GB 50500-2013 -> GB/T 50500-2024: changes to the clauses on statutory levies and fees, taxes and the mandatory health, safety and environmental (HSE) provisions — mandatory provisions withdrawn, the bills restructured into four parts, and the item renamed statutory safety provisions
2013 Clause 3.1.6, “statutory levies and fees and taxes must be calculated in accordance with the provisions of the state, provincial or industry construction authorities and shall not be treated as competitive costs” (a mandatory provision), disappears entirely from GB/T 50500-2024: the 2024 edition is a recommended GB/T standard with no mandatory provisions anywhere; under Clause 3.1.2 the bills become four parts (work items / preliminaries / provisional sums and other charges / VAT), statutory levies and fees are no longer a separate billed item, and taxes are renamed VAT (Clause 3.2.11: the tax base is the total of work items + preliminaries + other items, less the provisional sum for nominated specialist subcontract works, multiplied by the tax rate). The mandatory health, safety and environmental (HSE) provisions are renamed “statutory safety provisions” (Clause 3.2.5), and their “non-competitive” character is expressly retained (“is a non-competitive item”), but the wording is softened from “must ... shall not be treated as competitive costs” to “shall be priced in accordance with the relevant provisions of the state and provincial or industry authorities”. GB/T 50500-2024 takes effect on 1 September 2025, and GB 50500-2013 is repealed at the same time.
Applicable Codes
- GB 50500-2013 第3.1.5、3.1.6条(强制性条文)
- GB/T 50500-2024 第3.1.2、3.2.5、3.2.11、2.0.9、3.1.6条
- 建办〔2005〕89号《建筑工程安全防护、文明施工措施费及使用管理规定》
- https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2024/art_6186304e164c4c4982904f8734983235.html
Topic Positioning
This card compares the Code of Bills of Quantities and Valuation for Construction Works GB 50500-2013 (mandatory national standard) with the Standard for Bills of Quantities and Valuation for Construction Works GB/T 50500-2024 (recommended national standard) as regards statutory levies and fees, taxes and the mandatory health, safety and environmental (HSE) provisions: whether the mandatory provisions survive, how the “non-competitive” character is restated, and how the bill structure and terminology are renamed — for pricing practice, contract interpretation and training during the transition between the old and the new standard.
Core Conclusions
I. The two 2013 mandatory provisions (GB 50500-2013, set in bold as mandatory provisions and to be strictly enforced):
- Clause 3.1.5: “The mandatory health, safety and environmental (HSE) provisions within the preliminaries must be calculated in accordance with the provisions of the state, provincial or industry construction authorities and shall not be treated as competitive costs.” Under Jianban [2005] No. 89, Provisions on the Administration of Safety Protection and HSE Construction Preliminary Costs for Building Works and Their Use, this cost falls within the scope of mandatory national standards and comprises the four preliminaries items of HSE construction cost, environmental protection cost, temporary works and site establishment cost and safe construction cost; the employer may not require the tenderer to offer a discount, and the tenderer may not compete on it.
- Clause 3.1.6: “Statutory levies and fees and taxes must be calculated in accordance with the provisions of the state, provincial or industry construction authorities and shall not be treated as competitive costs.”
II. 2024 edition: the mandatory sentences are removed, the substance is retained in the new structure:
- Nature of the standard: the 2013 edition was a mandatory national standard (GB), its bold clauses carrying mandatory force; the 2024 edition is a recommended national standard (GB/T 50500-2024) containing no “mandatory provisions” at all, so the former mandatory clauses lapse with it — the whole sentence “must ... shall not be treated as competitive costs” no longer exists.
- Bill structure (Clause 3.1.2): from five parts (work items, preliminaries, other items, statutory levies and fees, taxes) to four — “bill of work items, bill of preliminaries, bill of provisional sums and other charges, and VAT”, prepared and priced separately; statutory levies and fees are no longer a standalone billed item, and taxes are renamed VAT.
- VAT (Clause 3.2.11): the tax base is the aggregate of the bill of work items, the bill of preliminaries and the bill of provisional sums and other charges (excluding the provisional sum for nominated specialist subcontract works), multiplied by the VAT rate prescribed by the competent government authority; the aggregate of the other-items bill used for calculating VAT shall deduct the provisional sum for nominated specialist subcontract works contained in it.
- Pricing basis (Clauses 2.0.9 and 3.1.6): the all-in unit rate comprises labour cost, material cost, plant and small tools cost, overheads, profit and risk costs within a specified range, and excludes VAT (a price-exclusive tax); the all-in unit rates and totals of billed items shall be fully inclusive prices excluding VAT; the provisional sum for nominated specialist subcontract works in the other-items bill already includes VAT, and the corresponding tax shall not be charged again in the VAT on the bill of quantities.
- Renaming of the HSE provisions (Clause 3.2.5): the “statutory safety provisions” in the bill of preliminaries shall be priced in accordance with the relevant provisions of the state and provincial or industry authorities; they “are a non-competitive item, and their pricing shall comply with the relevant provisions of the state and provincial or industry authorities” — the “non-competitive” character is expressly retained, but the verb is softened from “must ... shall not be treated as competitive costs” to “is a non-competitive item”; the name changes from “mandatory health, safety and environmental (HSE) provisions” to “statutory safety provisions”, converging with the railway quota system item “statutory work safety levy (earmarked funds)” (TB 10801-2024, Clause 3.11.11).
III. Timing: MOHURD's December 2024 announcement approved GB/T 50500-2024 as a national standard, effective from 1 September 2025, with the former national standard GB 50500-2013 repealed at the same time.
Applicable Boundaries
Applies to the BOQ pricing system for building works and general installation works. Highways (JTG 3830-2018: the rate is applied to the cost of works excluding the safety cost itself, not less than 1.5%) and railways (TB 10811-2024: 3.0% of the cost of works) follow different sector rules, so the sector standard must be confirmed first. GB/T 50500-2024 is a recommended standard, and where the contract expressly provides otherwise the contract prevails; although statutory levies and fees are no longer listed separately, social insurance, housing fund and similar costs are still estimated by the tenderer and spread into labour costs and overheads percentage rates, so the actual cost burden is not removed. “Non-competitive” binds only statutory items such as the safety cost and statutory levies and fees and taxes; ordinary preliminaries (night work, secondary handling) remain open to competitive pricing.
Further Reading
- GB 50500-2013 Clauses 3.1.5 and 3.1.6 (the original mandatory provisions); Jianban [2005] No. 89, Provisions on the Administration of Safety Protection and HSE Construction Preliminary Costs for Building Works and Their Use.
- GB/T 50500-2024: Clause 3.1.2 (four-part bill structure), Clause 3.2.5 (non-competitive statutory safety provisions), Clause 3.2.11 (VAT base), Clause 2.0.9 (all-in unit rate term), Clause 3.1.6 (fully inclusive price excluding VAT); preliminaries pricing and adjustment in 2.0.10/2.0.11, 3.2.1, 7.3.1 and Section 8.9.
- MOHURD approval announcement (2024 edition effective 2025-09-01; 2013 edition repealed): https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2024/art_6186304e164c4c4982904f8734983235.html
- Companion measurement standards GB/T 50854 to 50862-2024 issued and implemented in step — see the announcement page on the MOHURD website.
Keywords
- pricing on a bill of quantities basis
- GB/T 50500-2024
- GB 50500-2013
- mandatory provisions of codes
- statutory levies and fees
- taxes and duties (VAT under the current standard)
- value added tax (VAT)
- mandatory health, safety and environmental (HSE) provisions
- statutory work safety levy (earmarked funds)
- non-competitive (statutory fees not subject to competition)