Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Highway JTG 3830-2018 production preparation fee (clause 3.3.7) charging standards: production personnel training fee = design staffing x 3,000 yuan/person, plus traffic-maintenance management fee / works insurance fee (3.3.8-3.3.10)

Per JTG 3830-2018 clause 3.3.7, the production personnel training fee is "computed at design staffing and 3,000 yuan/person", i.e. = design staffing x 3,000 yuan/person; this sub-item has no rebuild/expansion discount (the "rebuild (expansion) projects at 70% of the tabulated fee" after table 3.3.7 applies only to office and living furniture purchase). The same clause's tooling purchase fee and emergency traffic-keeping equipment purchase fee are computed as per equipment purchase cost (clause 3.1.3); clause 3.3.9 works insurance fee = construction-installation cost (excluding equipment) x 0.4%.

Applicable Codes

  • JTG 3830-2018 公路工程建设项目概算预算编制办法 第3.3.7~3.3.10条、Table 3.3.7、App. G

Topic Positioning

The calculation standards for the production preparation fee (clause 3.3.7) within project costs other than the works under the 2018 highway quota system (JTG 3830-2018, Administrative Compilation Rules for Estimates and Budgets of Highway Works Construction Projects) — the core conclusion being that the production personnel training fee is calculated at the design manning level and 3,000 yuan/person; it also covers the co-located tooling procurement cost, office and living furniture procurement cost and emergency traffic-keeping equipment procurement cost, together with the listing rules for 3.3.8 works traffic-keeping management fee, 3.3.9 works insurance fee and 3.3.10 other related costs.

Core Conclusions

Per clause 3.3.7 of JTG 3830-2018 (project costs other than the works — production preparation fee), the section contains four costs:

  1. Production personnel training fee: the cost of training production and management personnel of the operating department before completion acceptance and handover so as to ensure normal operation of production, including trainees' wages, wage-related allowances, staff welfare, travel and transport, labour protection, and training and teaching practice costs. This cost is calculated at the design manning level and 3,000 yuan/person, i.e. production personnel training fee = design manning headcount × 3,000 yuan/person (design manning taken as the operating headcount fixed by the design documents).

  2. Tooling procurement cost: the cost of the first set of equipment, instruments, meters, jigs, dies and appliances below the fixed-asset threshold that must be procured for initial normal production, use and management; equipment, tools and spare parts constituting fixed assets, and special tools and spare parts already included in the equipment cost, are excluded from this item. The design organization (design institute) lists a planned procurement schedule (specifications, models, quantities); calculated on the same basis as the permanent equipment procurement cost.

  3. Office and living furniture procurement cost: the cost of furniture and appliances for offices and living (administration and production department offices, meeting rooms, records and archive rooms, reading rooms, dormitories and welfare facilities) procured for initial normal production, use and management, calculated per Table 3.3.7. Note to Table 3.3.7: for reconstruction (expansion) projects, 70% of the tabulated cost — this 70% discount applies only to the office and living furniture procurement cost, not to the production personnel training fee (the training fee has no reconstruction/expansion discount and is listed at the full 3,000 yuan/person).

  4. Emergency traffic-keeping equipment procurement cost: the cost of fixed-asset equipment procured by new and reconstruction (expansion) projects to meet initial normal operation, for emergency repair and traffic-keeping and emergency response; the design organization lists a planned procurement schedule, calculated on the same basis as the permanent equipment procurement cost.

Other costs in the same section: 3.3.8 works traffic-keeping management fee — for construction projects that require traffic or navigation to be kept open alongside construction, the costs of traffic (road, waterway, railway) control, rail traffic and vessel guidance, and publicity such as media and public notices, and the costs of assistant traffic-control personnel, needed to ensure the operating safety of the road (railway), the navigation safety of vessels and construction safety; to be listed according to the design requirements; the calculation method for navigation safety assurance costs during construction of water-related projects is given in Appendix G of these Rules. 3.3.9 works insurance fee — including all-risks insurance for construction works (insurance for permanent works, temporary works and equipment, and materials and equipment delivered to the construction site for permanent works) and third-party liability insurance (insurance against liability for loss of or damage to property (other than the works) or death of or injury to persons (other than the employer's and contractor's employees) caused by carrying out the contract works), calculated at a rate of 0.4% on the base of the cost of works (construction and installation), excluding equipment cost. 3.3.10 other related costs — other costs related to highway construction stipulated by the competent administrative departments of the State Council and provincial people's governments, calculated per their relevant provisions.

All the above costs belong to project costs other than the works and are not included in the cost of works (construction and installation).

Applicable Boundaries

  • Applies to the compilation of estimates and budgets for highway works construction projects (JTG 3830-2018); new and reconstruction (expansion) projects alike.
  • The Table 3.3.7 rule "for reconstruction (expansion) projects, 70% of the tabulated cost" applies only to the office and living furniture procurement cost and must not be extended to the other sub-items of the same clause (the production personnel training fee is listed at the full amount).
  • 3,000 yuan/person is a highway-specific standard of JTG 3830-2018; other sectors (building, municipal, railway, etc.) and the general basis of the Methods and Parameters for Economic Evaluation of Construction Projects have different production preparation/start-up cost standards — they must not be mixed.
  • For the tooling procurement cost and the emergency traffic-keeping equipment procurement cost, "calculated on the same basis as the permanent equipment procurement cost" — they must be calculated per clause 3.1.3 (equipment ex-works price + freight and handling charges + transit insurance + purchasing and custody charges).
  • The base for the 0.4% works insurance rate is the cost of works (construction and installation), excluding equipment cost; do not include equipment cost in the base.

Further Reading

See clauses 3.3.7–3.3.10 and Table 3.3.7 of JTG 3830-2018, Administrative Compilation Rules for Estimates and Budgets of Highway Works Construction Projects; for the calculation method of navigation safety assurance costs during construction of water-related projects see Appendix G of these Rules; for the composition of the permanent equipment procurement cost see clause 3.1.3 and, for the demarcation between equipment and materials, Appendix C; for the overall composition of the cost of works (8 items) see clause 3.1.1. The evidence for this card comes from the original text of section 3.3 of these Rules.