Three bases for the composition of the construction price: cost elements, BOQ-based pricing, and final-account listing
The construction price (cost of works (construction and installation)) has three composition bases: (1) by cost elements (GB/T 50875-2013 Clause 2.2.10) = labour cost + material cost + construction machinery usage cost + management fee + profit + statutory levies and fees + taxes and duties (VAT under the current standard); (2) by BOQ-based pricing (GB/T 50500-2024) = divisional/sub-divisional works cost + preliminaries + other-item cost + VAT — the 2024 edition abolishes the separate statutory-levies item, the all-in unit rate being a fully inclusive price excluding VAT, and the VAT base deducting provisional sums for nominated specialist subcontract works; (3) by final-account listing (Clause 10.3.2) — 13 items. Mind the differences between the 2013 and 2024 bases when comparing.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB/T 50875-2013 工程造价术语标准
Topic Positioning
An overview of the composition bases of the construction price (cost of works (construction and installation)): fix the basis first, then answer "which costs the price covers".
Core Conclusions
(1) Cost elements (GB/T 50875-2013 Clause 2.2.10): cost of works = labour cost + material cost + construction machinery usage cost + management fee + profit + statutory levies and fees + taxes and duties (VAT under the current standard). (2) BOQ-based pricing (GB/T 50500-2024): = divisional/sub-divisional works cost + preliminaries + other-item cost + VAT. The all-in unit rate is a fully inclusive price excluding VAT (covering labour/material/machinery, management fee, profit, and risk cost, 3.1.6); VAT is charged on the total of the other three items less provisional sums for nominated specialist subcontract works (3.2.11); other-item cost = provisional sums + provisional sums for nominated specialist subcontract works + dayworks + main contractor's attendance and coordination provisions. (3) Final-account listing (10.3.2, 13 items): contract BOQ total; BOQ errors / omissions; provisional sums; provisional sums for specified materials / nominated works; main contractor's attendance and coordination provisions; dayworks; changes in costs; changes in law and policy; variations; additional works; claims; penalties; other amounts. The 2024 edition abolishes the separate statutory-levies item — social insurance and the housing fund are absorbed into labour unit rates and the management-fee percentage rate.
Applicable Boundaries
The three bases serve element decomposition, tendering pricing, and final-account preparation — never mix them; building generic BOQs use "incomplete-cost" all-in unit rates, while highways and other industries may use fully inclusive bases — confirm the industry standard; payment timing has its own basis (advance payment -> progress payment -> final-account payment, GB/T 50875-2013 Section 3.4); mind edition differences against 2013.
Further Reading
See GB/T 50500-2024 Clauses 3.1.6, 3.2.11, 10.3.2; GB/T 50875-2013 Clauses 2.2.10, 2.2.50, 2.2.51, 2.2.57, 2.2.58.