Definitions, cost composition and applicable conventions of the direct-cost rate, the all-in unit rate and the fully loaded all-in rate compared (Order No. 107 of the Ministry of Construction, GB/T 50500-2024, GB/T 51095-2015, etc.)
The three rate conventions widen in scope in turn: the direct-cost rate (labour plus materials plus plant only, with on-costs, profit and taxes computed separately) is contained in the all-in unit rate (labour plus materials plus plant and small tools plus overheads plus profit plus risk fees within the agreed band; GB/T 50500-2024 clause 2.0.9 expressly excludes VAT, which is carried separately), which is contained in the fully loaded all-in rate (further including statutory levies and taxes, tax-inclusive; GB/T 51095-2015 clause 6.2.3 requires its use for the tender price ceiling and tenders). Note that the "all-in rate method" defined in Order No. 107 of the Ministry of Construction is a fully loaded unit rate - the same name as, but different content from, the "all-in unit rate" of current BOQ pricing; the "all-in rate" of highway works is likewise a wide convention including statutory levies and taxes (and additionally equipment procurement cost and preliminaries).
Applicable Codes
- 《建筑工程施工发包与承包计价管理办法》(建设部令第107号)第五条
- 《建筑工程施工发包与承包计价管理办法》(住房和城乡建设部令第16号,2014年施行;建设部令第107号的现行替代版本)
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.9条、第3.1.6条、第3.1.7条
- GB/T 50875-2013 · Standard glossary of project costs 第2.2.58条
- GB/T 51095-2015 · Code for construction cost consultation 第6.2.3条
- DB42/T 823—2021 · Specification for Quality Control of Construction Cost Consulting (Hubei) 第6.3.8条
- DB14/T 1319—2021 · Specification for Standard Bills of Quantities and Measurement of Highway Works (Shanxi) 第3.4、3.5节
Topic Positioning
Compares the three rate conventions of construction pricing - the direct-cost rate, the all-in unit rate and the fully loaded all-in rate - in terms of normative source, cost composition boundary and applicable scenario, for quick judgement of "which costs sit inside a unit rate" in tendering, construction-drawing budgets and settlements, and to prevent the mixing of conventions across systems and standard versions.
Core Conclusions
1. Direct-cost rate (labour-material-machinery rate)
Article 5 of the Measures for the Administration of Pricing of Construction Contracting (Order No. 107 of the Ministry of Construction): "The construction-drawing budget, tender benchmark price and tender are composed of cost (direct cost and on-costs), profit and taxes. Pricing may adopt the following methods: (1) the labour-material-machinery rate method - the unit rate of the quantity of a divisional work is the direct cost. The direct cost is determined from the consumption of labour, materials and machinery and their corresponding prices. On-costs, profit and taxes are computed separately under the relevant provisions. (2) The all-in rate method - the unit rate of the quantity of a divisional work is a fully loaded unit rate. The fully loaded unit rate comprehensively computes the direct cost, on-costs, profit and taxes incurred in completing the divisional work."
Composition = labour + materials + plant (direct cost only); on-costs, profit and taxes are computed separately outside the rate. Note: the "all-in rate method" defined in Order No. 107 is the fully loaded unit rate (direct cost, on-costs, profit, taxes) - the same name as, but different content from, the "all-in unit rate" of current BOQ pricing.
2. All-in unit rate (current BOQ convention)
GB/T 50500-2024 Standard for Pricing of Works on a Bill of Quantities Basis, clause 2.0.9: "The cost required to complete one unit quantity of a billed item, comprehensively considering influencing factors such as technical standards, construction period, construction sequence, construction conditions, geography and climate, as well as risks within the agreed scope and band. The all-in unit rate of a billed item comprises labour, materials, plant and small tools, overheads, profit and risk fees within a defined band, and does not include VAT."
Clause 3.1.6: "The all-in unit rate and price of billed items of the bill of quantities shall be a fully inclusive price excluding VAT, composed of labour, materials, plant and small tools, overheads, profit and the like, including risk fees within the agreed or reasonable scope of the billed item and the cost of indispensable auxiliary work; the tax of billed items shall be entered under VAT, provided that the provisional sum for nominated specialist works in the other charges bill already includes VAT, and its corresponding tax must not be charged again under the VAT of the bill of quantities."
GB/T 50875-2013 Standard for Construction Cost Terminology, clause 2.2.58 (same convention, including permanent equipment): "The labour, material and permanent equipment cost, plant cost, overheads, profit, and risk fees within a defined band required to complete one specified billed item."
Composition = labour + materials (including permanent equipment) + plant and small tools + overheads + profit + defined-band risk fees; excludes VAT (the tax is carried on a separate "VAT" line); statutory levies are not listed among the components.
3. Fully loaded all-in rate
GB/T 51095-2015 Code for Construction Cost Consultation, clause 6.2.3: "The quantities of the tender price ceiling and the tender shall be determined from the bill of quantities issued with the tender documents; the unit rates of the tender price ceiling and the tender shall be all-in rates, and the all-in rate shall include labour, materials, plant, overheads, profit, statutory levies and taxes." The commentary: "To implement fully loaded unit pricing ... this clause emphasises that the unit rates of the tender price ceiling and the tender shall be all-in rates including labour, materials, plant, overheads, profit, statutory levies and taxes, so that the unit rates of the feasibility estimate, the design estimate and the budget are consistent in composition."
Local conventions agree, e.g. DB42/T 823-2021 Code for Quality Control of Construction Cost Consultation, clause 6.3.8: "The all-in unit rate of each item should preferably be a fully loaded all-in rate, including labour, materials, plant, overheads, profit, statutory levies and taxes." (Its commentary notes that, because the national BOQ standard and consultation code are not aligned with the provincial quota system, the clause uses "should preferably" rather than "shall".)
Composition = labour + materials + plant + overheads + profit + statutory levies + taxes (tax-inclusive).
4. Comparison points and applicable scenarios
- Widening order of cost scope: direct-cost rate < all-in unit rate (BOQ convention) < fully loaded all-in rate.
- Identification rule: whether overheads and profit are included separates the direct-cost rate from the all-in unit rate; whether statutory levies and taxes (VAT) are included separates the all-in unit rate from the fully loaded all-in rate.
- Supporting requirement: the all-in rate build-up schedule shall state the computation method of the cost composition of the all-in unit rate of each billed item, and its all-in rates and item prices must agree exactly with the corresponding rates and prices in the bill of quantities (GB/T 50500-2024 clause 3.1.7).
- Application: works priced on a BOQ basis (tendering, interim payments, final account) use the all-in unit rate; the tender price ceiling and the tender use the fully loaded all-in rate (including statutory levies and taxes) per GB/T 51095-2015; the labour-material-machinery rate method belongs to traditional quota-based pricing, used for construction-drawing budgets and analysis of quota base prices.
- Sector difference: the "all-in rate" of highway works is itself a wide, fully loaded convention - DB14/T 1319-2021 Standard Bill of Quantities and Measurement for Highway Works defines it as "the labour, materials, construction plant, equipment procurement cost, preliminaries, overheads, statutory levies, profit, taxes and risk fees within the agreed contract band required to complete one specified billed item of highway works" - wider than the building BOQ convention by equipment procurement cost, preliminaries, statutory levies and taxes.
Applicability Boundaries
- Version boundary: the 2024 and 2013 editions of GB/T 50500 differ in the composition of the all-in unit rate (notably the treatment of statutory levies and taxes); conventions of different versions must not be mixed; the edition must be stated when citing clauses.
- Same name, different content: "all-in rate method = fully loaded unit rate" under Order No. 107 of the Ministry of Construction, "all-in unit rate (VAT excluded)" under the current BOQ standard, and "fully loaded all-in rate (including statutory levies and taxes)" under the consultation code are concepts of different contexts and must not be interchanged.
- Currency note: Order No. 107 has been superseded by Order No. 16 of the Ministry of Housing and Urban-Rural Development, Measures for the Administration of Pricing of Construction Contracting (in force from 2014); check the current version before citing articles of Order No. 107.
- Sector boundary: the general conventions for building and municipal works differ from those of highway, water conservancy and other sectors (e.g. the highway all-in rate includes equipment procurement cost, preliminaries, statutory levies and taxes); check the sector standard before cross-sector application.
- For a specific project, the convention agreed in the contract prevails; the wording of clauses in this card follows the cited editions.
Further Reading
- All-in unit rate terminology and the pre-tax convention: GB/T 50500-2024 Standard for Pricing of Works on a Bill of Quantities Basis, clauses 2.0.9 (terminology), 3.1.6 (fully inclusive price excluding VAT, VAT carried separately), 3.1.7 (all-in rate build-up schedule).
- Fully loaded convention and commentary: GB/T 51095-2015 Code for Construction Cost Consultation, clause 6.2.3.
- Terminology basis: GB/T 50875-2013 Standard for Construction Cost Terminology, clause 2.2.58.
- Source of the labour-material-machinery rate method and all-in rate method (historical articles): Order No. 107 of the Ministry of Construction, Measures for the Administration of Pricing of Construction Contracting, Article 5; the current version is Order No. 16 of the Ministry of Housing and Urban-Rural Development - check the current text before citing.
- Local and sector convention differences: DB42/T 823-2021 clause 6.3.8 (commentary on "should preferably" for the fully loaded all-in rate); DB14/T 1319-2021 sections 3.4 and 3.5 (wide-convention all-in rate of highway works).