Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Overheads (company and site) within the all-in unit rate vs. site management fee within lump-sum preliminaries: distinction and prevention of duplicate charging

Overheads (company and site) are on-costs (indirect costs) in nature and enter the all-in unit rate (labour cost + materials cost + plant and small tools cost + overheads (company and site) + profit + agreed risk, excluding value added tax (VAT)), and are settled with the quantities; the legacy 'site management fee' belonged to preliminaries and was lump-summed per item. Since Jian Biao [2003] No. 206, the site management fee has been merged into overheads (company and site), and most provinces no longer list it separately within lump-sum preliminaries; the same management outlay can be charged only once — in preparation and audit review, check that the local quota norm percentage rate basis and the item listing are consistent with each other.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 50875-2013 工程造价术语标准
  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
  • 建标〔2003〕206号 建筑安装工程费用项目组成

Topic Positioning

Distinguishes the site management fee within lump-sum preliminaries from the overheads (company and site) within the all-in unit rate — the core is preventing duplicate charging of the same management outlay.

Core Conclusions

Overheads (company and site) are the expense of the construction enterprise in organizing construction production and business management (on-costs (indirect costs) in nature, GB/T 50875-2013 §2.2.20); they enter the all-in unit rate (labour cost + materials cost + plant and small tools cost + overheads (company and site) + profit + agreed risk, excluding value added tax (VAT), GB/T 50500-2024 §2.0.9) and are settled with the quantities; under the railway scope, on-costs (indirect costs) = overheads (company and site) + profit (TB 10801-2024 §3.9), charged as (base-period labour cost + base-period plant and small tools cost) × percentage rate. The site management fee was part of the former 'on-site expenditure' (temporary works and site establishment costs + site management fee) and belonged to preliminaries; after Jian Biao [2003] No. 206, temporary works and site establishment costs were merged into mandatory health, safety and environmental (HSE) provisions and the site management fee merged into overheads (company and site); most provinces (Hubei 2024, Shaanxi 2025) no longer list it separately within lump-sum preliminaries; the few provinces that still list it have correspondingly reduced their overheads percentage rates — the same outlay can be charged only once.

Applicable Boundaries

A general-scope distinction that does not replace current provincial quota norm percentage rates and item listings; the 'on-site expenditure' scope of the legacy highway method (Jiao Gong Lu Fa [1996] No. 611) is historical and must not be carried over; mandatory health, safety and environmental (HSE) provisions (called statutory work safety levy (earmarked funds) on railways) are non-competitive, and temporary works and site establishment expenditure must not be listed duplicatively under overheads.

Further Reading

GB/T 50500-2024 §2.0.9; GB/T 50875-2013 §2.2.20; TB 10801-2024 §3.9; Jian Biao [2003] No. 206; Hubei 2024 norms for on-costs and expenses; Shaanxi 2025 on-cost and expense rules, Table 7-1.

Keywords

Cited By