Distinguishing the basis of the all-in unit rate from that of the fully loaded all-in rate (incl. taxes and specified on-costs): composition differences, applicable scenarios, and risks of mixed use

Narrow-sense all-in unit rate = labour cost + material cost (including engineering equipment) + plant and small tools cost + overheads (company and site) + profit + risk cost within the agreed scope and risk band (no-adjustment tolerance, e.g. ±5%), excluding statutory levies and fees and value added tax (VAT) (GB/T 50500-2024 Clause 2.0.9, VAT being a price-exclusive tax listed separately); the fully loaded all-in rate (incl. taxes and specified on-costs) = the above + statutory levies and fees + taxes and duties (VAT under the current standard), tax-inclusive (GB/T 51095-2015 and other consultancy/local bases). Note that the 2024 edition's "fully inclusive price excluding VAT" means all costs are included but VAT is still excluded — different from the industry-conventional fully loaded all-in rate (incl. taxes and specified on-costs). A single project must adopt a consistent basis; mixing the two leads to total-price miscalculation.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 51095-2015 建设工程造价咨询规范
  • GB/T 50875-2013 工程造价术语标准
  • SJG 111.2-2022 城市地下综合管廊工程消耗量标准
  • DB14/T 1319-2021 公路工程标准工程量清单及计量规范

Topic Positioning

Distinguishes two easily confused terms, "all-in unit rate" and "fully loaded all-in rate (incl. taxes and specified on-costs)": composition differences, code origins, applicable scenarios, and risks of mixed use, to support a consistent pricing basis.

Core Conclusions

Narrow-sense all-in unit rate (GB/T 50500-2024 Clause 2.0.9) = labour cost + material cost (including engineering equipment) + plant and small tools cost + overheads (company and site) + profit + risk cost within the agreed scope and risk band (no-adjustment tolerance, e.g. ±5%); value added tax (VAT) is a price-exclusive tax, excluded and listed separately under the VAT item (Clauses 3.1.6, 3.2.11), and the 2024 edition has abolished the separate item for statutory levies and fees. Fully loaded all-in rate (incl. taxes and specified on-costs) = the above + statutory levies and fees + taxes and duties (VAT under the current standard), tax-inclusive (GB/T 51095-2015 Clauses 5.3.8, 6.2.3; Shenzhen, Shanxi highway, and other local systems carry additional items). Note: the 2024 edition's "fully inclusive price excluding VAT" means all costs included but VAT still excluded, which differs from the industry-conventional fully loaded all-in rate (incl. taxes and specified on-costs).

Applicable Boundaries

Building and general installation BOQ-based pricing applies; highway, Shenzhen, Hubei, and other local/industry bases may already include statutory levies and fees and taxes and duties or more cost items — confirm the industry standard and version before citing (the 2024 and 2013 bases differ). Tendering and BOQ settlement mostly use the narrow-sense basis (tax listed separately); estimates, preliminary estimates, budget compilation, and some local systems use the fully loaded all-in basis; mixing the two bases in one project is a frequent cause of total-price miscalculation — the tender documents/contract agreement govern.

Further Reading

GB/T 50500-2024 Clauses 2.0.9, 3.1.6, 3.2.10, 3.2.11; GB/T 51095-2015 Clauses 5.3.8, 6.2.3; GB/T 50875-2013 Clause 2.2.58; local bases: Shenzhen SJG 111.2-2022 additionally includes mandatory health, safety and environmental (HSE) provisions; Shanxi highway DB14/T 1319-2021 additionally includes permanent equipment procurement cost and preliminaries; Hubei DB42/T 823-2021 preferably includes statutory levies and fees and taxes and duties.