Where statutory levies went after the 2024 BOQ pricing system dropped them as a separate line: social insurance and housing fund for production workers into labour cost; social insurance and housing fund for management staff and the works pollution charge (environmental protection tax) into overheads; urban maintenance and construction tax and surcharges likewise into overheads

The levies were not abolished but 'unbundled and no longer separately listed': GB/T 50500-2024 clause 3.1.2 makes the BOQ four parts - the works bill, the bill of preliminaries, the bill of provisional sums and other charges, and value added tax - leaving no slot for statutory levies at BOQ level; clause 3.1.6 requires the all-in unit rate and the item price to be 'fully inclusive pre-tax prices excluding VAT', which semantically absorbs the former levies into labour cost and overheads. The concrete destinations are fixed by the provincial expense norms: social insurance and housing fund for production workers (construction workers) go into labour cost; social insurance and housing fund for management staff and the works pollution charge (adjusted to the environmental protection tax under state provisions) go into overheads; urban maintenance and construction tax, education surcharge and local education surcharge also go into overheads.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 2.0.9、3.1.2、3.1.6、3.2.11 条
  • 《湖北省建筑安装工程费用定额》(2024)费用定额说明第四至第八条
  • 《陕西省建设工程费用规则》(2025)第 8.8 条其他说明
  • DB 61/T 5126-2025《陕西省建设工程工程量清单计价标准》
  • 建标〔2013〕44号《建筑安装工程费用项目组成》
  • 财资〔2022〕136号《企业安全生产费用提取和使用管理办法》
  • GB 50861-2013 · Code for Measurement of Quantities of Urban Rail Transit Works 第 4.1.2 条(旧版对比)

Topic positioning

Answers 'where the statutory levies went in the 2024 BOQ pricing system': with the levies line removed from the four-part BOQ structure, the concrete account destinations of the former levy items (labour cost / overheads / value added tax), with the national-standard clauses and the original wording of the provincial expense norms, for use in rate build-up, cost unbundling and reconciliation.

Core conclusions

1. At BOQ level: done by 'dropping the line', not by an express 'merge-in' clause

  • GB/T 50500-2024 clause 3.1.2: 'The bill of quantities shall be prepared and priced by the works bill, the bill of preliminaries, the bill of provisional sums and other charges, and value added tax respectively. Where pricing adopts another bill format, the rules of this standard still apply, and specific provisions may be made by the employer and the contractor with reference to this standard.' The clause text leaves no slot for a levies bill or a taxes bill.
  • Clause 2.0.9, term 'all-in unit rate': 'The all-in unit rate of a BOQ item covers labour cost, material cost, plant and small tools cost, overheads, profit and risk costs within a defined range; it does not include value added tax.' - no levies among the components.
  • Clause 3.1.6: 'The all-in unit rate and item price of BOQ items shall be fully inclusive pre-tax prices excluding value added tax, composed of labour cost, material cost, plant and small tools cost, overheads and profit, including risk costs within the agreed or reasonable range of the item and the cost of indispensable auxiliary work; the taxes of BOQ items shall be entered under value added tax, except that provisional sums for nominated specialist subcontract works within the bill of other items already include VAT, and the VAT of the bill of quantities must not charge their tax again.' - 'fully inclusive pre-tax' means every cost destined for the all-in unit rate must already be absorbed into labour cost or overheads, otherwise 'fully inclusive' fails; so clause 3.1.6 does not exclude the levies but requires their absorption.
  • Clause 3.2.11: value added tax 'shall take the total of the works bill, the bill of preliminaries and the bill of other items (excluding provisional sums for nominated specialist works) as the calculation base, multiplied by the VAT rate set by the government authority' - i.e. the total of the bill of other items used for tax computation deducts the nominated-works provisional sums it contains.

2. Which account absorbs what: expressly fixed by the provincial expense norms (the national standard stops at 'dropping the line')

  • Hubei Building and Installation Works Expense Norms (2024), expense-notes clause 8: 'To advance the market-oriented reform of construction costs, these expense norms abolish the separate listing of statutory levies in the cost composition of building and installation works. Of the former levies, the social insurance and housing fund paid for production workers are entered in labour cost; the social insurance and housing fund paid for management staff and the works pollution charge (adjusted to the environmental protection tax under state provisions) are entered in overheads.'
  • Shaanxi Works Construction Expense Rules (2025), clause 8.8 other notes item 2: 'Per the Shaanxi DB 61/T 5126-2025, BOQ Pricing Standard for Works Construction, the social insurance and housing fund within the levies is split into the part the employer pays for construction workers and the part the enterprise pays for management staff; these rules enter the employer-paid part of construction-worker social insurance in labour cost, and the employer-paid part of management-staff social insurance in overheads.'
  • Same clause item 4: 'Per the Ministry of Housing notice printing the minutes of the seminar on research and implementation of the VAT reform measures (Jian Biao Zao (2016) No. 49), these rules enter the urban maintenance and construction tax, education surcharge and local education surcharge in overheads.' Item 3: per Cai Zi (2022) No. 136, the work-safety liability insurance for construction is entered in the mandatory HSE provisions; item 1: per Jian Biao (2013) No. 44, inspection and testing costs are entered in overheads.

3. Contrast with the 2013 basis The old version listed them separately at BOQ level and made them non-competitive: the other-items, levies and taxes bills were prepared per the relevant GB 50500 provisions; the levies bill covered social insurance, housing fund and the works pollution charge; the taxes bill covered business tax, urban maintenance and construction tax, education surcharge and local education surcharge (see GB 50861-2013, Code for Measurement of Urban Rail Transit Works, clause 4.1.2 and its commentary). The 2024 version drops the levies bill and the taxes bill together, with taxes now carried by a single value added tax line. In one sentence: 2013 - a stand-alone cost outside the BOQ items; 2024 - an implicit cost inside the all-in unit rate.

4. Migration of the non-competitive costs With levies no longer separately listed, the Hubei 2024 expense norms still state: value added tax is non-competitive and shall be charged as prescribed (clause 5); the mandatory HSE provisions are non-competitive, charged at the prescribed percentage rate when preparing the tender price ceiling or a tender, with the work-safety liability insurance at settlement computed on the amount actually paid and the rest still by percentage rate (clause 7).

Applicability boundaries

  • GB/T 50500-2024 settles only 'no levies line at BOQ level'; whether amounts go into labour cost or overheads is a matter for local or sectoral expense standards - always follow the wording of the provincial expense norms or sectoral expense standard applicable to the project; the two provinces split social insurance at different granularity (Hubei by production worker / management staff, Shaanxi by construction-worker insurance / management-staff insurance) but the destinations agree.
  • This card applies to building, municipal and similar works priced under GB/T 50500-2024 and its companion provincial expense norms; highway, water and other sectors do not treat levies uniformly (some still list them as stand-alone costs), so confirm the applicable sectoral standard before cross-sector use; do not carry this card's conclusion over directly.
  • Dropping the levies line at BOQ level does not extinguish the statutory payment obligations: social insurance and housing fund and the environmental protection tax remain statutory outlays - only their character changes, from non-competitive costs separately listed at prescribed rates to competitive costs the tenderer absorbs itself within its labour and overhead rates.
  • Rate build-up impact: the all-in unit rate build-up sheet no longer carries a levies row; the labour rate and the management-staff payroll basis must include the employer-paid social insurance and housing fund, or costs will be missed.

Further reading

  • GB/T 50500-2024, BOQ Pricing Standard for Construction Works: clause 2.0.9 (term 'all-in unit rate', expressly excluding VAT), clause 3.1.2 (four-part BOQ preparation and pricing), clause 3.1.6 (fully inclusive pre-tax price and no double tax on nominated-works provisional sums), clause 3.2.11 (VAT base and rate).
  • Hubei Building and Installation Works Expense Norms (2024), expense notes clauses 4 to 8 (clause 4: the charging base for each trade is labour cost plus plant and small tools cost; clause 5: VAT non-competitive; clause 6: the mandatory HSE provisions exclude the extra cost of safety-standard demonstration sites and similar awards; clause 7: pricing of the mandatory HSE provisions; clause 8: dropping the separate levies line and the destinations).
  • Shaanxi Works Construction Expense Rules (2025), clause 8.7 (composition of the construction-drawing budget) and clause 8.8 other notes items 1 to 5 (inspection and testing costs, social-insurance split, work-safety liability insurance, city construction tax and surcharges, advance-payment funding cost).
  • GB 50861-2013, Code for Measurement of Urban Rail Transit Works, clause 4.1.2 and its commentary (old levies and taxes bill composition - for version comparison only, no longer cited as a current pricing basis).