minimising the scope: by nature of the dispute, cost expert assessment divides into five classes -- measurement disputes, pricing disputes, variation disputes, claims disputes and other disputes -- which may be commissioned singly or in combination; to avoid wasting social resources and adding to the parties' burden, the scope and content of assessment should be minimised to the disputed items and their content only; the workload cannot be measured by the amount in dispute alone, and the assessment fee should reflect the class of assessment (T/ZBD 100.4-2023 Article 2.1.4). The scope and content may be as broad as all works under the contract or as narrow as a particular item of work, work completed by a particular party, or one or more components such as labour cost, material cost and construction plant cost (Article 2.1.5).
  5. Form of opinion where the factual basis is disputed (Article 3.1.7): dispute over which drawing version applies -> determine from the evidence submitted by the parties and avoid issuing alternative opinions; dispute over variation facts or documentation -> issue a definitive or alternative opinion according to the completeness of the documentation; claims disputes -> definitive or alternative opinion according to the truth of the events and the evidentiary support; facts verifiable by site inspection -> definitive opinion on the basis of the inspection record.
  6. Contradictory evidence (GB/T 51262-2017 Article 4.7.3): where a party disputes the authenticity of the evidence or items of evidence contradict each other, the assessors shall promptly refer the matter to the commissioning party for determination and take the determination as the basis of assessment; where the commissioning party fails to determine in time or requires opinions in several versions on the contested evidence, the assessors shall, after seeking the parties' views and recording them in writing, assess the contested evidence separately and list those opinions separately.

5. Boundary between new and old rules (Fa Shi [2026] No. 12, Interpretation on Construction Contract Cases (II)) Article 13: where the parties agree that the price is determined by the audit conclusion of the audit organ or the review conclusion of the government fiscal review institution, but (1) the audit conclusion or review conclusion is not issued within a reasonable period for reasons not attributable to the contractor, or (2) the contractor has evidence that the audit conclusion or review conclusion obviously contradicts the construction contract, and the contractor applies for judicial assessment of the construction cost, the people's court shall permit it. The reasonable period follows the parties' agreement; absent agreement, the court fixes it comprehensively by project scale, cost amount and complexity, but the period may not exceed one year from the contractor's submission of the final account documents. Where the price was not agreed to be determined by the audit conclusion or review conclusion, the employer's request to determine the project price thereby is not supported. Article 23 (time boundary): 'This Interpretation takes effect on 30 June 2026. It applies to first-instance construction contract dispute cases newly accepted by the people's courts after its entry into effect. Where judicial interpretations previously issued by the Supreme People's Court conflict with this Interpretation after its entry into effect, this Interpretation prevails.' -> first-instance cases newly accepted after 30 June 2026 follow the new interpretation; cases accepted before that still follow the former rules such as Fa Shi [2020] No. 25.

6. Procedural time limits and sanctions (Fa [2020] No. 202 Articles 12-14) The court shall explain the legal consequences of failing to prepay the assessment fee and the assessor's court appearance fee within the time limit and supervise the charges; the assessment time limit is no more than 30 working days for ordinary cases and no more than 60 working days for major, difficult or complex cases, extension requiring a written application decided by the court; where the assessors fail to submit the written assessment on time without justified reason and the court permits re-commissioning, the original assessment institution and assessors shall be ordered to refund the fees received. Assessment institutions and assessors that assess beyond the commissioned scope, issue false assessments, delay without justified reason, refuse to appear in court to testify, or charge in breach of the rules may have commissioning suspended, be ordered to refund fees, be removed from the pre-selected roster and receive judicial recommendations, under a blacklist regime for assessors.

Boundaries of Application

  • Applies to fixing the scope of judicial assessment for variation, measurement and pricing disputes in construction contract litigation; administrative audit and government fiscal review conclusions cannot directly replace the contractually agreed price-determination mechanism (unless the parties expressly so agree).
  • The consequences of failing to prove fall on the party bearing the burden of proof: for disputed specialised issues such as cost, quality or repair cost, the court shall explain this to the party bearing the burden; 'where, after the explanation, the party does not apply for assessment, or applies but does not pay the assessment fee or refuses to provide the relevant materials, it bears the legal consequences of failing to prove'; where no application was made at first instance but is made at second instance and the court deems it truly necessary, Article 170(1)(3) of the Civil Procedure Law applies (Fa Shi [2020] No. 25 Article 32).
  • The conclusions resolve 'scope and procedure' only; whether a specific variation item can be priced, and how the rates are built up, must be judged separately under the contract and the pricing standards.
  • The above articles follow the currently effective versions; the same disputed point may attract different interpretations for cases accepted before and after 30 June 2026 -- verify the case acceptance date before citing.

Further Reading

  • Civil Procedure Law of the PRC (2023 amendment), Article 79.
  • Interpretation of the Supreme People's Court on the Application of the Civil Procedure Law of the PRC (Fa Shi [2015] No. 5, 2022 amendment), Article 121.
  • Interpretation of the Supreme People's Court on the Application of Law to Construction Contract Dispute Cases (I) (Fa Shi [2020] No. 25), Articles 29, 32, 33 and 34.
  • Interpretation of the Supreme People's Court on the Application of Law to Construction Contract Dispute Cases (II) (Fa Shi [2026] No. 12), Articles 13 and 23.
  • Provisions of the Supreme People's Court on Several Issues concerning the Review of Commissioned Assessment in Civil Litigation of the People's Courts (Fa [2020] No. 202), Part I 'Review of assessment items' Articles 1-2, Part II 'Review of assessment materials' Articles 3-5, Part VI 'Strengthening supervision of assessment activities' Articles 12-17 (effective 1 September 2020; commissioned assessment in administrative litigation applies by reference).
  • Code for Construction Cost Assessment GB/T 51262-2017, Articles 2.0.3 (terminology of assessment items), 3.2.2, 3.3.2, 4.7.3, 5.2.1, 5.5.2, 5.5.3 and 5.6.1.
  • Guidelines for Construction Cost Assessment Practice T/ZBD 100.4-2023, Articles 2.1.4, 2.1.5, 3.1.7 and 4.2.3.
  • Civil Code of the PRC, Articles 543 and 544.
  • Interface with variation pricing standards: the current Code of Valuation with Bill of Quantities for Construction Works GB 50500 (as indicated in the commentary to GB/T 51262-2017 Article 5.6.1).

Keywords

  • 工程造价鉴定范围
  • 工程变更鉴定
  • 委托鉴定事项
  • 不予委托鉴定
  • 鉴定材料质证
  • 建工解释二第十三条
  • 审计结果司法鉴定
  • 总价合同仅变更部分鉴定