Reading the all-in unit rate pricing schedule of the fee quota norms line by line: charging bases (labour cost / labour cost plus plant and small tools cost), the order of charging (overheads, profit, risk cost -> all-in unit rate; pre-tax project cost -> VAT -> unit works cost), and a comparison of provincial bases (Shaanxi 2025 tables 5-1/5-2/5-3; Hubei 2024) with sector bases (highway form 08; railway table 2.6.2)
The main line of the all-in unit rate pricing program: labour, materials and plant (including dynamic adjustment / price differentials) -> direct cost subtotal -> overheads and profit (base: 'labour cost plus plant and small tools cost'; some provinces use 'labour cost') x rate -> (the Hubei basis adds a separate risk-factor line) -> all-in unit rate = the sum of all items; unit works cost = element works + preliminaries + other items = pre-tax (net-of-tax) project cost, then x VAT rate and added. In the Shaanxi 2025 'Shaanxi construction works fee rules', table 5-2 (base = labour cost plus plant and small tools cost) and table 5-3 (base = labour cost) list the social security costs of construction workers separately into the all-in unit rate as labour cost x rate, and table 5-1 places VAT after 'pre-tax project cost'; in the Hubei 2024 fee quota norms, overheads / profit = (labour cost + plant and small tools cost) x rate with the risk factor alone on line 6, while Annex 4 (tender price ceiling program) still keeps an independent 'statutory levies and fees' line (a trace of the 2013 BOQ basis). Highway JTG 3830-2018 form 08: preliminaries / overheads take quota labour cost + quota plant cost (or quota direct cost) as base, statutory levies take labour cost as base, profit takes (quota direct cost + preliminaries + overheads) as base, and taxes and duties take (direct cost + preliminaries + overheads + statutory levies + profit) as base.
Applicable Codes
- 陕西省建设工程费用规则(2025版)表5-1、表5-2、表5-3
- 湖北省建筑安装工程费用定额(2024)二、计算程序 及 附件4
- JTG 3830-2018 公路工程建设项目概算预算编制办法(08表填表说明)
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第2.6节 Table 2.6.2、Table 2.6.3
- GB/T 50500-2024 建设工程工程量清单计价标准 第3.2.11条(增值税计算基础)
Scope of the Topic
Reading the 'pricing schedule' of the provincial fee quota norms and the sector compilation rules table by table: which lines sit inside the all-in unit rate, which sit at unit-works level, whether the charging base is labour cost alone or labour cost plus plant and small tools cost, and at which step of the program VAT appears.
Core Conclusions
I. The all-in unit rate calculation program (main line of the provincial fee quota norms)
Shaanxi 2025 'Shaanxi construction works fee rules', table 5-2, 'all-in unit rate pricing schedule on the base of labour cost plus plant and small tools cost', line by line: labour, materials and plant costs (labour cost A, material cost B, plant and small tools cost C) -> dynamic adjustment of labour, materials and plant (A1, B1, C1, i.e. compilation-period adjustment) -> social security costs of construction workers = A x social security rate for construction workers (listed separately into the rate) -> direct cost subtotal D = A + B + C -> overheads = (A + C) x overheads rate -> profit = (A + C) x profit rate -> all-in unit rate H = D + E + F. Table 5-3, 'all-in unit rate pricing schedule on the base of labour cost', has the same structure, but overheads = A x overheads rate and profit = A x profit rate (the base taken on labour cost alone). Key point: two charging bases coexist within one fee rule document; before applying rates you must confirm which table the works are priced on - bases must not be mixed across tables.
Hubei 'construction and installation works fee quota norms' (2024), 'II. calculation program', item 1, all-in unit rate calculation program for element works and unit-rate preliminaries: 1 labour cost, sum (labour cost); 2 material cost, sum (material cost); 3 plant and small tools cost, sum; 4 overheads = (1 + 3) x rate; 5 profit = (1 + 3) x rate; 6 risk factors (per the tender documents or as agreed); 7 all-in unit rate = 1 + 2 + 3 + 4 + 5 + 6. Differences from Shaanxi table 5-2: the risk cost is an explicit separate line, social security is not listed separately, and the base is uniformly (labour cost + plant and small tools cost).
II. Tendering-stage / unit works cost pricing program (the level at which items merge)
Shaanxi table 5-1, tendering-stage pricing schedule: 1 element works cost = sum (all-in unit rate x element works quantity), of which 1.1 including: social security costs of construction workers = sum (social security within the all-in unit rate x element works quantity) (social security enters the element cost inside the unit rate and is restored in an 'of which' line at summary level); 2 preliminaries = 2.1 specialist preliminaries (sum of all-in unit rate x specialist preliminaries quantity) + 2.2 general preliminaries (2.2.1 mandatory HSE provisions; 2.2.2 winter and rainy season construction additions; 2.2.3 night work additions; 2.2.4 secondary handling; 2.2.5 setting out and re-survey costs - each a sum of charging base x rate); 3 other items cost = 3.1 provisional sums + 3.2 provisional prices for specialist works + 3.3 dayworks, sum (all-in unit rate x quantity) + 3.4 main contractor's attendance and coordination provisions (3.4.1 custody fee for employer-supplied materials = sum of employer-supplied material cost x rate; 3.4.2 attendance and coordination provisions for specialist works let by the employer = sum of provisional amounts for employer-let specialist works x rate) + 3.5 quality works addition + 3.6 smart site addition; 4 pre-tax project cost = 1 + 2 + 3; 5 VAT = 4 x VAT rate; 6 unit works cost = 4 + 5.
Hubei 2024, '4. unit works cost calculation program': 1 element works and unit-rate preliminaries cost (with labour cost and plant and small tools cost shown in 'of which' lines) + 2 lump-sum preliminaries cost + 3 other items cost = 4 construction cost excluding tax (1 + 2 + 3); 5 VAT = 4 x rate; 6 construction cost including tax = 4 + 5. This program carries no statutory levies line. Hubei Annex 4, 'construction and installation pricing program (tender price ceiling)', is a different set: 1 element works cost + 2 preliminaries cost (mandatory HSE provisions shown in 'of which') + 3 other items cost (provisional sums, provisional prices for specialist works, dayworks, main contractor's attendance and coordination provisions) + 4 statutory levies and fees + 5 taxes and duties (deducting the amounts of engineering equipment outside the scope of taxation) = (1 + 2 + 3 + 4) x the prescribed rate; total = 1 + 2 + 3 + 4 + 5. That table keeps the separate 'statutory levies and fees' line, a trace of the 2013 BOQ pricing (five-part composition); when used for a tender price ceiling it must be distinguished from the provincial fee quota program to avoid double-charging statutory levies.
III. Sector basis comparison
Highway JTG 3830-2018 'compilation rules for estimates and budgets of highway construction projects', notes on completing form 08: (1) amount = sum over labour, materials and plant of unit price x quota x quantity; (2) preliminaries and overheads follow the sum of quota labour cost and quota plant cost of the relevant items, or quota direct cost x the prescribed percentage rate; (3) statutory levies follow labour cost of the relevant items x the prescribed rate; (4) profit follows (quota direct cost + preliminaries + overheads) x profit rate; (5) taxes and duties follow (direct cost + preliminaries + overheads + statutory levies + profit) x rate; (6) the calculation base of each cost is entered in the quota column and the rate in the quantity column. The highway profit base includes preliminaries and overheads - entirely different from the building formula '(labour + plant) x rate'. Railway TB 10801-2024 table 2.6.2, calculation program for the individual estimate (budget) of construction and installation works: 1 base-period labour cost / 2 base-period material cost / 3 base-period plant and small tools cost -> 4 quota direct works cost = (1) + (2) + (3) -> 5 freight and handling charges outside the price -> 6 to 8 labour cost differential, material cost differential, plant and small tools cost differential -> 9 differential subtotal = (6) + (7) + (8) -> 10 filling material cost -> 11 direct works cost = (4) + (5) + (9) + (10) -> 12 construction preliminaries = [(1) + (3)] x construction preliminaries rate -> 13 special construction additions (base: the compilation-period labour cost and compilation-period plant and small tools cost of the relevant items) -> 14 direct cost = (11) + (12) + (13) -> 15 on-costs = [(1) + (3)] x on-costs rate -> 16 individual estimate (budget) value = (14) + (15). Railway on-costs already absorb the management-type and statutory-levy-type costs; the individual program stops at 'direct cost + on-costs', with VAT listed separately in the static investment composition above it (see the section 2.6 cost composition diagram) - a hierarchy different from the building 'unit works cost = pre-tax cost + VAT'. The equipment individual estimate (budget) follows table 2.6.3: equipment freight and handling = (1) x freight and handling rate; individual estimate (budget) value = (1) + (2).
IV. Four questions for reading the table (fixed order when checking a program)
- Base: is the base of overheads / profit (labour cost + plant and small tools cost), labour cost or direct cost; on the quota basis always quota labour cost / quota plant cost, not compilation-period market prices.
- Risk cost: is it an explicit separate line (Hubei separates it; Shaanxi leaves it inside the rates), and is there duplication with the contract risk band clause.
- Statutory levies / social security: inside the unit rate (Shaanxi construction workers' social security) or listed separately at project level (the 'statutory levies' line of Hubei Annex 4) - mixing the two causes duplication or omission.
- VAT: is the base the pre-tax cost (1 + 2 + 3); are the amounts of engineering equipment outside the scope of taxation deducted; are provisional prices for specialist works already containing VAT deducted.
Applicability Boundaries
- Table numbers and formulas change with provincial editions: Shaanxi uses the 2025 fee rules, Hubei the 2024 fee quota norms; rates and bases must not be carried across provinces in tendering - use the current edition of the province where the project sits.
- Railway 'on-costs' is a composite concept (covering overheads and statutory-levy-type costs) and cannot be aligned item by item with building 'on-costs'; highway form 08 is an estimate/budget schedule basis and its line sequence must not be swapped with BOQ pricing tables.
- Several programs may coexist within one province (e.g. Hubei 'II. calculation program' and 'Annex 4 tender price ceiling program'); choose the right table by the type of deliverable (estimate/budget, tender price ceiling, tender).
Further Reading
- Shaanxi 2025 'Shaanxi construction works fee rules': table 5-1 tendering-stage pricing schedule; table 5-2 all-in unit rate schedule on the labour-plus-plant base; table 5-3 all-in unit rate schedule on the labour base.
- Hubei 'construction and installation works fee quota norms' (2024): 'II. calculation program' item 1 (all-in unit rate program for element works and unit-rate preliminaries) and item 4 (unit works cost program); Annex 4 construction and installation pricing program (tender price ceiling program for the employer).
- JTG 3830-2018 'compilation rules for estimates and budgets of highway construction projects', notes on completing form 08.
- TB 10801-2024 'compilation rules for design estimates (budgets) of railway capital construction projects', section 2.6 cost composition and individual estimate (budget) calculation program (composition diagram, tables 2.6.2 and 2.6.3).
- For the fee boundary against the BOQ basis see GB 50500-2013 clauses 1.0.3, 2.0.8, 3.1.4 and GB/T 50500-2024 clauses 2.0.9, 3.1.6, 3.2.11.