Highway works JTG 3830-2018 composition of overheads (company and site): the five items — basic fee, staple and non-staple food freight subsidy, staff home-visit travel expenses, staff heating subsidy and financial costs — and the bases to which percentage rates are applied (clause 3.1.7)
JTG 3830-2018 clause 3.1.7: highway overheads (company and site) comprise basic fee, staple and non-staple food freight subsidy, staff home-visit travel expenses, staff heating subsidy and financial costs. The basic fee is calculated on the sum of (norm-based labour cost + norm-based construction plant and machinery cost) at the percentage rates in Table 3.1.7-1; the other four are each calculated on the norm-based direct cost of the respective works category at the percentage rates in Tables 3.1.7-2~3.1.7-5 (the heating subsidy by the temperature zone of the works location; see Appendix D). Composite mileage for the food subsidy = grain haul distance x 0.06 + fuel haul distance x 0.09 + vegetable haul distance x 0.15 + water haul distance x 0.70; for works with a composite mileage within 3 km, the fee is calculated as 3 km.
Applicable Codes
- JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.7条、第3.1.6条、App. D
Topic Positioning
This card covers the composition of overheads (company and site) under clause 3.1.7 of JTG 3830-2018 Administrative Compilation Rules for Estimates and Budgets of Highway Works — the definitions, bases to which percentage rates are applied and percentage rate table numbers of the five items — for the compilation and review of highway estimates and budgets and for checking the fee bases used in cost software.
Core Conclusions
JTG 3830-2018 clause 3.1.7: overheads (company and site) comprise basic fee, staple and non-staple food freight subsidy, staff home-visit travel expenses, staff heating subsidy and financial costs. Definitions and rules:
Basic fee: costs incurred by contractors in organising construction production and business management. Calculated on the sum of norm-based labour cost and norm-based construction plant and machinery cost of each works category at the percentage rates in Table 3.1.7-1 (rates by works category).
Staple and non-staple food freight subsidy: the additional cost of purchasing daily necessities for field construction far from towns and villages. Calculated on the norm-based direct cost of each works category at the percentage rates in Table 3.1.7-2. Composite mileage = grain haul distance x 0.06 + fuel haul distance x 0.09 + vegetable haul distance x 0.15 + water haul distance x 0.70; the haul distances for grain, fuel, vegetables and water are all whole-line average haul distances; where the composite mileage falls between the mileages listed in the table, the percentage rate may be interpolated; for works with a composite mileage within 3 km, this item is calculated as 3 km.
Staff home-visit travel expenses: round-trip transport and en-route accommodation incurred by staff during home visits and paid in accordance with the relevant provisions. Calculated on the norm-based direct cost of each works category at the percentage rates in Table 3.1.7-3.
Staff heating subsidy: winter heating allowances paid to staff in accordance with the provisions and the cost of temporary heating facilities provided for staff at the construction site. Calculated on the norm-based direct cost of each works category at the percentage rates in Table 3.1.7-4, selected by the temperature zone of the works location (see Appendix D of the rules).
Financial costs: costs incurred by the contractor in raising funds and providing bid, advance-payment, performance and wage-payment guarantees, including net short-term loan interest expense, net exchange losses, foreign-exchange adjustment fees, financial-institution fees and other financial costs incurred in raising funds. Calculated on the norm-based direct cost of each works category at the percentage rates in Table 3.1.7-5.
Key charging points: of the five items, only the basic fee uses the sum of (norm-based labour cost + norm-based construction plant and machinery cost) as the base to which percentage rates are applied; the other four use norm-based direct cost; on this basis, Form 08 books overheads (company and site) together with preliminaries, statutory levies and fees and profit.
Applicable Boundaries
- Applies to the calculation of overheads (company and site) at the preliminary estimate and budget compilation stages of highway works; the percentage rate tables are banded by works category (earthwork, rockwork, haulage, Structures I/II/III, etc.) — during compilation, look up by works category and mileage/temperature zone.
- Overheads (company and site) are on-costs (indirect costs) in nature and are included in all-in unit rates; distinguish them from the old site management fee (a lump-sum preliminary item) — since Jian Biao [2003] No. 206, site management fees have been merged into overheads (company and site); avoid double counting in compilation/review.
- Do not confuse adjacent items: the works-transfer fee (clause 3.1.6, a preliminary item, calculated on the sum of norm-based labour cost and norm-based construction plant and machinery cost at the percentage rates in Table 3.1.6-9; for expressways/first-class highways and standalone major bridges/tunnels, the transfer distance is measured from the provincial-capital city to the site) and auxiliary production on-costs (indirect costs) (calculated at 3% of norm-based labour cost and included in material budget unit rates as material cost) are not among the five components of overheads (company and site) and must not be misclassified.
Further Reading
- Source provisions: JTG 3830-2018 Administrative Compilation Rules for Estimates and Budgets of Highway Works, clause 3.1.7 (the five components of overheads (company and site) and their charging rules); percentage rate Tables 3.1.7-1 to 3.1.7-5; Appendix D (temperature zone classification, used to select the percentage rate for the staff heating subsidy); clause 3.1.6 works-transfer fee and auxiliary production on-costs (for contrast).
- Higher-level framework: the eight-item composition of construction cost under clause 3.1.1 of the same rules (direct costs, permanent equipment procurement cost, preliminaries, overheads (company and site), statutory levies and fees, profit, taxes and duties (VAT under the current standard), special costs) and the rule on separation of net price and VAT; in Form 08, preliminaries, overheads (company and site), statutory levies and fees and profit are booked at the sum of (norm-based labour cost + norm-based construction plant and machinery cost) or norm-based direct cost x the prescribed percentage rate.
- Extension: distinction between overheads (company and site) and site management fees and prevention of double counting (Jian Biao [2003] No. 206 basis).
Keywords
- overheads (company and site)
- JTG 3830-2018
- compilation rules for highway estimates and budgets (JTG 3830)
- 基本费用
- 主副食运费补贴
- 职工探亲路费
- 职工取暖补贴
- 财务费用
- 综合里程
- norm-based direct cost