statutory levies and fees

12 knowledge cards · sorted by most recently updated

Concept Guide

Concept

Statutory levies and fees (规费) is a mandatory cost category in Chinese construction pricing. It covers the statutory social insurance contributions (pension, unemployment, medical, work injury, maternity) and the housing provident fund that must be calculated at rates set by national or provincial authorities. Under the GB 50500 bill-of-quantities pricing system, statutory levies and fees, together with safety and civilized-construction measures, are classed as non-competitive: bidders may not discount or waive them.

Mechanism: the employer lists statutory levies and fees as a separate item in the bill of quantities; the bidder applies the rate published by the provincial cost-management authority, normally on a base of labour cost (or labour plus plant). The rate comes from local documents and does not move with competition; at settlement it is adjusted to the confirmed base. Money flows from the employer to the contractor, which then remits it to the social insurance agency and the housing provident fund centre - a collection-and-remittance role, so it never becomes competitive margin.

FIDIC Mapping

FIDIC has no separate non-competitive line for such statutory levies and fees. Sub-Clause 1.1.19 defines Cost as all expenditure reasonably incurred by the Contractor, including taxes, overheads and similar charges; such statutory payments must already sit inside that Cost and inside the Contractor's price. Sub-Clause 6.1 [Engagement of Staff and Labour] obliges the Contractor to arrange engagement, payment, accommodation, feeding, transport and welfare of all Contractor's Personnel; Sub-Clause 19.2.5 [Injury to Employees] requires insurance against injury, sickness, disease or death of employees. So the same money appears, but as a competitively priced cost and insurance premium rather than an administratively fixed levy. A Chinese practitioner who carries the "non-competitive" assumption into a FIDIC contract will see it treated as a discount or an omission, with no employer compensation for changes in local statutory rates.

Chinese TermEnglish TermFIDIC TermRelationNotes
规费statutory levies and feesCost (Sub-Clause 1.1.19)absent中国规费按行政费率强制计取、不可竞争,独立于成本科目;FIDIC 无对应科目,法定社保与公积金缴费落入 1.1.19 Cost 的 taxes、overheads and similar charges,由承包人自主测算、市场竞争形成,费率变动风险由承包人承担。
人工费与用工福利engagement, payment and welfare of Contractor's PersonnelSub-Clause 6.1 [Engagement of Staff and Labour]adjacent中国以规费科目统一计取社保与公积金;FIDIC 把雇佣、报酬、食宿、交通与福利整体交由承包人自行安排(规范另有规定除外),属可竞争的间接成本,不设政府定价的独立科目。
员工伤害保险insurance against injury to employeesSub-Clause 19.2.5 [Injury to Employees]adjacent中国工伤保险由法定规费覆盖、按费率统一计取;FIDIC 要求承包人自费投保并保持雇主责任险有效,属商业保险成本计入合同价格,与行政强制计取的口径不同。