GB/T 50500-2024 Appendix E pricing cost summary: Table E.1.1 summary hierarchy (project → single project → unit work) and aggregation rules for billed items, preliminary items, other charges and VAT

GB/T 50500-2024 Appendix E contains a single general summary table — Table E.1.1 "Project summary table" — using three-level numbering (1 → 1.1 → 1.1.1) to express the project → single project → unit work hierarchy; Note 2: "This table is preferably used for the summary calculation of works where the contract subject is the object of preparation of the bill of quantities; works where a single project or unit work is the object of preparation of the bill of quantities may also be summarised using this table." Aggregation rules: billed (BOQ) item costs (the only level expanded down to unit-work detail) roll up level by level; preliminary items (with 2.1 safety-production preliminary items listed separately) and other charges (broken out into provisional sums / provisional sum for nominated specialist subcontract works / dayworks / main contractor's attendance and coordination provisions / other items agreed in the contract) are summarised at whole-project level; VAT is listed separately and its calculation base excludes the provisional sum for nominated specialist subcontract works (Note 1); total = 1+2+3+4. All-in unit rates are fully inclusive prices excluding VAT (Clause 3.1.6, term 2.0.9); statutory levies and fees are no longer listed separately in the 2024 edition, having been merged into management fee; settlement follows Table E.6.1, with amounts adjusting for errors and omissions in the BOQ entered respectively under "contract price adjustment amount" of billed items and preliminary items.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 App. E(Table E.1.1/E.5.1/E.6.1)
  • GB/T 50500-2024 第3.1.6条
  • GB/T 50500-2024 第2.0.9条术语 综合单价
  • GB 50500-2013 建设工程工程量清单计价规范(旧版对比)

Topic Positioning

The summary hierarchy and cost aggregation rules of Appendix E "Pricing cost summary" of GB/T 50500-2024 (China national pricing standard for BOQ): how project → single project → unit work roll up level by level in Table E.1.1, how billed (BOQ) items, preliminary items, other charges and VAT are aggregated, and the 2024 change whereby statutory levies and fees are no longer listed separately.

Core Conclusions

  1. Summary table structure: The 2024 edition of Appendix E contains only one general summary table — Table E.1.1 "Project summary table" — expressing the project → single project → unit work hierarchy through three-level numbering (1 → 1.1 → 1.1.1); there are no separate unit-work or single-project cost summary tables. Note 2 reads: "This table is preferably used for the summary calculation of works where the contract subject is the object of preparation of the bill of quantities; works where a single project or unit work is the object of preparation of the bill of quantities may also be summarised using this table."
  2. Aggregation rows of Table E.1.1: ① billed (BOQ) items — the only level expanded down to unit-work detail (level 2 being single projects 1.1/1.2, level 3 being unit works 1.1.1/1.1.2 …), rolling up level by level to the project total; ② preliminary items — summarised at whole-project level, with safety-production preliminary items (2.1, non-competitive) listed separately under "of which"; ③ other charges — summarised as a whole, with provisional sums, provisional sum for nominated specialist subcontract works, dayworks, main contractor's attendance and coordination provisions and other items agreed in the contract broken out under "of which"; ④ VAT — listed separately at whole-project level; total = 1+2+3+4.
  3. All-in unit rate basis (which determines the aggregation): Clause 3.1.6 reads: "The all-in unit rate and total price of billed items in the bill of quantities shall be fully inclusive prices excluding VAT, comprising labour cost, material cost, plant and small tools cost, management fee, profit, etc. … the taxes and duties of billed items shall be entered under VAT"; term 2.0.9 reads: "VAT is a price-exclusive tax; the all-in unit rate excludes VAT." There is no statutory levies and fees element in the all-in unit rate — in the 2024 edition statutory levies and fees (social insurance, housing provident fund, etc.) have been merged into management fee and are no longer listed separately, and E.1.1 has no row for them; this is the biggest difference in basis from the 2013 edition.
  4. VAT: listed separately in accordance with Table E.5.1 "VAT pricing table". Note 1 to Table E.1.1 reads: "The provisional sum for nominated specialist subcontract works is a tax-inclusive price and shall not be included in the calculation base for VAT"; Clause 3.1.6 is to the same effect: "The provisional sum for nominated specialist subcontract works in the bill of provisional sums and other charges shall be a provisional price inclusive of VAT, and the corresponding tax shall not be levied again in the VAT of the bill of quantities."
  5. Settlement stage: Table E.6.1 "Completion (interim) settlement summary table" is likewise summarised on this hierarchy; Note 2 reads: "Amounts of adjustment arising from errors and omissions in the BOQ shall be entered respectively under the 'contract price adjustment amount' of the corresponding billed items and preliminary items"; Note 3 mirrors Note 2 to E.1.1 (where a single project or unit work is the object of preparation, this table may be referred to).

Applicable Boundaries

  • Table E.1.1 applies to summaries where the contract subject (the whole project) is the object of preparation of the bill of quantities; where a single project or unit work is the object of preparation, the table "may" (Note 2 to E.1.1) / "may be referred to" (Note 3 to E.6.1) for the summary calculation.
  • "Statutory levies and fees not listed separately" is the 2024 national standard basis; where local companion quota norms, sector standards (e.g. highway fully inclusive unit rates) or the contract provide otherwise, the sector rules and the contract prevail.
  • E.1.1 is a summary table and does not replace the detail schedules — billed item pricing schedule, all-in unit rate analysis schedule, preliminary item pricing schedule, bill of provisional sums and other charges pricing schedule, VAT pricing schedule, etc.; the summary level only aggregates, while the amounts originate in the detail schedules.
  • The provisional sum for nominated specialist subcontract works is a tax-inclusive price and is excluded from the VAT calculation base; this differs from provisional sums for specified materials/plant and equipment (where the pre-tax difference is charged to VAT separately) — do not conflate the two.
  • GB/T 50500-2024 is a recommended national standard; its binding force normally arises as a contractual obligation through citation in the tender documents and the contract.

Further Reading

  • GB/T 50500-2024, Appendix E "Pricing cost summary": Table E.1.1 "Project summary table", Table E.5.1 "VAT pricing table", Table E.6.1 "Completion (interim) settlement summary table"; companion detail schedules: BOQ pricing schedule, all-in unit rate analysis schedule, preliminary item pricing schedule (unit rate / percentage rate / lump-sum pricing), bill of provisional sums and other charges pricing schedule.
  • Main text Clause 3.1.6 (all-in unit rate as fully inclusive price excluding VAT; provisional sum for nominated specialist subcontract works tax-inclusive and not charged to VAT again), term 2.0.9 "all-in unit rate" (VAT as a price-exclusive tax).
  • Comparison with the previous edition: GB 50500-2013 listed five cost elements separately (billed items / preliminary items / other charges / statutory levies and fees / taxes and duties); in the 2024 edition statutory levies and fees are merged into management fee, leaving four categories plus VAT; for the differences in basis between editions see the related cards.