Highway estimate/budget equipment purchase costs: four components — original price, freight, transport insurance, procurement and storage (JTG 3830-2018 clause 3.1.3)
Per clause 3.1.3 of JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects": equipment purchase costs = equipment original price + freight + transport insurance + procurement-and-storage fee, taxes computed per compilation-period authority provisions; equipment enters at budget price with a planned purchase list (spec, model, quantity); installation costs of equipment needing installation are not part of this item and follow the construction-installation cost provisions separately; the equipment/material division follows Appendix C.
Applicable Codes
- JTG 3830-2018 公路工程建设项目概算预算编制办法(第3.1.3条、第3.1.1条、第3.1.2条、App. C)
Topic Positioning
This card covers the statutory cost composition and listing rules for "permanent equipment procurement cost" in highway works estimate and budget compilation under clause 3.1.3 of JTG 3830-2018 "Administrative Compilation Rules for Estimates and Budgets of Highway Construction Projects"; it elaborates one of the 8 components of the cost of works (clause 3.1.1).
Core Conclusions
Key points of clause 3.1.3: (1) Definition and scope: permanent equipment procurement cost means "the cost of equipment that meets fixed-asset standards and is purchased to meet the initial operation and management needs of the highway, plus equipment below those standards that the design expressly lists in the equipment schedule" — including ferry equipment; tunnel lighting, fire-protection and ventilation power equipment; and highway tolling, monitoring, communications, road-network operation monitoring, power supply and distribution, and lighting equipment. (2) Four cost components (verbatim): "Permanent equipment procurement cost comprises the equipment original price, freight and handling charges, transport insurance, and purchasing and custody charges; all taxes and duties are calculated per the provisions of the relevant authorities at the time of compilation." (3) Listing rules: the permanent equipment procurement cost shall set out the planned procurement schedule (equipment specifications, models and quantities) and be included at the equipment price for estimating; for equipment requiring installation, the installation cost is calculated separately under the provisions for the cost of works; the division between equipment and materials follows Appendix C of these Rules.
Applicable Boundaries
- Applies only within the JTG 3830-2018 highway works estimate and budget system (including the listing of permanent equipment procurement cost); permanent equipment procurement cost is one of the 8 components of the cost of works (clause 3.1.1: direct costs + permanent equipment procurement cost + preliminaries + overheads (company and site) + statutory charges + profit + taxes + special items), and when computing fees only 40% of the permanent equipment procurement cost within the norm-based cost of works is counted (see clause 3.1.1).
- For "equipment requiring installation", the installation cost is not part of the permanent equipment procurement cost but is calculated separately under the cost-of-works provisions — a common pitfall.
- Costs classified as "materials" under Appendix C do not fall under this item; their norm-based material price for estimating follows clause 3.1.2 (including off-site transport wastage and the purchasing and custody charge rate) — do not conflate with permanent equipment procurement cost.
- The railway system (TB 10801-2024) applies a different basis for permanent equipment procurement cost (equipment cost plus equipment freight and handling charges only — two components); the two must not be mixed.
- All taxes and duties (such as value added tax (VAT)) are calculated per the provisions of the relevant authorities at the time of compilation and are not capped by the four components of this item.
Further Reading
- Clause sources: JTG 3830-2018 clause 3.1.3 (definition, four cost components, installation cost calculated separately, Appendix C equipment/material division), clause 3.1.1 (the 8-component composition of the cost of works and the separation of net price and VAT), clause 3.1.2 (norm-based material price for estimating, including the purchasing and custody charge rate).
- For comparison: the railway TB 10801-2024 basis for permanent equipment procurement cost; the equivalent provisions of JTG 3820-2018 for the feasibility-stage cost estimate.