Composition of the duty-paid arrival cost of imported equipment (its original price) and the three-step tax chain: customs duty, then consumption tax (an inclusive tax whose base must first be grossed up), then import-stage VAT - the formula chain, variable definitions and how each charging base is fixed

Per GB/T 50875-2013 clauses 2.2.5, 2.2.7 and 2.2.8, the duty-paid arrival cost of imported equipment = CIF (= FOB + international freight + international transport insurance) + import-related charges (bank financial charges, foreign-trade agent commission, import duty, consumption tax, import-stage VAT and vehicle purchase tax for imported vehicles). The order must be duty, then consumption tax, then VAT: duty = CIF x duty rate; consumption tax = (duty-paying value + duty) / (1 - consumption tax rate) x consumption tax rate (an inclusive tax - the tax-inclusive base must first be restored); import-stage VAT = (duty-paying value + duty + consumption tax) x VAT rate (VAT Regulations Article 14: composite taxable value = duty-paying value + duty + consumption tax). The bases must not be crossed: bank financial charges on FOB, foreign-trade commission on CIF.

Applicable Codes

  • GB/T 50875-2013 · Standard glossary of project costs 第 2.2.4、2.2.5、2.2.7、2.2.8、2.2.46 条
  • 《中华人民共和国增值税暂行条例》(国务院令第 666 号,2016 修订)第十四条
  • 《中华人民共和国消费税暂行条例》(国务院令第 135 号)第九条
  • 《中华人民共和国增值税法》(2024 年通过,自 2026 年 1 月 1 日起施行)
  • JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第 3.1.3 条

Positioning

The cost components of the duty-paid arrival cost of imported equipment (its original price), the computation order and formula chain of the three taxes (duty, then consumption tax, then import-stage VAT), and how each tax and charge base is fixed. For equipment procurement budgets, imported-equipment tender review and estimate auditing.

Core conclusions

1. Composition of the arrival cost (GB/T 50875-2013 wording)

  • Clause 2.2.5: "The equipment original price divides into domestically purchased and foreign-purchased. The foreign-purchased original price is the duty-paid arrival cost of imported equipment, normally consisting of the CIF value and the import-related charges."
  • Clause 2.2.7: "CIF consists of the FOB value, the international freight and the international transport insurance. FOB is the free-on-board price at the port of shipment... FOB includes the ex-works price of the equipment and the domestic freight and handling in the exporting country."
  • Clause 2.2.8 (import-related charges): "Bank financial charges, foreign-trade agent commission, import duty, consumption tax, import-stage VAT and, for imported vehicles, vehicle purchase tax incurred in import formalities and attributable to the equipment original price."

So the full chain: arrival cost = goods value (FOB) + international freight + international transport insurance (together CIF) + bank financial charges + foreign-trade commission + duty + consumption tax + import-stage VAT (+ vehicle purchase tax for imported vehicles).

  • Clause 2.2.4: equipment procurement cost "includes the original price and freight and handling" - the arrival cost is only the original price; domestic freight must be added for the procurement cost. Office and living furniture is not in equipment procurement cost but in preparations for production under project costs other than the works.

2. Formulas and statutory text of the three taxes

  1. Duty = CIF x duty rate. The customs duty-paying value (as appraised by customs) is normally the CIF value; duty is the only tax computable from known inputs and must come first.
  2. Consumption tax = (duty-paying value + duty) / (1 - consumption tax rate) x consumption tax rate. Consumption Tax Regulations (State Council Decree No. 135), Article 9: "Imported taxable consumer goods taxed ad valorem are assessed on the composite taxable price: composite price = (duty-paying value + duty) / (1 - consumption tax rate)." Consumption tax is price-inclusive - the tax itself joins the next tax base - so it must not be computed as (CIF + duty) x rate; the division by (1 - rate) first restores the tax-exclusive base to the tax-inclusive composite price.
  3. Import-stage VAT = (duty-paying value + duty + consumption tax) x VAT rate. VAT Regulations (State Council Decree No. 666, 2016 revision), Article 14: "Taxpayers importing goods assess tax on the composite taxable price at the rate under Article 2: composite taxable price = duty-paying value + duty + consumption tax; tax payable = composite taxable price x rate." VAT is price-exclusive - the composite price already holds consumption tax but not VAT itself - so one multiplication suffices, no second grossing-up.

3. Why the order cannot be inverted

Duty depends only on CIF and its rate; the consumption tax base contains duty; the VAT base contains duty and consumption tax - three nested layers. Mis-computing consumption tax as (CIF + duty) x rate understates both the consumption tax and the subsequent VAT composite price (the missing consumption tax becomes a hole in the VAT base), and the error propagates down the chain.

4. The two charge bases must not be crossed

  • Bank financial charges are based on FOB;
  • Foreign-trade agent commission is based on CIF.

The bases differ (one free-on-board, one landed); crossing them systematically over- or under-states the charges. Moreover, bank charges and trade commission are not part of the VAT composite taxable price (Article 14 lists only "duty-paying value + duty + consumption tax") and must not be treated as VAT base.

Applicable boundaries

  • Consumption tax applies only to taxable consumer goods: ordinary machinery or production lines bear none, and the VAT composite price degenerates to "duty-paying value + duty".
  • The grossing-up formula is ad valorem only: quantity-based or composite assessment follows its own rules - do not apply the divide-by-(1 - rate) form.
  • The duty-paying value is fixed by customs: normally CIF; where the transaction price excludes freight and insurance before unloading at the place of entry, they are added per the rules before taxing.
  • Rates and bases of bank charges and trade commission follow agency agreements, bank and trade-authority rules and industry practice: GB/T 50875-2013 only classifies them as import-related charges; check the project's pricing bases before use.
  • Vehicle purchase tax applies to imported vehicles only, under its own rules, and does not join the VAT composite price.
  • Whether an item qualifies as a fixed asset, and the equipment/material divide, follow the industry criteria and decide whether it enters equipment procurement cost.
  • Timeliness: the VAT clauses cited are the 2016-revised Regulations, Article 14; VAT is now governed by the PRC VAT Law (passed 2024-12-25, effective 2026-01-01) - verify article numbers and rates under the new law; the composite-price logic (duty-paying value + duty + consumption tax) is unchanged.

Further reading

  • GB/T 50875-2013 Construction Cost Terminology Standard, clauses 2.2.4 (procurement cost), 2.2.5 (original price / arrival cost), 2.2.7 (CIF and FOB), 2.2.8 (import-related charges), 2.2.46 (interest during construction capitalised).
  • VAT Regulations (Decree No. 666, 2016 revision) Article 14 and Article 2 rates.
  • Consumption Tax Regulations (Decree No. 135) Article 9.
  • PRC VAT Law (passed 2024, effective 2026-01-01) - current import-stage provisions.
  • Industry comparisons: JTG 3830-2018 clause 3.1.3 (procurement cost = original price + freight + transport insurance + purchasing and custody).